Ask Question, Ask an Expert

+61-413 786 465

info@mywordsolution.com

Ask Civil Engineering Expert

Question 1: Determine the maximum depth in a 5-m wide rectangular channel if the flow is to be supercritical with a flow rate of Q = 40 m3/s. What is the critical slope corresponding to the above flow rate? (n = 0.011)

Question 2: A flow of 28 m3s-1 occurs in an earth-lined canal having a base width of 3 m, side slopes of 1(vertical) to 2 (horizontal) and the Manning’s n value of 0.022. Calculate the critical depth and critical slope.

Question 3: 

a. A hydraulic jump occurs in a rectangular open channel. The water depths before and after the jump are 0.6 m and 1.5 m, respectively. Calculate the critical depth.

b. A hydraulic jump occurs in a rectangular channel 3 m wide having a discharge of 9 m3s-1. The approach depth is 0.75 m. What is the downstream depth, and what fraction of the upstream energy is dissipated in the jump?

Question 4: Water enters a very wide rectangular channel (Manning’s n = 0.0149) at a velocity of 12.2 ms-1 and a depth of 0.61 m. An H3 curve forms downstream and the water jumps to a depth of 2.4 m some distance downstream. Find the distance downstream to the location of the hydraulic jump.

Question 5: A long wide rectangular channel carries a steady flow rate of 35 m2s-1 (flow per unit width) and passes through an abrupt change in slope from 0.005 (upstream of the change) to 0.003 (downstream). Manning’s n for the channel is 0.013. Is there a hydraulic jump in the channel and if so where? Describe the water surface profiles at the various parts of the channel.

Question 6: 6. Question from Hydrology section

Note:

(i) The numerical values for the variables in the questions are based on your ID number and you must use the appropriate values for answering the questions. Failure to do so will result in no marks being awarded to those questions.

The following variable is used in the questions: R

If the last two digits of your ID is greater than or equal to 45 then R = the last two digits

If the last two digits of your ID is less than 45, then R = 45 + the last two digits

Example: If the ID =230675467, then R = 67

If the ID = 230675134, then R = 45 + 34 = 79

Note that your R value can only be between 45 and 99 (both inclusive)

6 (b)

Flood peaks of a river for 5-yr and 100-yr return periods are given as (100 + R) and (400 + R) m3/s respectively:

i. Calculate mean (X) and standard deviation ( S ) of the river floods assuming that Gumbel distribution fits the data

ii. Using Normal distribution calculate 50 and 100 year return period flood peaks,

iii. Calculate 50 and 100 year return period flood peaks using 2-parameter Log-Normal distribution. The mean (Y), standard deviation (Sy ) and skewness coefficient (gy) of the logarithms (base 10) of the annual flood peaks are given as follows:

Y= 2 + R/1000, Sy = 0.4 + R/1000 , gy= -(R /100)

iv. For statistics of the log transformed data in (iii), calculate flood peak for 50 and 100 year return periods using the Log-Pearson


Attachment:- Hydro-Hydraulics.pdf

Civil Engineering, Engineering

  • Category:- Civil Engineering
  • Reference No.:- M91271614
  • Price:- $75

Priced at Now at $75, Verified Solution

Have any Question?


Related Questions in Civil Engineering

Task details the client is doing masters in civil

Task Details: The client is doing Masters in Civil Engineering. He needs a Technical Paper on Earthquake pertaining to Geology and Rock Mechanics. There should be a through discussion of Earthquake in relation to the men ...

Civilyou are provided with bill of quantities prepared

Civil You are provided with bill of quantities prepared separately, priced and submitted by 3 con- tractors (A,B,C found on LMS) in respect of a proposed project (see appendix for drawings). The site is located on Mt. Al ...

The drainage system of a cantilever wall shown in below

The drainage system of a cantilever wall shown in below figure, became blocked after a heavy rainstorm and the groundwater level, which was originallybelow the base, rose to1.5 (m) below the surface. Determine the stabil ...

Masonry design assignmentquestion 1 - derivation of seismic

MASONRY DESIGN ASSIGNMENT Question 1 - Derivation of seismic actions on building a) Determine the storey seismic weights (Wi) for each suspended level of the building, hence the seismic weight (Wt) of the entire building ...

Assessment taskpractical investigationinstructions- it is

Assessment Task Practical Investigation Instructions: - It is very important that you read these instructions. - The hardcopy of the Assignment report, with the Assignment cover sheet, should be submitted to the Assignme ...

Masonry design assignmentquestion 1 - derivation of seismic

MASONRY DESIGN ASSIGNMENT Question 1 - Derivation of seismic actions on building a) Determine the storey seismic weights (Wi) for each suspended level of the building, hence the seismic weight (Wt) of the entire building ...

Aimthis assignment aims to demonstrate the structural

Aim: This assignment aims to demonstrate the structural design requirements of a glazed façade in a multi-storey building. Among other requirements, the glazed façade is required to comply with Australian Standard AS 204 ...

Aimthis assignment aims to demonstrate the structural

Aim: This assignment aims to demonstrate the structural design requirements of a glazed façade in a multi-storey building. Among other requirements, the glazed façade is required to comply with Australian Standard AS 204 ...

1 aimthe assignment aims to develop the ability to analyse

1. Aim The assignment aims to develop the ability to analyse, evaluate, research plan and manage a major building project through individual and group participation (ideally 4-6 people).Refer to vUWS for the DA plans and ...

Assignmenta continuous three spans beam with

Assignment A continuous three spans beam with centre-to-centre distance of 6 m supports 150 mm thick one-way slabs as shown below. The beams have clear spans of 8 m, 9 m, and 8 (face-to-face of 400 mm square columns). Th ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As