a pulverized coal steam power unit is designed to operate as a baseload plant. the capital cost of the plant is $1400/kW. the fixed charge rate is $0.16/year. the plant will require 9700 btu/kWh, and coal will cost $1.50/Mbtu. o&m cost will be $0.43/kwh. if the plant operates at a capacity factor of 0.913, how many hours does it operate each year? What annual revenue is required to cover fixed costs? What will be the annual variable costs? How much will electricity cost per kWh?