Ask Question, Ask an Expert

+61-413 786 465

info@mywordsolution.com

Ask Civil Engineering Expert

Barracks logic is built out of sleeping soldiers covered by electric blankets. Each blanket has a control switch with discrete control settings ranging in S-degree (Fahrenheit) intervals from 0 to SO degrees. The temperature of a soldier covered by one or more electric blankets will be the sum of the ambient temperature in the barracks plus the setting on the controller for each blanket. Each soldier has a preferred sleeping temperature, which varies from individual to individual but is always within the range of 60 to 80 degrees, inclusive. If a soldier's temperature departs from his preferred temperature, he will wake up once every minute and adjust the control by one 5-degree increment in the direction he would like his temperature to be modified (if he is cold, he will increase the setting on his control, and vice versa). He will continue these adjustments by S-degree increments until he once again reaches his preferred temperature (and goes to sleep) or runs out of settings (in which case he grumbles angrily in bed). If every soldier is allowed to control his own blanket, each will soon reach his preferred temperature and slide into nocturnal bliss (assuming a suitable ambient temperature). The interesting aspects of barracks logic result from switching the controls of the various blankets to different soldiers. Inputs to the system are accomplished by placing a few controls in the hands of outsiders, and outputs are read from the control settings of certain soldiers designated by the logic designer.

A. Draw the graph of output control setting vs. input control setting for a typical soldier in steady state. Assume an ambient temperature of 40 degrees. Mark your graph with good choices of the valid regions for the two logical values, the forbidden zone, and the noise margins. Let logical 0 be when a control is completely off and logical 1 be when the control is completely on (or at the highest setting).

B. List some sources of noise that justify the need for noise margins.

C. Even though it is the middle of February, a sudden warm spell raises the ambient temperature in our barracks logic system to 55 degrees. Sketch a new graph of output control setting vs. input control setting in the warmer barracks.

D. Over what range of ambient temperatures will barracks logic function reliably?

E. Does the following arrangement perform a useful function? What is it?

1492_images.png

F. A model HOT-l electric blanket control can power 1200 W of blankets. A model HOT-BED electric blanket requires 275 W. What is the fanout of a HOTl? What might happen if this rating is exceeded? Is there more danger of exceeding the rating at an output value of logical 0 or logical l?

G. To create a system with multiple inputs, we allow several blankets to be placed over a single soldier. What is the maximum fanin possible in barracks logic if 170 degrees is the highest temperature a soldier can tolerate without his characteristics being permanently altered?

H. Show how to build a NOR gate and an AND gate in barracks logic.

I. Explain what causes rise time, fall time, and propagation delay in barracks logic. Give worst-case numerical values for each of these parameters for the barracks logic inverter. (Let rise time be the time from when an output leaves the valid logical 0 range until it enters the valid logical 1 range, and vice versa for fall time. For propagation delay, use the time from when the input switches to a valid logic level to the time when the output switches to a valid logic level.)

Civil Engineering, Engineering

  • Category:- Civil Engineering
  • Reference No.:- M92070642

Have any Question?


Related Questions in Civil Engineering

Civilyou are provided with bill of quantities prepared

Civil You are provided with bill of quantities prepared separately, priced and submitted by 3 con- tractors (A,B,C found on LMS) in respect of a proposed project (see appendix for drawings). The site is located on Mt. Al ...

Assignment -ewb design report format - cover page - the as

Assignment - EWB Design Report Format - Cover page - The as EWB project Table of content Introduction about -EWB and CRDT (Cambodian Rural development team) Background about Cambodia - Economic, Weather, People - living ...

Masonry design assignmentquestion 1 - derivation of seismic

MASONRY DESIGN ASSIGNMENT Question 1 - Derivation of seismic actions on building a) Determine the storey seismic weights (Wi) for each suspended level of the building, hence the seismic weight (Wt) of the entire building ...

Assessment taskpractical investigationinstructions- it is

Assessment Task Practical Investigation Instructions: - It is very important that you read these instructions. - The hardcopy of the Assignment report, with the Assignment cover sheet, should be submitted to the Assignme ...

Task details the client is doing masters in civil

Task Details: The client is doing Masters in Civil Engineering. He needs a Technical Paper on Earthquake pertaining to Geology and Rock Mechanics. There should be a through discussion of Earthquake in relation to the men ...

Aimthis assignment aims to demonstrate the structural

Aim: This assignment aims to demonstrate the structural design requirements of a glazed façade in a multi-storey building. Among other requirements, the glazed façade is required to comply with Australian Standard AS 204 ...

Assignmenta continuous three spans beam with

Assignment A continuous three spans beam with centre-to-centre distance of 6 m supports 150 mm thick one-way slabs as shown below. The beams have clear spans of 8 m, 9 m, and 8 (face-to-face of 400 mm square columns). Th ...

Aimthis assignment aims to demonstrate the structural

Aim: This assignment aims to demonstrate the structural design requirements of a glazed façade in a multi-storey building. Among other requirements, the glazed façade is required to comply with Australian Standard AS 204 ...

The drainage system of a cantilever wall shown in below

The drainage system of a cantilever wall shown in below figure, became blocked after a heavy rainstorm and the groundwater level, which was originallybelow the base, rose to1.5 (m) below the surface. Determine the stabil ...

1 aimthe assignment aims to develop the ability to analyse

1. Aim The assignment aims to develop the ability to analyse, evaluate, research plan and manage a major building project through individual and group participation (ideally 4-6 people).Refer to vUWS for the DA plans and ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As