Prepare a gantt chart for the stock control project:

Scenario

Lucas-TVS is the Leader in Auto Electricals in India today with 50 years experience in design and manufacturing. 4 out of 5 vehicles rolled out daily are fitted with Lucas-TVS products. The company has manufacturing units with fully integrated state-of-the-art technology that includes most advanced design, production, quality, testing and  R& D facilities. You are appointed as Graduate Engineer Trainee. You will be working with different departments of the company and the concerned department managers will test your analytical knowledge and techniques to carry out managerial tasks.

 

 

TASK 1

The company is planning to conduct a large international motor sports rally due to take place in four years time. A significant portion of the project will be provision of new building & facilities.  Major new works associated with the project include the construction of a 30,000 seat outdoor stadium with car racing tracks & a world press & media centre. A further consideration is the upgrade of the current transport network, with major development work required on the local metro rail system between the main stadium & the city centre & an airport bus link.

Success will be measured in terms of trouble free performance of the events, level of customer enthusiasm & satisfaction & sustained economic activity generated in the region.  Completion of the project on time is critical even if costs are adversely affected.

The major software development aspect of the project is the development of communication software in the form of an information database. This will require development of a dedicated website to give public access to event information. The database will contain information about competitors & their events, time & location & availability of tickets. The database will be designed to allow the general public to monitor the events, order tickets for any event  & purchase merchandise. The website will also contain links to local hotels & restaurant facilities.

The project can be broken down into following areas of work :

 

Activity

Activity Description

Preceding Activity


Duration in Weeks

 

A

Obtain financing & sponsorship negotiation

-


22

 

B

Sporting facilities

-


52

 

C

Analysis & design of communications software

A


14

 

D

 Construct media facilities

B,C


16

 

E

Program Communications system

C


26

 

F

Install communications software & telecommunications hardware

D.E


6

 

G

Transport network update & construct participants accommodation

-


40

 

H

Security arrangements & checks

G,F


12

 

I

Public Relations / Advertising / Marketing

F


10

 

J

Human Resources & Volunteers

I


12

 

K

Trial Events, media systems & contingency

H,J


6

 

L

Events (including the opening and closing ceremonies)

K


2

 

 

Each of the above activities is carried out by individual specialist project teams & is led by a  Project Team Manager. It is critical that these events are coordinated & planned effectively, as timing is critical to the success of this project. One of the key tasks to undertake immediately is the determination of the critical path.

You have been asked by your management to prepare a report which includes :

(a)    An explanation of the importance of undertaking critical path analysis for a project such as this.

(b)   A critical path analysis for the project , clearly identifying :

(i)   The critical path activities & the critical duration of the project.

(ii)  The Earliest Event Time for each activity (EET).

(iii) The Latest Event Time for each activity (LET)

(c)    A calculation of the slack time on activity H and an explanation of how this information may assist decision making during this project.

(d)   How using project management software may assist during this project.

 

 

 

TASK 2

 

The company has planned to purchase hardware & develop an in house  software to run a completely new stock control system & a website allowing access to the stock database. The design stage has been completed & the project is progressing through the implementation stage, but is falling behind schedule. The following is the schedule of events for the 16 week implementation phase of the project :

 

Planned :

Task

Planned Start

Planned Duration

Write Programmes

Start of Week 1

8

Purchase & Install hardware

Start of Week 1

5

Create databases

Start of Week 6

4.5

Convert Existing Files

Start of Week 9

2.5

Test Programs

Start of Week 6

3

Test System

Middle of Week 11

2.5

Select & Train personnel

Start of Week 8

5

Cutover

Start of Week 14

3

 

Actual :

Write Programmes

Start of Week 1

9

Purchase & Install hardware

Start of Week 1

6

Create databases

Start of Week 7

4

Convert Existing Files

Middle of Week 10

1.5 ( Continuing)

Test Programs

Start of Week 7

5 ( Continuing)

Test System

Not Started

 

Select & Train personnel

Start of Week 8

4 ( Continuing)

Cutover

Not Started

 

 

Current date is start of week 12.

Required  

(a)    Prepare a Gantt chart for the stock control Project

(b)   Explain the purpose of a Gantt chart & interpret the information shown on the chart prepared for the project.

 

 

TASK 3

The company is planning to develop an in house  software to run a completely new stock control system & a website allowing access to the stock database as indicated in task 2. At the planning stage you are required to prepare a Work Break down structure giving activities & costs.

 

 

 

 

DBMS, Programming

  • Category:- DBMS
  • Reference No.:- M9521394

Have any Question?


Related Questions in DBMS

Data mining assignment -in this assignment you are asked to

Data Mining Assignment - In this assignment you are asked to explore the use of neural networks for classification and numeric prediction. You are also asked to carry out a data mining investigation on a real-world data ...

Sql query assignment -for this assignment you are to write

SQL Query Assignment - For this assignment you are to write your answers in a word document. This assignment is in three parts: Part A (reporting queries), Part B (query performance), Part C (query design). For this assi ...

The groceries datasetimagine 10000 receipts sitting on your

The groceries Dataset Imagine 10000 receipts sitting on your table. Each receipt represents a transaction with items that were purchased. The receipt is a representation of stuff that went into a customer's basket. That ...

You are in a real estate business renting apartments to

You are in a real estate business renting apartments to customers. Your job is to define an appropriate schema using SQL DDL in MySQL. The relations are Property(Id, Address, NumberOfUnits), Unit(ApartmentNumber, Propert ...

Objectivethe objective of this lab is to be familiar with a

OBJECTIVE: The objective of this lab is to be familiar with a process in big data modeling. You're required to produce three big data models using the MS PowerPoint software. This tool is available on UMUC Virtual Deskto ...

The relation memberstudentid organizationid roleid stores

The relation Member(StudentId, OrganizationId, RoleId) stores the membership information of student joining organization. For example, ('S1', 'O2', 'R3') indicates that student with Id 'S1' joined the organization with i ...

Relational database exerciseyou have been assigned to a new

Relational Database Exercise: You have been assigned to a new development team. A client is requesting a relational database system to manage their present store with the anticipation of adding more stores in the future. ...

Relational database design a given the following business

Relational Database Design A) Given the following business rules, identify entity types, attributes (at least two attributes for each entity, including the primary key) and relationships, and then draw an Entity-Relation ...

We can represent a data set as a collection of object nodes

We can represent a data set as a collection of object nodes and a collection of attribute nodes, where there is a link between each object and each attribute, and where the weight of that link is the value of the object ...

Data model development and implementationpurpose of the

Data model development and implementation Purpose of the assessment (with ULO Mapping) The purpose of this assignment is to develop data models and map Database System into a standard development environment to gain unde ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As