Ask Question, Ask an Expert

+1-415-315-9853

info@mywordsolution.com

Ask Mechanical Engineering Expert

1. Determine the cost of generation per kW-hr from data given below.

Capacity of the plant - 120MW
Capital cost - Rs.1,200 per kW installed
Interest and depreciation - 10 %on capital
Fuel consumption - 1.2 kg / kW-hr.
Fuel cost - Rs. 40 tone
Salaries, wages, repairs and maintenance - 6, 00,000 / year

Maximum demand is 80 MW and load factor is 40 %.

2. Central power station has annual factors which are given below:

Load factor = 60%
Capacity factor = 40%
Use factor = 45%
Power station has a maximum demand of 15,000kW.

Find out; Annual energy production, Reserve capacity over and above peak load, Hours per year not in service.

3. A power station has two 60MW units each running for 1500hours a year. Energy produced per year is 700 x 106 kW-hr. Compute the plant load factor and plant use factor.

4. a) Design and describe the two pool tidal power plant.

b) describe with help of neat and suitable sketch the working of solar thermal receiver system plant and prepare down the advantages and disadvantages of concentrating collectors over flat plate collectors.

5. Describe the various system used for generating power by using geothermal energy.

6. What do you mean by power plant economics? Describe the fixed costs and operating costs of the power station.

Mechanical Engineering, Engineering

  • Category:- Mechanical Engineering
  • Reference No.:- M911716

Have any Question? 


Related Questions in Mechanical Engineering

Why is a combination of torque and angle measurement or

Why is a combination of torque and angle measurement or control so popular in mass production operations? What is meant by window control? What is meant by yield control in mass production applications? Does tightening a ...

Calculate the power factor of an electronic system subject

Calculate the power factor of an electronic system subject to a reasonable amount of harmonics given as THD(v) = 1.0%, the displacement factor is 0.92. What would be the calculated error if harmonic components were not t ...

I need a proposal project for surface metrology asap i need

I need a proposal project for Surface Metrology ASAP. I need two documents: 1. Project outlines Proposal outlines (the instruction & template is in the attached Proposal for the project) should be 1 page 2. Final project ...

Asignmentnote all dimensions are in mm unless stated

ASSIGNMENT Note: All dimensions are in mm unless stated otherwise. A steel frame is shown in Figure 1. The steel used is ASTM A572 Grade 50. It consists of two span and braced by an arrangement of trusses at the right si ...

Calculate the fraction of n2 molecules in a sample at 298 k

Calculate the fraction of N2 molecules in a sample at 298 K that have speeds less than 10.0ms -1 by integrating the Maxwell-Boltzmann distribution over the appropriate range of speeds (just writing the correct integral i ...

The figure illustrates the operation of an air lift pump

The figure illustrates the operation of an air lift pump. Compressed air is forced into a perforated chamber to mix with the water so that the specific gravity of the air-water mixture above the air inlet is 0.5. Neglect ...

Assume that the level of water in the tank remains the same

Assume that the level of water in the tank remains the same and that there is no friction loss in the pipe, entrance, or nozzle. Determine (a) The volumetric discharge rate from the nozzle; (b) The pressure and velocity ...

In problem above find the depth at which the net force on

In Problem above, find the depth at which the net force on the tank is zero. Problem :- On a certain day the barometric pressure at sea level is 30.1 in. Hg, and the temperature is 708F. The pressure gage in an airplane ...

Rework problem if the exit velocity profile is given bywhen

Rework Problem. if the exit velocity profile is given by when y is measure vertically from the center line of the water tunnel. Problem A two-dimensional object is placed in a 4-ft-wide water tunnel as shown. The upstrea ...

A watertight bulkhead 22 ft high forms a temporary dam for

A watertight bulkhead 22 ft high forms a temporary dam for some construction work. The top 12 ft behind the bulkhead consists of sea water with a density of 2 slugs/ft 3  , but the bottom 10 ft begin a mixture of mud and ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

WalMart Identification of theory and critical discussion

Drawing on the prescribed text and/or relevant academic literature, produce a paper which discusses the nature of group

Section onea in an atwood machine suppose two objects of

SECTION ONE (a) In an Atwood Machine, suppose two objects of unequal mass are hung vertically over a frictionless

Part 1you work in hr for a company that operates a factory

Part 1: You work in HR for a company that operates a factory manufacturing fiberglass. There are several hundred empl

Details on advanced accounting paperthis paper is intended

DETAILS ON ADVANCED ACCOUNTING PAPER This paper is intended for students to apply the theoretical knowledge around ac

Create a provider database and related reports and queries

Create a provider database and related reports and queries to capture contact information for potential PC component pro