Question
What are main dissimilarities in applications between pipe culverts and box culverts?

Answer
Essentially, culvert resources covered hydraulic structure that conveys fluid. So in a broad sense, pipe culverts in small scale stand for normal pipes similar to precast concrete pipes.

In conditions of hydraulic presentation, circular section is best geometrical sections between all. Consequently, for relative little discharge, precast concrete pipes and ductile iron pipes are usually used which are circular in shape. For applications of extremely large flow, precast concrete pipes and ductile iron pipes might not be obtainable in present market. In this connection, cast-in-situ structure has to be employed. It is further than doubt that fabrication of formwork for circular shape is not easy when compared with regular box culvert structures. Still, circular shape is mainly hydraulic efficient structure which way for a given release, area of flow is smallest amount. Thus, it helps to save cost of extra linings compulsory for choice of box culverts.

But, box culverts do own a number of advantages. As in they can manage with large flow situation anywhere headroom is partial since height of box culverts can be reduced while size of pipe culverts is permanent. Secondly, for some difficult site situations for example excavation of arrangement in rock, for same equivalent cross-sectional area, width of box culverts know how to be designed to be lesser than that of pipe culverts and this improves smaller quantity of excavation and backfilling.

 

Civil Engineering, Engineering

  • Category:- Civil Engineering
  • Reference No.:- M9591009

Have any Question?


Related Questions in Civil Engineering

Aimthis assignment aims to demonstrate the structural

Aim: This assignment aims to demonstrate the structural design requirements of a glazed façade in a multi-storey building. Among other requirements, the glazed façade is required to comply with Australian Standard AS 204 ...

1 aimthe assignment aims to develop the ability to analyse

1. Aim The assignment aims to develop the ability to analyse, evaluate, research plan and manage a major building project through individual and group participation (ideally 4-6 people).Refer to vUWS for the DA plans and ...

Masonry design assignmentquestion 1 - derivation of seismic

MASONRY DESIGN ASSIGNMENT Question 1 - Derivation of seismic actions on building a) Determine the storey seismic weights (Wi) for each suspended level of the building, hence the seismic weight (Wt) of the entire building ...

Masonry design assignmentquestion 1 - derivation of seismic

MASONRY DESIGN ASSIGNMENT Question 1 - Derivation of seismic actions on building a) Determine the storey seismic weights (Wi) for each suspended level of the building, hence the seismic weight (Wt) of the entire building ...

Aimthis assignment aims to demonstrate the structural

Aim: This assignment aims to demonstrate the structural design requirements of a glazed façade in a multi-storey building. Among other requirements, the glazed façade is required to comply with Australian Standard AS 204 ...

The drainage system of a cantilever wall shown in below

The drainage system of a cantilever wall shown in below figure, became blocked after a heavy rainstorm and the groundwater level, which was originallybelow the base, rose to1.5 (m) below the surface. Determine the stabil ...

Assignmenta continuous three spans beam with

Assignment A continuous three spans beam with centre-to-centre distance of 6 m supports 150 mm thick one-way slabs as shown below. The beams have clear spans of 8 m, 9 m, and 8 (face-to-face of 400 mm square columns). Th ...

Assignment -ewb design report format - cover page - the as

Assignment - EWB Design Report Format - Cover page - The as EWB project Table of content Introduction about -EWB and CRDT (Cambodian Rural development team) Background about Cambodia - Economic, Weather, People - living ...

Task details the client is doing masters in civil

Task Details: The client is doing Masters in Civil Engineering. He needs a Technical Paper on Earthquake pertaining to Geology and Rock Mechanics. There should be a through discussion of Earthquake in relation to the men ...

Civilyou are provided with bill of quantities prepared

Civil You are provided with bill of quantities prepared separately, priced and submitted by 3 con- tractors (A,B,C found on LMS) in respect of a proposed project (see appendix for drawings). The site is located on Mt. Al ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As