1. General Foundry, Inc., a metal works plant in Milwaukee, has long been trying to avoid the expense of installing air pollution control equipment. The local environment protection group has recently given the foundry 16 weeks to install a complex air filter system on its main smokestack. General Foundry has been warned that it may be forced to close unless the device installed in the allotted period. Lester Harky, the managing partner, wants to make sure that installation of the filtering system progressed smoothly and on time.
General Foundry has identified the following eight activities that need to be performed and their sequential relationship.

Activity

Description

Time

(weeks)

Immediate

Predecessors

A

Build internal components

2

--

B

Modify roof and floor

4

--

C

Construct collection stack

2

A

D

Pour concrete and install frame

4

A, B

E

Build high-temperature burner

4

C

F

Install pollution control system

3

C

G

Install air pollution device

5

D, E

H

Inspect and test

2

F, G

a. Construct the appropriate network diagram.

b. Which jobs can be delayed without delaying the project completion time?

c. Can General Foundry complete the project on time? Why or why not?

d. Suppose Lester wants to shorten the completion time and his options are:

(1) Reduce activity D by one week, which costs $700/week;
(2) Reduce activity E by one week, which costs $800/week;
(3) Reduce activity G by one week, which costs $1000/week;

If General Foundry will save $2000 for each week that the earliest completion time is reduced, which single option, if any, should Lester choose?

2. The following table represents a plan for a project:

 

Time Estimates (days)

Job No.

Predecessor Job(s)

Optimistic

Most likely

Pessimistic

A

-

1

2

3

B

-

2

3

4

C

A

4

5

6

D

B

8

9

10

E

C, D

2

5

8

F

D

4

5

6

G

E

1

2

3

a. Construct the appropriate network diagram.

b. What is the critical path?

c. What is the expected completion time for the project and what is the variance of project completion time?

d. Is the probability that the project will take less than 18 days to complete larger than 50% or smaller than 50%?

Computer Network & Security, Computer Science

  • Category:- Computer Network & Security
  • Reference No.:- M91647263
  • Price:- $40

Priced at Now at $40, Verified Solution

Have any Question?


Related Questions in Computer Network & Security

Security challenges in emerging networksassignment

Security Challenges in Emerging Networks Assignment Description The purpose of this assignment is to develop skills to independently think of innovation. In this assignment students will first learn how to develop knowle ...

Security challenges in emerging networksassignment

Security Challenges in Emerging Networks Assignment Description The purpose of this assignment is to develop skills to independently think of innovation. In this assignment students will first learn how to develop knowle ...

Security challenges in emerging networksassignment

Security Challenges in Emerging Networks Assignment Description The purpose of this assignment is to develop skills to independently think of innovation. In this assignment students will first learn how to develop knowle ...

Security challenges in emerging networksassignment

Security Challenges in Emerging Networks Assignment Description The purpose of this assignment is to develop skills to independently think of innovation. In this assignment students will first learn how to develop knowle ...

Advanced network design assessment - human factors in

Advanced Network Design Assessment - Human factors in network analysis and design Purpose of the assessment - This assignment is designed to assess students' knowledge and skills related to the following learning outcome ...

Advanced network design assessment - human factors in

Advanced Network Design Assessment - Human factors in network analysis and design Purpose of the assessment - This assignment is designed to assess students' knowledge and skills related to the following learning outcome ...

Assignment descriptionproject scope a typical network

Assignment Description Project Scope: A typical network layout diagram of a firm is given below for illustrative purposes only. The service requirements are enclosed. Figure. Network layout of a firm Service requirements ...

Assignment descriptionproject scope a typical network

Assignment Description Project Scope: A typical network layout diagram of a firm is given below for illustrative purposes only. The service requirements are enclosed. Figure. Network layout of a firm Service requirements ...

After reading this weeks materials please respond to two 2

After reading this week's materials, please respond to TWO (2) of the following questions. AND PROVIDE CITATION IN APA 1. Describe the differences between bus, ring, star and mesh topologies. 2. Explain the TCP/IP Model ...

The abstract should not be more than 250 words describe

The abstract should not be more than 250 words. Describe your project, focusing on research questions and research method for next stage of the project. 1. Introduction [The introduction should describe what the project ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As