Outcomes of the assignment

1. Critically evaluate the linkages and interrelationships between disciplines of the construction, property management and administration of construction contracts.

2. Analyse and synthesise the obligations of various parties in a contractual arrangement.

3. Understand the detailed requirements various contracts, applying them to a scenario or case study.

Assignment Task 1

Outback Contractors have won a fixed price contract to construct a new National Football Stadium (The works comprise; (1) multipurpose track and field stadium; (2) Leisure facilities; (3) Restaurants; (4) entrance and parking area, with works starting on 1 March 2016 and the Employer is to take over control of the site on 28 February 2018. The following letter is sent during the contract from the Contractor to the Employers agent as in the following table.

You are required to complete the following:

- Write a letter replying to the Extract of the letter of 24 August 2017 (200 words)
- Prepare a report to discuss the contractual reasoning behind your responses under JCT Standard Building Contract and NEC3. Also outline differences and similarities of the conditions relevant to this scenario. (approximately 500 words)

Assignment Task 2
Assume yourself to be working in a Consultant firm providing service to a reputed entrepreneur organisation who has participated in several construction projects in sultanate of Oman. You are asked to select a live, large size, infrastructure development project on going in Oman and to submit a report (2000 words) to discuss construction contracts and contract management pertaining to obligations of various parties, contract administration, various contracts requirements and interrelationships between disciplines of the live construction project referencing to the case study, the report must discuss and cover the following information:

- From your live project describe the obligations of various construction parties involved.
- Describe the possible forms of contract used in Oman construction projects and suggest the possible one which suits your case study project. ( based on reasoning and justification)
- Based on the contract administration process describe the methods used to manage the following aspects in the project: (clear explanations with examples)
o Construction bonds,
o Delay's analysis and extension of time.
o Construction variations, and
o Claims.
- Describe the contract documents included in your selected construction project. Are they selected and prepared appropriately as per your professional opinion? Explain with reason.

Guidelines
Follow the guidelines mentioned below for your assignment.
- Assignment should be typed and an electronic copy is to be submitted through Moodle
- Handwritten assignments will not be accepted
- Assignment should have Complete and sign the cover sheet with the following information
o Assignment Title
o Class
o Student name

o Student ID
- It should have Table of Contents
- Use page numbers
- Assignment should be typed in your own words using Times New Roman font size 12.
- Heading should be with Font Size 14, Bold.
- Use Diagrams and Examples to explain your topic, provided citation, if applicable.
- You are encouraged to refer the books in Library or use internet resource or computer magazines or any other resource but you should not cut/copy and paste from internet.
- Copy paste from the Internet is strictly not acceptable.
- Harvard referencing style must be followed.

Civil Engineering, Engineering

  • Category:- Civil Engineering
  • Reference No.:- M92557933
  • Price:- $140

Guranteed 48 Hours Delivery, In Price:- $140

Have any Question?


Related Questions in Civil Engineering

The drainage system of a cantilever wall shown in below

The drainage system of a cantilever wall shown in below figure, became blocked after a heavy rainstorm and the groundwater level, which was originallybelow the base, rose to1.5 (m) below the surface. Determine the stabil ...

Assignment -ewb design report format - cover page - the as

Assignment - EWB Design Report Format - Cover page - The as EWB project Table of content Introduction about -EWB and CRDT (Cambodian Rural development team) Background about Cambodia - Economic, Weather, People - living ...

Assignmenta continuous three spans beam with

Assignment A continuous three spans beam with centre-to-centre distance of 6 m supports 150 mm thick one-way slabs as shown below. The beams have clear spans of 8 m, 9 m, and 8 (face-to-face of 400 mm square columns). Th ...

Aimthis assignment aims to demonstrate the structural

Aim: This assignment aims to demonstrate the structural design requirements of a glazed façade in a multi-storey building. Among other requirements, the glazed façade is required to comply with Australian Standard AS 204 ...

Masonry design assignmentquestion 1 - derivation of seismic

MASONRY DESIGN ASSIGNMENT Question 1 - Derivation of seismic actions on building a) Determine the storey seismic weights (Wi) for each suspended level of the building, hence the seismic weight (Wt) of the entire building ...

Aimthis assignment aims to demonstrate the structural

Aim: This assignment aims to demonstrate the structural design requirements of a glazed façade in a multi-storey building. Among other requirements, the glazed façade is required to comply with Australian Standard AS 204 ...

Civilyou are provided with bill of quantities prepared

Civil You are provided with bill of quantities prepared separately, priced and submitted by 3 con- tractors (A,B,C found on LMS) in respect of a proposed project (see appendix for drawings). The site is located on Mt. Al ...

Assessment taskpractical investigationinstructions- it is

Assessment Task Practical Investigation Instructions: - It is very important that you read these instructions. - The hardcopy of the Assignment report, with the Assignment cover sheet, should be submitted to the Assignme ...

Masonry design assignmentquestion 1 - derivation of seismic

MASONRY DESIGN ASSIGNMENT Question 1 - Derivation of seismic actions on building a) Determine the storey seismic weights (Wi) for each suspended level of the building, hence the seismic weight (Wt) of the entire building ...

1 aimthe assignment aims to develop the ability to analyse

1. Aim The assignment aims to develop the ability to analyse, evaluate, research plan and manage a major building project through individual and group participation (ideally 4-6 people).Refer to vUWS for the DA plans and ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As