Problem 1 - Roundabouts

As part of the transport impact assessment for a proposed residential development off Zinglemann Road at Carmzow, you have been asked to evaluate the performance of a singlelane roundabout under 2018 weekday AM peak hour traffic projections as a possible intersection form to replace an existing unsignalised cross intersection, which has been found to be inadequate for the proposed conditions. The figure below illustrates the proposed intersection form, turning movements and flow rates.

1463_Calculate the flow rate on each approach lane.png

Figure Lane allocation and control, turning movement flow rates (veh/h)

The geometric characteristics of the roundabout are listed in the table below.

Criterion  multi-lane roundabout 
Approach lanes  1 east and west, 1 north and south 
Circulating lanes  1
Circulating lane width  6.5m 
Central island diameter  10m 
Entry lane width  4.1m 
Approach speed  60km/h 
Negotiation speed  30km/h 

Assume that any pedestrians (flows not shown) must give way to vehicle traffic. Stating any other assumptions you need to make, conduct your roundabout intersection analysis in a table according to the following procedure:

(i) Calculate the circulating flow past each approach to the roundabout;

(ii) Calculate the flow rate on each approach lane;

(iii) Estimate the headway distribution characteristics of the circulating stream past each approach;

(iv) Estimate the theoretical capacity and degree of saturation of each approach lane. Compare with the roundabout practical degree of saturation of 0.85;

(v) Estimate the average queuing delay for all vehicles on each approach lane;

(vi) Estimate the 95th percentile design queue length in each approach lane;

(viii) Comment on the overall operation of the proposed roundabout for the conditions analysed, including the amount of spare capacity to accommodate traffic growth.

- Use a tabulated spreadsheet to complete this problem.

- Numbering of the movements in your response must be the same as those shown here. In your spreadsheet, your movement calculations must be ordered in rows from the lowest to highest movement down the page. For each movement clearly carry your calculations in rows right across the spreadsheet and be consistent with placement of these calculations for all movements.

- In your spreadsheet, your lane calculations must be ordered in rows according to the following convention: S1, E1, N1, W1.

- Use sensible rounding when displaying answers on your spreadsheet (Excel has a displayed rounding tool, while still carrying the values to a high level of significance throughout the calculations). For example, flows in whole veh/h or 0.xxx veh/s, delays to whole s, and queue lengths to the next whole veh.

- Submit clearly labelled your electronic spreadsheet on electronic media with your hard copy so that your working can be tracked.

Problem 2 - Signalised Intersections

As part of the transport impact assessment, you also have been asked to evaluate the performance of a signalised intersection at the cross intersection of Zinglemann Road and Old School Road under the 2018 weekday AM peak hour traffic projections shown in the following figure, as a possible replacement. The intersection geometry, movement numbers and flows, and signal phasing arrangement are shown in the following figure and table.

1997_Calculate the flow rate on each approach lane1.png

Figure Proposed Signalised Intersection Information

The required parameters for the proposed signalised intersection control are given as follows.

Table Signalized Intersection Parameters

Criterion  Value 
Environmental class: Old School Rd 
Environmental class: Zinglemann Rd 
Grade: Old School Rd  0%
Grade: Zinglemann Rd  -2% (south approach only) 
Curve Radii (all approaches)  Nil tight 
Pedestrian crossings  Nil 
Heavy vehicles  10% (north approach only) 
Yellow time  4s 
All-red time  2s 
Minimum green time  2s 
Lost time (all movements)  (assume same as intergreen time) 
Practical Degree of Saturation  0.85
Optimal Cycle Time k Value  0

Other requirements

- Use a tabulated spreadsheet to complete this Problem.

- Reproduce the following tables for inclusion of your calculations in your spreadsheet.

- Numbering of the movements in your response must be the same as those shown here.

In your spreadsheet, your movement calculations must be ordered in rows from the lowest to highest movement down the page. For each movement clearly carry your calculations in rows right across the spreadsheet and be consistent with placement of these calculations for all movements.

