JOHNSTON PRODUCTS

No matter how many times Justin Wang, the master scheduler for Johnston Products, tried, he couldn't seem to get it through people's minds. They kept trying to "front load" the production schedule, and the problem appeared to be getting worse.
By "front loading" Justin meant that production supervisors would attempt to catch up with production they failed to make the previous week. It seemed to happen every week, and the only way Justin could get things back to a realistic position was to completely reconstruct the entire master schedule-usually about every three weeks.

Last month could serve as an example. The first week of the month Justin had scheduled production equal to 320 standard hours in the assembly area. The assembly area managed to complete only 291 hours that week because of some equipment maintenance and a few unexpected part shortages. The assembly supervisor then had the workers complete the remaining 29 hours from week 1 at the start of week 2. Since week 2 already had 330 standard hours scheduled, the additional 29 hours really put them in a position of attempting to complete 359 hours. The workers actually completed 302 hours in week 2, leaving 57 hours to front load into week 3, and so forth. Usually by the time Justin came to his three-week review of the master schedule, it was not uncommon for the assembly area to be more than 100 standard hours behind schedule.
Clearly something needed to be done. Justin decided to review some of the areas that could be causing the problem:

1. Job standards-Although it had been at least four years since any job standards had been reviewed or changed, Jason felt the standards could not be the problem- quite the opposite. His operations course had taught him about the concept of the learning curve, implying that if anything the standards should be too large, allowing the average worker to complete even more production than implied by the job standard.

2. Utilization-The general manager was very insistent on high utilization of the area. He felt that it would help control costs, and consequently used utilization as a major performance measure for the assembly area. The problem was that customer service was also extremely important. With the problems Justin was having with the master schedule, it was difficult to promise order delivery accurately, and equally difficult to deliver the product on time once the order promise was made.

3. The workers-In an effort to control costs, the hourly wage for the workers was not very high. This caused a turnover in the workforce of almost 70% per year. In spite of this, the facility was located in an area where replacement workers were fairly easy to hire. They were assigned to the production area after they had a minimum of one week's worth of training on the equipment. In the meantime, the company filled vacant positions with temporary workers brought in by a local temporary employment service.

4. Engineering changes-The design of virtually all the products was changing, with the average product changing some aspect of the design about every two months. Usually this resulted in an improvement to the products, however, so Justin quickly dismissed the changes as a problem. There were also some engineering changes on the equipment, but in general little in the way of process change had been made. The setup time for a batch of a specific design had remained at about 15 minutes. That forced a batch size of about from 50 to 300 units, depending on the design. The equipment was getting rather old, however, forcing regular maintenance as well as causing an occasional breakdown. Each piece of equipment generally required about three hours of maintenance per week.

Since the computer had done most of his calculations in the past, Justin decided to check to see if the computer was the source of the problem. He gathered information to conduct a manual calculation on a week when there were eight people assigned to the assembly area (one person for each of eight machines) for one shift per day. With no overtime, that would allow 320 hours of production.


Case Analysis

1. With this information, Justin calculated the total standard time required to be within the 320 hours available. Is he correct?

Calculate the time required and check the accuracy of his calculation.

2. List the areas you think are causing trouble in this facility.

3. Develop a plan to deal with the situation and try to get the production schedule back under control under the constraints listed.

Civil Engineering, Engineering

  • Category:- Civil Engineering
  • Reference No.:- M91789595

Have any Question?


Related Questions in Civil Engineering

Masonry design assignmentquestion 1 - derivation of seismic

MASONRY DESIGN ASSIGNMENT Question 1 - Derivation of seismic actions on building a) Determine the storey seismic weights (Wi) for each suspended level of the building, hence the seismic weight (Wt) of the entire building ...

The drainage system of a cantilever wall shown in below

The drainage system of a cantilever wall shown in below figure, became blocked after a heavy rainstorm and the groundwater level, which was originallybelow the base, rose to1.5 (m) below the surface. Determine the stabil ...

Civilyou are provided with bill of quantities prepared

Civil You are provided with bill of quantities prepared separately, priced and submitted by 3 con- tractors (A,B,C found on LMS) in respect of a proposed project (see appendix for drawings). The site is located on Mt. Al ...

Assessment taskpractical investigationinstructions- it is

Assessment Task Practical Investigation Instructions: - It is very important that you read these instructions. - The hardcopy of the Assignment report, with the Assignment cover sheet, should be submitted to the Assignme ...

Aimthis assignment aims to demonstrate the structural

Aim: This assignment aims to demonstrate the structural design requirements of a glazed façade in a multi-storey building. Among other requirements, the glazed façade is required to comply with Australian Standard AS 204 ...

Task details the client is doing masters in civil

Task Details: The client is doing Masters in Civil Engineering. He needs a Technical Paper on Earthquake pertaining to Geology and Rock Mechanics. There should be a through discussion of Earthquake in relation to the men ...

1 aimthe assignment aims to develop the ability to analyse

1. Aim The assignment aims to develop the ability to analyse, evaluate, research plan and manage a major building project through individual and group participation (ideally 4-6 people).Refer to vUWS for the DA plans and ...

Assignment -ewb design report format - cover page - the as

Assignment - EWB Design Report Format - Cover page - The as EWB project Table of content Introduction about -EWB and CRDT (Cambodian Rural development team) Background about Cambodia - Economic, Weather, People - living ...

Masonry design assignmentquestion 1 - derivation of seismic

MASONRY DESIGN ASSIGNMENT Question 1 - Derivation of seismic actions on building a) Determine the storey seismic weights (Wi) for each suspended level of the building, hence the seismic weight (Wt) of the entire building ...

Aimthis assignment aims to demonstrate the structural

Aim: This assignment aims to demonstrate the structural design requirements of a glazed façade in a multi-storey building. Among other requirements, the glazed façade is required to comply with Australian Standard AS 204 ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As