QUESTION 1

As an estimator in a construction firm, you have been instructed to include only the costs relating to labour, material and plant in your calculations for the unit rates for a bill of quantities. You should assume that the required labour is readily available and that wage rates are stable.

Discuss and use examples to explain the specific factors that you will need to consider when pricing the following items in the bill of quantities:

a. foundation excavation;

b. disposal of excavated material.

QUESTION 2

With reference to the estimating data contained in Appendix A, build up rates and establish the cost of the following items contained in a bill of quantities:

Item

Description

Quantity

Unit

Rate
(£)

Item
cost (£)

A

Excavation commencing 150mm below original ground level, foundation excavation maximum depth not exceeding 2.00m

40

,

E

 

 

 

 

 

 

 

 

B

In situ concrete 1:2:4 mix horizontal work, less than 300mm thick in structures, foundation, poured against face of earth

10

M3

 

 

 

 

 

 

 

 

C

Common brickwork, walls, half brick thick in stretcher bond, skins of hollow walls in cement mortar (1:4)

30

m2

 

 

Allocation of marks
• Item A
• Item B
• Item C
• Cost of bill of quantities items
• Clear presentation and inclusion of all supporting calculations.

139_disposal of excavated material1.png

QUESTION 3

You are a director in a construction firm and are assessing the mark-up to he added to the estimated costs which have been established. this assesment will then be considered by the other director prior ro finalisation and submission or the tender.

You have obtained information relating to a similar project completed in the past, together with some relevant information relating to the current tender as detailed in Appendix R. where information is not provided, you should make and clearly slate , your assumptions.

In a briefing paper to be rerained on file For future use bx the firm pro. provide your recommendation with regard to the mark-up to be added ro the tender, including explanatory infomation to support this recommendation.

932_Disposal of excavated material.png

Civil Engineering, Engineering

  • Category:- Civil Engineering
  • Reference No.:- M9741227
  • Price:- $70

Priced at Now at $70, Verified Solution

Have any Question?


Related Questions in Civil Engineering

Assessment taskpractical investigationinstructions- it is

Assessment Task Practical Investigation Instructions: - It is very important that you read these instructions. - The hardcopy of the Assignment report, with the Assignment cover sheet, should be submitted to the Assignme ...

1 aimthe assignment aims to develop the ability to analyse

1. Aim The assignment aims to develop the ability to analyse, evaluate, research plan and manage a major building project through individual and group participation (ideally 4-6 people).Refer to vUWS for the DA plans and ...

Civilyou are provided with bill of quantities prepared

Civil You are provided with bill of quantities prepared separately, priced and submitted by 3 con- tractors (A,B,C found on LMS) in respect of a proposed project (see appendix for drawings). The site is located on Mt. Al ...

Aimthis assignment aims to demonstrate the structural

Aim: This assignment aims to demonstrate the structural design requirements of a glazed façade in a multi-storey building. Among other requirements, the glazed façade is required to comply with Australian Standard AS 204 ...

Assignmenta continuous three spans beam with

Assignment A continuous three spans beam with centre-to-centre distance of 6 m supports 150 mm thick one-way slabs as shown below. The beams have clear spans of 8 m, 9 m, and 8 (face-to-face of 400 mm square columns). Th ...

Aimthis assignment aims to demonstrate the structural

Aim: This assignment aims to demonstrate the structural design requirements of a glazed façade in a multi-storey building. Among other requirements, the glazed façade is required to comply with Australian Standard AS 204 ...

The drainage system of a cantilever wall shown in below

The drainage system of a cantilever wall shown in below figure, became blocked after a heavy rainstorm and the groundwater level, which was originallybelow the base, rose to1.5 (m) below the surface. Determine the stabil ...

Task details the client is doing masters in civil

Task Details: The client is doing Masters in Civil Engineering. He needs a Technical Paper on Earthquake pertaining to Geology and Rock Mechanics. There should be a through discussion of Earthquake in relation to the men ...

Masonry design assignmentquestion 1 - derivation of seismic

MASONRY DESIGN ASSIGNMENT Question 1 - Derivation of seismic actions on building a) Determine the storey seismic weights (Wi) for each suspended level of the building, hence the seismic weight (Wt) of the entire building ...

Masonry design assignmentquestion 1 - derivation of seismic

MASONRY DESIGN ASSIGNMENT Question 1 - Derivation of seismic actions on building a) Determine the storey seismic weights (Wi) for each suspended level of the building, hence the seismic weight (Wt) of the entire building ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As