Ask Question, Ask an Expert

+1-415-315-9853

info@mywordsolution.com

Ask Civil Engineering Expert

problem 1: Out of a long-term record of precipitation for four adjacent stations you find that records of one station (station D) are missing for the spring months, September, October, and November for the year 2011. For those three months the other three stations recorded the following total depth in mm.

778_long term precipitation.jpg

Estimate the missing precipitation if the long-term average precipitations for the three months in all four stations are:

1045_long term average precipitation.jpg

An alternative way of estimating a missing record is by weighting observations by the inverse square distance to the point of the missing record. If the distance of the station D from stations A, B, and C are 5 km, 1 km, and 10 km respectively, compute the missing records for the station D.

problem 2:

a) Average rainfall during the month of January is found to be  R  mm. A Class A pan evaporation recorded an average of [7 + (R/100)] mm/day near an irrigation reservoir. The average January inflow into the reservoir  is  (100 +  R) m3/s  and the  average  irrigation demand during the month is 170 m3/s. The water level drops by (10 times R) mm  in that month and the average surface area of the reservoir is 21,000 ha. Estimate the seepage through the banks and the dam during this month. Assume the pan coefficient of 0.7 for the month of January.

b) find out the evaporation in mm/day from the free water surface using Penman’s method.

The following data were measured on that day:

Net Radiation = (100 + R) W/m2
 
Air Temperature = 200C
Humidity = R %
Wind run = 20 km/day measured at 2 m above the surface
 
The wind function f(u) can be find outd as 73 + 0.44 u, when u is in km/day

Vapour pressures is in kPa and γ can be taken as 0.065 kPa/0C

problem 3: Show that the infiltration volume estimated using Horton’s infiltration equation between times t1 and t2 is given by;

1182_infiltration volume.jpg

Use the above concept in answering the following problem.

In a small watershed with homogeneous soil, runoff from two storms separated by an interval of 3 hours was monitored. The infiltration capacity of the soil at the beginning of the first storm was observed to be at its maximum capacity. Given the following information, determine the runoff for the first burst and the rate of infiltration recovery between the two storms.

Storm intensities:

2148_storm intensities.jpg

Infiltration capacity: fo = 14 mm/hr, fc = 4.0 mm/hr,  k = 0.6 hr-1
 
The surface runoff for the second storm was measured as Y mm at the outlet of the watershed, where Y is given by:

If your R value is between 45 and 55 (both inclusive), then Y = 15.5 mm
If your R value is between 56 and 66 (both inclusive), then Y = 16.0 mm
If your R value is between 67 and 77 (both inclusive), then Y = 16.5 mm
If your R value is between 78 and 88 (both inclusive), then Y = 17.0 mm
If your R value is between 89 and 99 (both inclusive), then Y = 17.5 mm

problem 4:

a) Rainfall intensities for every 10 min increments of a 60 min storm are given in sequence as: 102, 78, 90, 72, 56 and 45 mm/hr.

The infiltration capacity for the given soil type and cover is known to decrease at the following rate:

1249_infiltration capacity.jpg

Determine:

i) the surface runoff for every 10 min increments 
ii) the runoff volume for the storm 
iii) Φ-index for the storm. Infiltration capacity at the start of the storm may be assumed as 100 mm/hr.

Note: The area under the infiltration capacity curve may be computed using the trapezoidal rule for every 10 min increments.

b) The following data were obtained by stream gauging of a river:

2330_stream gauging.jpg

What should be the discharge when the main gauge reads 12 m and the auxiliary gauge reads [10.7 + (R/100)] m ?

problem 5: At the outlet of a catchment with area of 182.3 km2, direct runoff flood hydrograph (total runoff minus the base flow hydrographs) resulting from a 2-hr uniform rainfall excess is presented in the following table.

