Using the project given below and you are required to assess the changes to the works listed and present them in a priced variations account and a short (maximum 1500 words) report. The account is to follow contract administration conventions and the report is to cover the following points:

1. The project parameters -

Project Scope, project Risk, meaning of terms, nature of the contract and role of the parties.

2. The technology involved in each issue.

3. The source of prices for omissions and additions to the work. Current prices, for both omissions and additions, are to be obtained, either from industry or a suitable price book. Each price is to have a source of pricing noted.

4. What the financial effect would be to the Employer if the change is made late

a) So that it delays subsequent work

b) So that any substituted work has already been carried out

5. Prepare an additional detail claim in order to adjust the cost overrun. For example, under the part "d" instead of timber trusses client prefers steel trusses. It causes massive impact on rates whereas the provided BoQ doesn't have such items. In such cases you need to provide a new rate along with a specific rate analysis (breakdown). You shall take any necessary assumptions

PROJECT No 1

Project

Refurbishment, alterations, extensions and redecoration of the

 

exterior and common parts of an Apartment.

 

You are acting as the contract administrator.

 

 

Estimated cost

£40 500.00 plus VAT

Projected duration

15 Weeks

Documents

Bills of Quantities incorporating Preliminaries, Preambles and

 

Measured Work (for valuing variations).

 

 

Contract to be used

JCT Standard Form of Building Contract SBC/Q.

Damages for non-

£250.00 per week

completion

 

Public liability insurance

£1 000 000.00

Insurance of the works

6.3 Applies - Employer is to insure.

a) Change wall tiling from 150 x 150 glazed ceramic tiles (Supply provisional sum of £10.00/m2) to 100 x 100 glazed ceramic tiles (Supply price of £8.75/m2)

Item

Quantity

 

 

Omit 150 x 150 tiles

150m2

Add 100 x 100 tiles

150m2

Add rounded edge top tile

45m

b) Provide new stud partition between WC and Bathroom consisting of plasterboard and three coats of emulsion paint to each side, 75 x 100 timber studding at 400 centres, head and sole member. Demolish and remove existing 100mm blockwork partition and plaster finish.

Item

Quantity

 

 

Demolish partition

55m2

Plasterboard and skim coat plaster

105m2

Emulsion

105m2

Timber studding

42m

c) Change roof tiling from interlocking tiles (Redland Regent 2) to plain concrete tiles (Redland Plain Tile)

Item

Quantity

 

 

Omit interlocking roof tiles

455m2

Add plain roof tiles

455m2

Add double course of tiles at eaves

73m

d) Change roof trusses, timber to steel. Overall Roof span area is 180 m2

Item

Quantity

 

 

Omit Roof truss type T1; spanning 10400mm wide x 2600mm high, consisting of 50 x 150mm wooden members, bolted to 50 x 150mm wood splice as per detail drawings. Rates shall include for painting of wood preservatives as specified

8 Nrs

Omit supplying & fixing of wood purlins, 50mm x 100m: nailed or screwed to roof trusses ( measured separately)at 700mm centres: complete with all the required preservative paint works and all necessary

56 m

Add Roof truss type T1; spanning 10400mm wide x 2600mm high, consisting of  80x60x6mm (double bottom member) structural rectangular tube members welded to gusset plate-all as per detail drawing; Rate shall include for painting as specified.

6 Nr

Add Supplying & fixing of  Zed purlins, 100 x 50 x 2mm: welded to roof trusses(measured separately )at 850mm centres: complete with all the required paint works and all necessary supports

Civil Engineering, Engineering

  • Category:- Civil Engineering
  • Reference No.:- M91609109

Have any Question?


Related Questions in Civil Engineering

Task details the client is doing masters in civil

Task Details: The client is doing Masters in Civil Engineering. He needs a Technical Paper on Earthquake pertaining to Geology and Rock Mechanics. There should be a through discussion of Earthquake in relation to the men ...

Assessment taskpractical investigationinstructions- it is

Assessment Task Practical Investigation Instructions: - It is very important that you read these instructions. - The hardcopy of the Assignment report, with the Assignment cover sheet, should be submitted to the Assignme ...

Aimthis assignment aims to demonstrate the structural

Aim: This assignment aims to demonstrate the structural design requirements of a glazed façade in a multi-storey building. Among other requirements, the glazed façade is required to comply with Australian Standard AS 204 ...

The drainage system of a cantilever wall shown in below

The drainage system of a cantilever wall shown in below figure, became blocked after a heavy rainstorm and the groundwater level, which was originallybelow the base, rose to1.5 (m) below the surface. Determine the stabil ...

Masonry design assignmentquestion 1 - derivation of seismic

MASONRY DESIGN ASSIGNMENT Question 1 - Derivation of seismic actions on building a) Determine the storey seismic weights (Wi) for each suspended level of the building, hence the seismic weight (Wt) of the entire building ...

Assignmenta continuous three spans beam with

Assignment A continuous three spans beam with centre-to-centre distance of 6 m supports 150 mm thick one-way slabs as shown below. The beams have clear spans of 8 m, 9 m, and 8 (face-to-face of 400 mm square columns). Th ...

Civilyou are provided with bill of quantities prepared

Civil You are provided with bill of quantities prepared separately, priced and submitted by 3 con- tractors (A,B,C found on LMS) in respect of a proposed project (see appendix for drawings). The site is located on Mt. Al ...

Masonry design assignmentquestion 1 - derivation of seismic

MASONRY DESIGN ASSIGNMENT Question 1 - Derivation of seismic actions on building a) Determine the storey seismic weights (Wi) for each suspended level of the building, hence the seismic weight (Wt) of the entire building ...

Aimthis assignment aims to demonstrate the structural

Aim: This assignment aims to demonstrate the structural design requirements of a glazed façade in a multi-storey building. Among other requirements, the glazed façade is required to comply with Australian Standard AS 204 ...

1 aimthe assignment aims to develop the ability to analyse

1. Aim The assignment aims to develop the ability to analyse, evaluate, research plan and manage a major building project through individual and group participation (ideally 4-6 people).Refer to vUWS for the DA plans and ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As