Construction Cost Estimate Assignment

A land developer plans to build a new building on a site that has marginal soil conditions. The geotechnical engineer has identified two alternative foundation systems for this proposed building:

Alternative 1: Support the building on pile foundations that extend through the marginal soils into the deeper stronger soils.

Alternative 2: Excavate the upper 10 feet of soil and replace it as a compacted fill. The proposed building may then be supported on spread footing foundations founded on the compacted fill.

Both alternatives will use a slab-on-grade floor. In addition, both alternatives will produce a foundation system with equal quality and reliability, and the construction time will be about the same. Neither will require any future maintenance. Thus, the only consideration in selecting the final design is the respective cost of the foundation construction.

The structural engineer developed preliminary design drawings for both alternatives, and these drawings show the following:

• The proposed building will be rectangular with plan dimensions of 150 ft by 200 ft. It will have 35 interior columns and all of the perimeter walls will be bearing walls.

• For Alternative 1, each column will require four piles, each of which must be 25 ft long. In addition, each column will require a 5x5x3 ft reinforced concrete pile cap. The exterior bearing walls will require 25 ft long piles at 10 ft on center, and a 2x2 ft reinforced grade beam along the base of the wall.

• For Alternative 2, each column will require a 10x10x3 ft reinforced concrete spread footing, and the exterior bearing walls will require a 3x2 ft reinforced concrete continuous spread footing.

The civil engineer developed a preliminary site plan and grading plan. For Alternative 2, the excavation and recompaction will extend 10 ft beyond the building footprint, as recommended by the geotechnical engineer. The civil engineer also determined that Alternative 2 will require 1800 cubic yards of import fill to make up for the shrinkage that will occur during the excavation and recompaction process.

Develop hand-drawn sketches of each alternative showing the relevant items needed to develop the cost estimate. Include relevant dimensions.

The unit cost information is as follows: Excavation and recompaction Materials $0

Equipment and labor $5.00 / yd3

Overhead and profit 10% of the materials, labor, and equipment costs

Import fill

Materials $20.00 / yd3

Equipment and labor $4.00 / yd3

Overhead and profit 10% of the materials, labor, and equipment costs

Pile foundations
Materials $27.00 / ft
Equipment and labor $9.50 / ft
Overhead and profit 10% of the materials, labor, and equipment costs

Reinforced concrete for pile caps and grade beams; includes excavation costs Materials $180.00 / yd3
Equipment and labor $230.00 / yd3
Overhead and profit 10% of the materials, labor, and equipment costs

Reinforced concrete for footings; includes excavation costs Materials $150.00 / yd3
Equipment and labor $200.00 / yd3
Overhead and profit 10% of the materials, labor, and equipment costs

Compute the construction quantity take offs and develop construction cost estimates for both alternatives.

Item

Quantity

Units

Materials

Equipment and Labor

Total Cost

Unit Cost

Cost

Unit Cost

Cost

Insulation R19

2000

sf

$0.20

$400

$0.18

$360

$760

Insulation R30

2300

sf

$0.28

$644

$0.20

$460

$1104

Drywall

4300

sf

$0.40

$1720

$0.62

$2666

$4386

Paint

4300

sf

$0.15

$645

$0.20

$860

$1505

Subtotal

 

 

 

 

 

 

$7755

10% overhead and profit

 

 

 

 

 

 

$775

Total

 

 

 

 

 

 

$8530

Based on the results of this analysis, recommend a course of action.

Your submittal should include:

• A cover sheet with the course name, the name of the assignment, your name, the submittal date, and any other information you deem to be relevant

• The hand-drawn sketches of each alternative

• Your quantity take offs and cost estimates presented as shown above with the relevant hand and/or spreadsheet calculations as needed.

• Short statement of your recommended course of action

Civil Engineering, Engineering

  • Category:- Civil Engineering
  • Reference No.:- M91585476
  • Price:- $180

Guranteed 48 Hours Delivery, In Price:- $180

Have any Question?


Related Questions in Civil Engineering

1 aimthe assignment aims to develop the ability to analyse

1. Aim The assignment aims to develop the ability to analyse, evaluate, research plan and manage a major building project through individual and group participation (ideally 4-6 people).Refer to vUWS for the DA plans and ...

Task details the client is doing masters in civil

Task Details: The client is doing Masters in Civil Engineering. He needs a Technical Paper on Earthquake pertaining to Geology and Rock Mechanics. There should be a through discussion of Earthquake in relation to the men ...

Assignmenta continuous three spans beam with

Assignment A continuous three spans beam with centre-to-centre distance of 6 m supports 150 mm thick one-way slabs as shown below. The beams have clear spans of 8 m, 9 m, and 8 (face-to-face of 400 mm square columns). Th ...

Assignment -ewb design report format - cover page - the as

Assignment - EWB Design Report Format - Cover page - The as EWB project Table of content Introduction about -EWB and CRDT (Cambodian Rural development team) Background about Cambodia - Economic, Weather, People - living ...

Aimthis assignment aims to demonstrate the structural

Aim: This assignment aims to demonstrate the structural design requirements of a glazed façade in a multi-storey building. Among other requirements, the glazed façade is required to comply with Australian Standard AS 204 ...

Masonry design assignmentquestion 1 - derivation of seismic

MASONRY DESIGN ASSIGNMENT Question 1 - Derivation of seismic actions on building a) Determine the storey seismic weights (Wi) for each suspended level of the building, hence the seismic weight (Wt) of the entire building ...

Civilyou are provided with bill of quantities prepared

Civil You are provided with bill of quantities prepared separately, priced and submitted by 3 con- tractors (A,B,C found on LMS) in respect of a proposed project (see appendix for drawings). The site is located on Mt. Al ...

The drainage system of a cantilever wall shown in below

The drainage system of a cantilever wall shown in below figure, became blocked after a heavy rainstorm and the groundwater level, which was originallybelow the base, rose to1.5 (m) below the surface. Determine the stabil ...

Aimthis assignment aims to demonstrate the structural

Aim: This assignment aims to demonstrate the structural design requirements of a glazed façade in a multi-storey building. Among other requirements, the glazed façade is required to comply with Australian Standard AS 204 ...

Assessment taskpractical investigationinstructions- it is

Assessment Task Practical Investigation Instructions: - It is very important that you read these instructions. - The hardcopy of the Assignment report, with the Assignment cover sheet, should be submitted to the Assignme ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As