2099_uniform rainfall.jpg

a) find out the rainfall excess (in cm) for the above runoff hydrograph.

b) Using the value in Part (a) find out the unit hydrograph of 2-hr duration (that is for 1cm of rainfall excess in 2 hours).

c) From the 2-hr unit hydrograph in Part (b), find out the 1-hr unit hydrograph.

d) Using the 1-hr unit hydrograph of Part (c), estimate direct runoff flood hydrograph for a storm with the rainfall excess distribution of (R/100) cm and (R/50) cm during the first
and the second 1-hr time steps respectively.

e) What would be the direct runoff flood peak if the total depth of rainfall excess (i.e. 3R/100 cm) in section (d) is used in association with 2-hr unit hydrograph?

f) Compare the results for direct runoff flood peaks in sections (d) and (e) and discuss the difference.

Civil Engineering, Engineering

  • Category:- Civil Engineering
  • Reference No.:- M91130

Have any Question? 


Related Questions in Civil Engineering

The arm abcd of the industrial robot lies in a vertical

The arm ABCD of the industrial robot lies in a vertical plane that is inclined at 40? to the yz-plane. The arm CD makes an angle of 30? with the vertical. A socket wrench attached at point D applies a 52-lb · ft couple a ...

In this classic problem you are to design a single

In this classic problem, you are to design a single finite-state machine S that will be connected in an arbitrarily long one-dimensional string as follows: Each FSM in the string is connected by k wires to its left and r ...

Blood is a very interesting fluid a suspension of red and

Blood is a very interesting fluid: a suspension of red and white blood cells and platelets in a liquid plasma. We would like to be as optimistic as Jean Poiseuille in modeling blood flow, but we know that these cells in ...

Given the elevation of the end shearwall of a building as

Given: The elevation of the end shearwall of a building as shown in Fig. 3.C. The force from the roof diaphragm to the shearwall is 10 k. The wall dead load D = 20 psf, and the seismic coefficient is 0.200. Find: The tot ...

Objectivethe fundamental objectives of this assignment is

OBJECTIVE: The fundamental objectives of this assignment is to demonstrate the student ability to 1. Use the knowledge of different analysis methods learned in lectures to solve the task given in this assessment 2. Use S ...

Consider the gain plot in figure p12-68a find the transfer

Consider the gain plot in Figure P12-68. (a) Find the transfer function corresponding to the straightline gain plot. (b) Use MATLAB to plot the Bode magnitude of the transfer function. (c) Design a circuit that will real ...

Step response of an rlc bandpass circuit the step response

Step Response of an RLC Bandpass Circuit The step response of a series RLC bandpass circuit is (a) Find the passband center frequency and the two cutoff frequencies. (b) Design a circuit that would possess the above step ...

A tunable tank circuit the rlc circuit in figure p12-81

A Tunable Tank Circuit The RLC circuit in Figure P12-81 (often called a tank circuit) has R = 4.7 kΩ, C = 680 pF, and an adjustable (tunable) L ranging from 64 to 640 μH. (a) Show that the circuit is a bandpass filter. ( ...

A water treatment plant has four clarifiers treating 80 mgd

A water treatment plant has four clarifiers treating 8.0 MGD (0.350 m 3 /sec) of water. Each clarifier is 16 ft (4.88 m) wide, 80 ft (24.4 m) long, and 15 ft (4.57 m) deep. Determine: A. The detention time (hr) B. Overfl ...

Determine the force-couple system with the force acting at

Determine the force-couple system, with the force acting at point O, that is equivalent to the force and couple acting on the arm CD of the industrial robot. Note that the arm ABCD lies in a vertical plane that is inclin ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

WalMart Identification of theory and critical discussion

Drawing on the prescribed text and/or relevant academic literature, produce a paper which discusses the nature of group

Section onea in an atwood machine suppose two objects of

SECTION ONE (a) In an Atwood Machine, suppose two objects of unequal mass are hung vertically over a frictionless

Part 1you work in hr for a company that operates a factory

Part 1: You work in HR for a company that operates a factory manufacturing fiberglass. There are several hundred empl

Details on advanced accounting paperthis paper is intended

DETAILS ON ADVANCED ACCOUNTING PAPER This paper is intended for students to apply the theoretical knowledge around ac

Create a provider database and related reports and queries

Create a provider database and related reports and queries to capture contact information for potential PC component pro