Question: The following scenario pertains to Questions 1-5.

A project consists of the following 5 elements. Assume that the CapEx (capital expenditure) takes place at the beginning of each element, that there are 40 working hours in a week, and that labor is charged at $100/hr. The precedents are given in the second column.

Element Dependencies       CapEx         Duration      Total hrs

A Can start immediately     $5,000      4 weeks        160

B Can start immediately     $10,000     4 weeks        160

C B needs to be complete  $8,000      2 weeks         80

D A and C need to be complete   $12,000 1 week     40

E C needs to be complete   $9,000     2 weeks         80

Question 1:

Using PlanBee scheduling software set up a project (AoN) for the project shown above,

then display a PERT chart for the project. Simply capture the screen with something like Snagit and paste the JPG in here. I am suggesting PlanBee, because it is easy to learn. If you already have MS Project on your computer, you may use that instead.

Question 2:

Create the Gantt chart for the project and paste it in here.

Question 3:

Give a cost estimate for the project, without contingencies.

Question 4:

Using the software Projrisk supplied, calculate the additional contingency for this project so that you will have a 90% confidence of having sufficient funds. Please ensure YOU provide the answer from the software. The examiner will NOT interpret any software pastings you include. However - please paste a copy of the data you have entered and also any relevant backups to support your answer. Also paste a copy of your S-curve in here.

Assume the following, based on past experience:

Expected variation on all materials -5%, +10% triangular distribution

Expected variation on labor -5%, +5% [10]

Question 5:

At the end of the third week you are compiling a progress report.

Task A is proceeding as per plan. However, B is a problem. You have only completed 50% of the work, and you have already booked 140 hours on the job. All CapEx has already been done.

Calculate the following (IF THERE ARE ERRORS - I CAN TRY AND GIVE MARKS BUT ONLY IF FORMULAE ARE SUPPLIED AS WELL):
BAC
BCWS
BCWP
ACWP
SPI
CPI
CV
SV
ETC
EAC

Mechanical Engineering, Engineering

  • Category:- Mechanical Engineering
  • Reference No.:- M91673748

Have any Question?


Related Questions in Mechanical Engineering

Force exerted by jet on moving cart1 you need to determine

Force Exerted By Jet On Moving cart. 1. You need to determine the velocity of water that comes out from the nozzle of this system. need the equation please formulate the equation. 2. This water will strike a small cart a ...

Questions -q1 a qualitative estimate of the effect of a

Questions - Q1. A qualitative estimate of the effect of a wind-tunnel contraction (Figure) on turbulent motion can be obtained by assuming that the angular momentum of eddies does not change through the contraction. Let ...

Materials behaviour from atoms to bridges assignment -

Materials Behaviour from Atoms to Bridges Assignment - Distributed loads and static equilibrium (Please note: you should show your steps with necessary figures) Q1. Two beam sections are jointed at C and supported at A b ...

1 explain the term critical equipment and provide two clear

1. Explain the term "critical equipment" and provide two clear examples of machinery which falls into this category on board a twin screw motor vessel. 2. Explain the process of Charpy lmpact Testing including sample mar ...

Heat transfer and combustionyou will need graph paper a

HEAT TRANSFER AND COMBUSTION You will need graph paper, a calculator, a copy of Appendix 1 from lesson HTC - 4 - 2 and access to steam tables to answer this TMA. 1. A fuel gas consists of 75% butane (C 4 H 10 ), 10% prop ...

Life cycle assessmentfor your chosen service eg white board

LIFE CYCLE ASSESSMENT For your chosen service (e.g. white board markers), identify two alternatives of getting the service (e.g. brand A, brand B). Choose the most environmentally friendly option by conducting life cycle ...

Fluid mechanics assignment - viscous flow in pipesq1 as

Fluid Mechanics Assignment - Viscous Flow in Pipes Q1. As shown in the figure below, water "bubbles up" 3 in. above the exit of the vertical pipe attached to three horizontal pipe segments. The total length of the 0.75-i ...

Assignment - machine learning for signal processingproblem

Assignment - Machine Learning for Signal Processing Problem 1: Instantaneous Source Separation 1. As you might have noticed from my long hair, I've got a rock spirit. However, for this homework I dabbled to compose a pie ...

Problem -a long pipe od 1413 mm id 1318 mm kp 20 wmk

Problem - A long pipe (OD = 141.3 mm, ID =131.8 mm, k p = 20 W/m.K) supplies hot pressurized liquid water at 400 K to a heater in a factory. The pipe has an insulation thickness of 100 mm. A new efficient heater replaces ...

The aim of the project is to demonstrate certain aspects of

The aim of the project is to demonstrate certain aspects of engineering materials in different applications. The projects will be assessed on the basis of a written Research Report. The report should clearly show what yo ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As