QUANTITY SURVEYING & VALUATION

SECTION A

I. The Damp Proof Course is measured in_______________.

II. Quantity of Plaster is measured in_______.

III. Concrete of 50 mm thick flooring is measured in___________.

IV. The most reliable estimate is (a)Detailed estimate (b)Preliminary estimate(c)Plinth area estimate(d)Cube rate estimate

V. If d is the diameter of MS Steel bar in mm the standard weight in Kg per meter of the bar is(a)0.00618 d2 (b)0.00618 d (c)0.00816 d2 (d) 0.00816 d

VI. Write down the basis formula for calculating the road earthwork by prismoidal formula.

VII. The Approximate cost of the Electrification work as a % of the total cost of the estimated cost is
(a) 10 % (b)8 % (c)12 % (d) 4 %

VIII. Write down the method of Building Estimate.

IX. How much % of the total estimated cost is added for contingencies?
(a) 1.5% (b)2 % (c)3% (d) 8%

X. Find the volume of Earthwork in the following

216_Earthwork.jpg

SECTION B

1. What is Estimate .What is purpose of estimate.

2. Explain different types of estimate and explain each?

OR

1. Explain various type of deduction in the masonry work?

2. What do you mean by "Revised Estimate"? Explain the circumstances under which such estimates are prepared.

SECTION C

3. Write down the different formula to calculate the volume of earthwork in road.

4. Calculate the Quantity of earth work for a road from the following data:

Formation Width of road: - 8 m, Side slope of cutting &banking: 2:1

Assume there is no transverse slope, Using Prismoidal formula.

Distance in m

0

40

80

120

R.L of Ground  in m

50.2

50.7

51.2

51.8

R.L of Formation in m

51.2

Downward Gradient    1: 200

OR

3. Estimate the quantity of the following items of a two roomed building from a given plan & section:(15)
1. Earthwork in excavation in foundation.
2. LimeConcrete in foundation
3. 1 class brickwork in cement mortar 1:6 cement mortar in foundation and plinth.
4. 2.5 cm c.c damp proof course.
5. 1 class brickwork in cement mortar 1:6 cement mortar in superstructure.
Door D 1.20 m x 2.10 m Window W 1.00m x 1.50m Shelves S 1.00 m x 1.50 m

All walls are of same section, lintel over Door, Windows and Shelves are 15 cm thick.

2311_Earthwork1.jpg

OR
3. Estimate the cost of earthwork for a portion of road 400 metre length from the following data. (15)
Formation Width of road: - 10m, Side slope of banking are 2:1 and 1.5:1 in cutting

station

25

26

27

28

29

30

31

32

33

34

35

Distance

1000

1040

1080.

1120

1160

1200

1240

1280

1320

1360

1400

R.L of GL

51.00

50.90

50.5

50.80

50.60

50.70

51.20

51.40

51.30

51.00

50.60

R.L of Formation

52.00

Downward Gradient of  1 in 200

Rates:-

1.Earthwork in Banking Rs.275.00 per cum
2. Earthwork in cutting Rs.350.00 per cum

Mechanical Engineering, Engineering

  • Category:- Mechanical Engineering
  • Reference No.:- M92768196
  • Price:- $25

Priced at Now at $25, Verified Solution

Have any Question?


Related Questions in Mechanical Engineering

Life cycle assessmentfor your chosen service eg white board

LIFE CYCLE ASSESSMENT For your chosen service (e.g. white board markers), identify two alternatives of getting the service (e.g. brand A, brand B). Choose the most environmentally friendly option by conducting life cycle ...

Assignment - machine learning for signal processingproblem

Assignment - Machine Learning for Signal Processing Problem 1: Instantaneous Source Separation 1. As you might have noticed from my long hair, I've got a rock spirit. However, for this homework I dabbled to compose a pie ...

Expansion processes of a perfect gasassignment1 attend the

Expansion Processes of a Perfect Gas Assignment: 1. Attend the laboratory class and complete the lab tests according to the supervisor's requirement. Students will not allowed to submit their report if they do not come t ...

Question - truss structureconsider the three membered

Question - Truss Structure Consider the three membered planar truss structure shown in the figure below. All members of the truss have identical square cross-sectional area (A) of 25 mm x 25 mm, and Youngs Modulus (E) = ...

Structural mechanics questions -q1 a 150-lb bucket is

Structural Mechanics Questions - Q1. A 150-lb bucket is suspended from a cable on the wooden frame. Determine the resultant internal loadings on the cross section at D, and at E. Q2. The shaft is supported at its ends by ...

The aim of the project is to demonstrate certain aspects of

The aim of the project is to demonstrate certain aspects of engineering materials in different applications. The projects will be assessed on the basis of a written Research Report. The report should clearly show what yo ...

5star questions amp answers1a define heat treatment bname

5 STAR QUESTIONS & Answers 1. A) Define Heat treatment B) Name different types of heat treatment processes C) Write any 4 purposes of Heat treatment 2. Explain various Heat treatment processes 3. A) Compare Thermo plasti ...

Problem on shaft -assuming no frictional losses a torque of

Problem on Shaft - Assuming no frictional losses, a torque of T = 750lb·in is applied through the shaft of gear F in order to drive the roller chain at point B at a constant speed. The chain sprocket has a pitch diameter ...

Fluid mechanics assignment - finite control volume analysis

Fluid Mechanics Assignment - Finite Control Volume Analysis and Dimensional Analysis Q1. The wind blows through a 7ft × 10ft garage door opening with a speed of 5 ft/s as shown in the figure. Determine the average speed, ...

Materials behaviour from atoms to bridges assignment -

Materials Behaviour from Atoms to Bridges Assignment - Distributed loads and static equilibrium (Please note: you should show your steps with necessary figures) Q1. Two beam sections are jointed at C and supported at A b ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As