Ask Civil Engineering Expert

Consider the aggregate planning problem discussed in Example 2.13 (Section 2.15). Discuss how the LP formulation will change if the following constraints are added.

(a) Union regulation requires that no more than 10% of the workforce can be laid off in any month.

(b) The personnel department estimates that no more than 50 trainees can be hired in any month.

(c) The company wants to limit the change in workforce from 1 month to the next to 10 workers.

(d) Company's warehouse limits the monthly inventory to 120 units.

Example 2.13

A parts supplier has a contract with an OEM to supply 1550 units of some component C for the next 6 months. Table 2.10 gives the OEM's monthly requirements during the contract period. The supplier has 20 workers and 50 units of C on hand now. Each worker can produce 10 units of C per month. The company can recruit from the local labor market, but the recruits have to be trained for 1 month by a worker before they can be used in production. Each worker can train at most five recruits during a month. A worker is paid $3000 per month, when used in production or training. A worker can be laid off at a cost of $2000 per month. Firing a worker costs $5000. Each recruit is paid $1500 during training. Production ahead of schedule incurs an inventory holding cost of $50 per unit per month. Each unit of C not delivered on schedule involves a penalty cost of $75 per month until delivery is completed. However, all deliveries must be completed in 6 months. The supplier requires a final labor force of 30 workers and 50 units of C at the end of the 6th month. The aggregate planning problem is to decide what hiring, firing, producing, storing, and shortage policy the supplier should follow in order to minimize the total costs during the contract period. Formulate this problem as an LP model and solve. Discuss the production plan.

1004_6508ac58-8487-4e9c-8a1e-18bbfb708afd.png

Civil Engineering, Engineering

  • Category:- Civil Engineering
  • Reference No.:- M92218511

Have any Question?


Related Questions in Civil Engineering

Assignment -ewb design report format - cover page - the as

Assignment - EWB Design Report Format - Cover page - The as EWB project Table of content Introduction about -EWB and CRDT (Cambodian Rural development team) Background about Cambodia - Economic, Weather, People - living ...

Assessment taskpractical investigationinstructions- it is

Assessment Task Practical Investigation Instructions: - It is very important that you read these instructions. - The hardcopy of the Assignment report, with the Assignment cover sheet, should be submitted to the Assignme ...

Task details the client is doing masters in civil

Task Details: The client is doing Masters in Civil Engineering. He needs a Technical Paper on Earthquake pertaining to Geology and Rock Mechanics. There should be a through discussion of Earthquake in relation to the men ...

Aimthis assignment aims to demonstrate the structural

Aim: This assignment aims to demonstrate the structural design requirements of a glazed façade in a multi-storey building. Among other requirements, the glazed façade is required to comply with Australian Standard AS 204 ...

Masonry design assignmentquestion 1 - derivation of seismic

MASONRY DESIGN ASSIGNMENT Question 1 - Derivation of seismic actions on building a) Determine the storey seismic weights (Wi) for each suspended level of the building, hence the seismic weight (Wt) of the entire building ...

Masonry design assignmentquestion 1 - derivation of seismic

MASONRY DESIGN ASSIGNMENT Question 1 - Derivation of seismic actions on building a) Determine the storey seismic weights (Wi) for each suspended level of the building, hence the seismic weight (Wt) of the entire building ...

Aimthis assignment aims to demonstrate the structural

Aim: This assignment aims to demonstrate the structural design requirements of a glazed façade in a multi-storey building. Among other requirements, the glazed façade is required to comply with Australian Standard AS 204 ...

Assignmenta continuous three spans beam with

Assignment A continuous three spans beam with centre-to-centre distance of 6 m supports 150 mm thick one-way slabs as shown below. The beams have clear spans of 8 m, 9 m, and 8 (face-to-face of 400 mm square columns). Th ...

The drainage system of a cantilever wall shown in below

The drainage system of a cantilever wall shown in below figure, became blocked after a heavy rainstorm and the groundwater level, which was originallybelow the base, rose to1.5 (m) below the surface. Determine the stabil ...

Civilyou are provided with bill of quantities prepared

Civil You are provided with bill of quantities prepared separately, priced and submitted by 3 con- tractors (A,B,C found on LMS) in respect of a proposed project (see appendix for drawings). The site is located on Mt. Al ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As