Question

In case if there is a delay of bituminous laying on top of sub-base, have to tack coat be applied on the top surface of sub-base?


Answer


When there is a delay between bituminous laying of different bituminous layers such as roadbase, base course. A tack coat is applied on top of bituminous layers as it helps to improve better bonding between bituminous materials. If there is not enough bonding between adjacent bituminous layers, they perform as separate independent layers which are able to barely resist traffic loads. When applying tack coat, it have to be sprayed uniformly on bituminous surface and allowed for enough curing. Hot bituminous material laid on top of coat would soften it, enabling tack coat to partly fill voids in bituminous materials. For emulsified asphalt category tack coats, they are usually diluted with water in order to achieve an additional uniform application without excessive usage of asphalt. After subsequent compaction is carried out, coat would be interlocked with bituminous materials. On other hand, care should be taken to make sure that excessive coat will not be laid, or else slippage or shear cracks in bituminous material would occur due to relative thick layer of tack coat applied.

Though, for sub-base surface, priming coat in its place of tack coat might be applied in event of a delay in laying of bituminous layer on top of sub-base layer. Function of primer serves to maintain existing surface condition for a longer period and it also provides an impervious surface to stop ingress of water or water beating by evaporation.

Besides, it fills surface voids and protects sub-base from adverse weather setting. In adding up, it and helps to promote adhesion between adjacent road layers and to harden surface.

 

Civil Engineering, Engineering

  • Category:- Civil Engineering
  • Reference No.:- M9591089

Have any Question?


Related Questions in Civil Engineering

Task details the client is doing masters in civil

Task Details: The client is doing Masters in Civil Engineering. He needs a Technical Paper on Earthquake pertaining to Geology and Rock Mechanics. There should be a through discussion of Earthquake in relation to the men ...

The drainage system of a cantilever wall shown in below

The drainage system of a cantilever wall shown in below figure, became blocked after a heavy rainstorm and the groundwater level, which was originallybelow the base, rose to1.5 (m) below the surface. Determine the stabil ...

Aimthis assignment aims to demonstrate the structural

Aim: This assignment aims to demonstrate the structural design requirements of a glazed façade in a multi-storey building. Among other requirements, the glazed façade is required to comply with Australian Standard AS 204 ...

Civilyou are provided with bill of quantities prepared

Civil You are provided with bill of quantities prepared separately, priced and submitted by 3 con- tractors (A,B,C found on LMS) in respect of a proposed project (see appendix for drawings). The site is located on Mt. Al ...

Assignment -ewb design report format - cover page - the as

Assignment - EWB Design Report Format - Cover page - The as EWB project Table of content Introduction about -EWB and CRDT (Cambodian Rural development team) Background about Cambodia - Economic, Weather, People - living ...

Masonry design assignmentquestion 1 - derivation of seismic

MASONRY DESIGN ASSIGNMENT Question 1 - Derivation of seismic actions on building a) Determine the storey seismic weights (Wi) for each suspended level of the building, hence the seismic weight (Wt) of the entire building ...

Aimthis assignment aims to demonstrate the structural

Aim: This assignment aims to demonstrate the structural design requirements of a glazed façade in a multi-storey building. Among other requirements, the glazed façade is required to comply with Australian Standard AS 204 ...

Assessment taskpractical investigationinstructions- it is

Assessment Task Practical Investigation Instructions: - It is very important that you read these instructions. - The hardcopy of the Assignment report, with the Assignment cover sheet, should be submitted to the Assignme ...

Masonry design assignmentquestion 1 - derivation of seismic

MASONRY DESIGN ASSIGNMENT Question 1 - Derivation of seismic actions on building a) Determine the storey seismic weights (Wi) for each suspended level of the building, hence the seismic weight (Wt) of the entire building ...

Assignmenta continuous three spans beam with

Assignment A continuous three spans beam with centre-to-centre distance of 6 m supports 150 mm thick one-way slabs as shown below. The beams have clear spans of 8 m, 9 m, and 8 (face-to-face of 400 mm square columns). Th ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As