Cost and Quality

This assignment is a continuation and enhancement of Assignment 2.

Create a Work Breakdown Structure (WBS), and assign resources and cost by using a project management tool. As the IT project manager, you have been assigned a project to deploy ten (10) wireless access points in your company's warehouse and break room within the next ninety (90) days. You are free to make assumptions that satisfy the scope of the project such as training, wiring, consulting efforts, etc.

Your submission will be made in .mpp format and will be graded on the accuracy of your work package assumptions and duration estimates.

In your assignment, address the following:
1. Create 15 or more decomposed work packages into 4 levels that are assigned to 5 or more main tasks (75 line items).
2. Ensure the main WBS tasks headings are the 5 PMBOK® process areas.
3. Create a Work Breakdown Structure Code for each task.
4. Determine an overall project duration and duration estimates for each of the tasks. The duration is not to exceed 90 days.
5. Create accurate work package assumptions and duration estimates.
6. Include 7 resources assigned in the Resource Sheet as "Work" types and 3 resources assigned as "Material" types.
7. Ensure the Resources are paid no more than $30/hour and that the "Material" cost per use will not exceed $50.
8. Include your resources and materials from the Resource Sheet in the task sheet.
9. Create 10 dependencies in the Task Sheet.

Your assignment must follow these formatting requirements:
• Microsoft Project or its open source alternative in .mpp format.

The specific course learning outcomes associated with this assignment are:
• Describe the knowledge and processes areas of project management in accordance to the Project Management Institute Project Management Body of Knowledge (PMBOK®) Guide.
• Evaluate the different cost management factors in an IT project management context.
• Use technology and information resources to research issues in IT project management.
• Write clearly and concisely about issues in IT project management using proper writing mechanics and technical style conventions.

Grading for this assignment will be based on answer quality, logic / organization of the paper, and language and writing skills, using the following rubric.

 

Assignment 3: Cost and Quality

Criteria

Unacceptable

Below 70% F

Fair

70-79% C

Proficient

80-89% B

Exemplary

90-100% A

1. Create 15 or more decomposed work packages into 4 levels that are assigned to 5 or more main tasks (75 line items).

Weight: 10%

Did not submit or incompletely created 15 or more decomposed work packages into 4 levels that are assigned to 5 or more main tasks (75 line items).

Partially created 15 or more decomposed work packages into 4 levels that are assigned to 5 or more main tasks (75 line items).

Satisfactorily created 15 or more decomposed work packages into 4 levels that are assigned to 5 or more main tasks (75 line items).

Thoroughly created 15 or more decomposed work packages into 4 levels that are assigned to 5 or more main tasks (75 line items).

2. Ensure the main WBS tasks headings are the 5 PMBOK® process areas.

Weight: 10%

Did not submit or incompletely ensured the main WBS tasks headings are the 5 PMBOK® process areas.

Partially ensured the main WBS tasks headings are the 5 PMBOK® process areas.

Satisfactorily ensured the main WBS tasks headings are the 5 PMBOK® process areas.

Thoroughly ensured the main WBS tasks headings are the 5 PMBOK® process areas.

3. Create a Work Breakdown Structure Code for each task.

Weight: 10%

Did not submit or incompletely created a Work Breakdown Structure Code for each task.

Partially created a Work Breakdown Structure Code for each task.

Satisfactorily created a Work Breakdown Structure Code for each task.

Thoroughly created a Work Breakdown Structure Code for each task.

4. Determine an overall project duration and duration estimates for each of the tasks. The duration is not to exceed 90 days.

Weight: 10%

Did not submit or incompletely determined an overall project duration and duration estimates for each of the tasks. The duration is not to exceed 90 days.

Partially determined an overall project duration and duration estimates for each of the tasks. The duration is not to exceed 90 days.

Satisfactorily determined an overall project duration and duration estimates for each of the tasks. The duration is not to exceed 90 days.

Thoroughly determined an overall project duration and duration estimates for each of the tasks. The duration is not to exceed 90 days.

5. Create accurate work package assumptions and duration estimates.

Weight: 10%

Did not submit or incompletely created accurate work package assumptions and duration estimates.

Partially created accurate work package assumptions and duration estimates.

Satisfactorily created accurate work package assumptions and duration estimates.

Thoroughly created accurate work package assumptions and duration estimates.