- In your spreadsheet, your lane calculations must be ordered in rows according to the following convention: S1, S2...; E1, E2...; N1, N2...; W1, W2...

- Use sensible rounding when displaying answers on your spreadsheet (Excel has a displayed rounding tool, while still carrying the values to a high level of significance throughout the calculations): Display flow rate to three decimal places, probability to three decimal places; degree of saturation to two decimal places; delay to nearest whole second; queue length rounded upwards to nearest whole vehicle.

- Submit clearly labelled your electronic spreadsheet on electronic media with your hard copy so that your working can be tracked.

(i) Find the base saturation flow rates for each lane.

(ii) Lane width and gradient factors adjustment.

(iii) Traffic composition factor adjustment.

(iv) Flow ratio calculation.

(v) Critical movement identification and intersection flow ratio.

(vi) Cycle time calculation.

Calculate optimal cycle time, practical cycle time, and cycle time to use.

(vii) Green time allocation.

(viii) Average delay time and level of service.

(ix) Compare the signalised intersection performance for the 2018 opening year weekday AM peak hour with that of the existing unsignalised intersection from Problem 2 and that of the roundabout from Problem 1.

Civil Engineering, Engineering

  • Category:- Civil Engineering
  • Reference No.:- M91411776
  • Price:- $80

Priced at Now at $80, Verified Solution

Have any Question?


Related Questions in Civil Engineering

1 aimthe assignment aims to develop the ability to analyse

1. Aim The assignment aims to develop the ability to analyse, evaluate, research plan and manage a major building project through individual and group participation (ideally 4-6 people).Refer to vUWS for the DA plans and ...

Masonry design assignmentquestion 1 - derivation of seismic

MASONRY DESIGN ASSIGNMENT Question 1 - Derivation of seismic actions on building a) Determine the storey seismic weights (Wi) for each suspended level of the building, hence the seismic weight (Wt) of the entire building ...

Task details the client is doing masters in civil

Task Details: The client is doing Masters in Civil Engineering. He needs a Technical Paper on Earthquake pertaining to Geology and Rock Mechanics. There should be a through discussion of Earthquake in relation to the men ...

The drainage system of a cantilever wall shown in below

The drainage system of a cantilever wall shown in below figure, became blocked after a heavy rainstorm and the groundwater level, which was originallybelow the base, rose to1.5 (m) below the surface. Determine the stabil ...

Assignmenta continuous three spans beam with

Assignment A continuous three spans beam with centre-to-centre distance of 6 m supports 150 mm thick one-way slabs as shown below. The beams have clear spans of 8 m, 9 m, and 8 (face-to-face of 400 mm square columns). Th ...

Assessment taskpractical investigationinstructions- it is

Assessment Task Practical Investigation Instructions: - It is very important that you read these instructions. - The hardcopy of the Assignment report, with the Assignment cover sheet, should be submitted to the Assignme ...

Assignment -ewb design report format - cover page - the as

Assignment - EWB Design Report Format - Cover page - The as EWB project Table of content Introduction about -EWB and CRDT (Cambodian Rural development team) Background about Cambodia - Economic, Weather, People - living ...

Civilyou are provided with bill of quantities prepared

Civil You are provided with bill of quantities prepared separately, priced and submitted by 3 con- tractors (A,B,C found on LMS) in respect of a proposed project (see appendix for drawings). The site is located on Mt. Al ...

Aimthis assignment aims to demonstrate the structural

Aim: This assignment aims to demonstrate the structural design requirements of a glazed façade in a multi-storey building. Among other requirements, the glazed façade is required to comply with Australian Standard AS 204 ...

Masonry design assignmentquestion 1 - derivation of seismic

MASONRY DESIGN ASSIGNMENT Question 1 - Derivation of seismic actions on building a) Determine the storey seismic weights (Wi) for each suspended level of the building, hence the seismic weight (Wt) of the entire building ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As