Ask Question, Ask an Expert

+61-413 786 465

info@mywordsolution.com

Ask Civil Engineering Expert

Q. Advantages of continuous multiple-span deck over simply supported multiple-span deck?

Movement joints are generally added to bridge structures to accommodate movements because of dimensional changes arising from temperature variation, shrinkage, creep and effect of pre-stress. Though provision of excessive movement joints must be avoided in design since movement joints always encounter problems giving rise to trouble in normal operation and this increases cost of maintenance. 

A number of designers may prefer to add more movement joints to guard against possible occurrence of differential settlements. Though the effect of continuity is disabled by this excessive introduction of movement joints.

From structural point of view, use of continuous deck increases the reduction of bridge deck thickness. Furthermore deck continuity allows the potential increase in headroom in mid-span of bridges by using sucker deck principle. 

Some designers may prefer to employ the use of simply supported multiple-span deck to guard against probable occurrence of differential settlements. But the effect of continuity is undermined by the introduction of movement joints. In essence structural reserve provided by a continuous bridge is destroyed by multiple-span statically determinate structure resulting from the addition of joints.

Furthermore the reduction of joints in bridge structures signifies substantial cost savings arising from construction and maintenance costs of movement joints. Reduction of deck thickness helps to cut the cost for both deck and foundation. Particularly the number of bearings in every piers is substantially decreased when compared with the case of simply supported multiple-span deck.

Advantages of using the bridge form of precast pre-stressed beams supporting in-situ concrete top slab.

The potential benefits of employing the useof bridge form of precast pre-stressed beams supporting in-situ concrete top slab are:

(i)  For bridges which are built on top of rivers and carriageway, this bridge form provides working platform by precast beams so that erection of falsework isn't required.

(ii)  This bridge form normally doesn't require any transverse beams or diaphragms (excepting at the location of bridge supports) leading to reduction of construction cost andtime. 

(iii) It creates the potential for concurrent construction with several spans.

Civil Engineering, Engineering

  • Category:- Civil Engineering
  • Reference No.:- M9575503

Have any Question?


Related Questions in Civil Engineering

Masonry design assignmentquestion 1 - derivation of seismic

MASONRY DESIGN ASSIGNMENT Question 1 - Derivation of seismic actions on building a) Determine the storey seismic weights (Wi) for each suspended level of the building, hence the seismic weight (Wt) of the entire building ...

Assignment -ewb design report format - cover page - the as

Assignment - EWB Design Report Format - Cover page - The as EWB project Table of content Introduction about -EWB and CRDT (Cambodian Rural development team) Background about Cambodia - Economic, Weather, People - living ...

Assessment taskpractical investigationinstructions- it is

Assessment Task Practical Investigation Instructions: - It is very important that you read these instructions. - The hardcopy of the Assignment report, with the Assignment cover sheet, should be submitted to the Assignme ...

The drainage system of a cantilever wall shown in below

The drainage system of a cantilever wall shown in below figure, became blocked after a heavy rainstorm and the groundwater level, which was originallybelow the base, rose to1.5 (m) below the surface. Determine the stabil ...

Assignmenta continuous three spans beam with

Assignment A continuous three spans beam with centre-to-centre distance of 6 m supports 150 mm thick one-way slabs as shown below. The beams have clear spans of 8 m, 9 m, and 8 (face-to-face of 400 mm square columns). Th ...

Aimthis assignment aims to demonstrate the structural

Aim: This assignment aims to demonstrate the structural design requirements of a glazed façade in a multi-storey building. Among other requirements, the glazed façade is required to comply with Australian Standard AS 204 ...

Aimthis assignment aims to demonstrate the structural

Aim: This assignment aims to demonstrate the structural design requirements of a glazed façade in a multi-storey building. Among other requirements, the glazed façade is required to comply with Australian Standard AS 204 ...

Task details the client is doing masters in civil

Task Details: The client is doing Masters in Civil Engineering. He needs a Technical Paper on Earthquake pertaining to Geology and Rock Mechanics. There should be a through discussion of Earthquake in relation to the men ...

Civilyou are provided with bill of quantities prepared

Civil You are provided with bill of quantities prepared separately, priced and submitted by 3 con- tractors (A,B,C found on LMS) in respect of a proposed project (see appendix for drawings). The site is located on Mt. Al ...

Masonry design assignmentquestion 1 - derivation of seismic

MASONRY DESIGN ASSIGNMENT Question 1 - Derivation of seismic actions on building a) Determine the storey seismic weights (Wi) for each suspended level of the building, hence the seismic weight (Wt) of the entire building ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As