6. Include 7 resources assigned in the Resource Sheet as "Work" types and 3 resources assigned as "Material" types.

Weight: 15%

 

Did not submit or incompletely included 7 resources assigned in the Resource Sheet as "Work" types and 3 resources assigned as "Material" types.

Partially included 7 resources assigned in the Resource Sheet as "Work" types and 3 resources assigned as "Material" types.

Satisfactorily included 7 resources assigned in the Resource Sheet as "Work" types and 3 resources assigned as "Material" types.

Thoroughly included 7 resources assigned in the Resource Sheet as "Work" types and 3 resources assigned as "Material" types.

7. Ensure the Resources are paid no more than $30/hour and that the "Material" cost per use will not exceed $50.

Weight: 15%

Did not submit or incompletely ensured the Resources are paid no more than $30/hour and that the "Material" cost per use will not exceed $50.

Partially ensured the Resources are paid no more than $30/hour and that the "Material" cost per use will not exceed $50.

Satisfactorily ensured the Resources are paid no more than $30/hour and that the " Material" cost per use will not exceed $50.

Thoroughly ensured the Resources are paid no more than $30/hour and that the " Material" cost per use will not exceed $50.

8. Include your resources and materials from the Resource Sheet in the task sheet.

Weight: 15%

 

Did not submit or incompletely included your resources and materials from the Resource Sheet in the task sheet.

Partially included your resources and materials from the Resource Sheet in the task sheet.

Satisfactorily included your resources and materials from the Resource Sheet in the task sheet.

Thoroughly included your resources and materials from the Resource Sheet in the task sheet.

9. Create 10 dependencies in the Task Sheet.

Weight: 5%

Did not submit or incompletely created 1-5 dependencies in the Task Sheet.

Partially created 6-8 dependencies in the Task Sheet.

Satisfactorily created 8 -9 dependencies in the Task Sheet.

Thoroughly created 10 dependencies in the Task Sheet.

Programming Language, Programming

  • Category:- Programming Language
  • Reference No.:- M9891350
  • Price:- $50

Priced at Now at $50, Verified Solution

Have any Question?


Related Questions in Programming Language

Assignment - horse race meetingthe assignment will assess

Assignment - Horse Race Meeting The Assignment will assess competencies for ICTPRG524 Develop high level object-oriented class specifications. Summary The assignment is to design the classes that are necessary for the ad ...

Php amp session managment assignment -this assignment looks

PHP & SESSION MANAGMENT ASSIGNMENT - This assignment looks at using PHP for creating cookies and session management. Class Exercise - Web Project: Member Registration/Login This exercise will cover adding data connectivi ...

Assignment task -q1 a the fibonacci numbers are the numbers

Assignment Task - Q1. (a) The Fibonacci numbers are the numbers in the following integer sequence, called the Fibonacci sequence, and are characterised by the fact that every number after the first two is the sum of the ...

Assignment - horse race meetingthe assignment will assess

Assignment - Horse Race Meeting The Assignment will assess competencies for ICTPRG524 Develop high level object-oriented class specifications. Summary The assignment is to design the classes that are necessary for the ad ...

Assignmentquestion onegiving the following code snippet

Assignment Question One Giving the following code snippet. What kind of errors you will get and how can you correct it. A. public class HelloJava { public static void main(String args[]) { int x=10; int y=2; System.out.p ...

Task - hand execution of arraysoverviewin this task you

Task - Hand Execution of Arrays Overview In this task you will demonstrate how arrays work by hand executing a number of small code snippets. Instructions Watch the Hand Execution with Arrays video, this shows how to ste ...

Task silly name testeroverviewcontrol flow allows us to

Task: Silly Name Tester Overview Control flow allows us to alter the order in which our programs execute. Building on our knowledge of variables, we can now use control flow to create programs that perform more than just ...

Assignment - proposal literature review research method1

Assignment - Proposal, Literature Review, Research Method 1. Abstract - Summary of the knowledge gap: problems of the existing research - Aim of the research, summary of what this project is to achieve - Summary of the a ...

Structs and enumsoverviewin this task you will create a

Structs and Enums Overview In this task you will create a knight database to help Camelot keep track of all of their knights. Instructions Lets get started. 1. What the topic 5 videos, these will guide you through buildi ...

Assignment - haskell program for regular expression

Assignment - Haskell Program for Regular Expression Matching Your assignment is to modify the slowgrep.hs Haskell program presented in class and the online notes, according to the instructions below. You may carry out th ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As