This assessment item relates to the course learning outcomes 3 and 4.

Background information for questions 1 and 2

A Client has decided to redevelop an existing block in an in-city area by removing an old dilapidated house (existing) and constructing of a new modern two story family home.

The following information is provided regarding the development:

- This area has recently undergonetown planning changes that allow for large coverage of the site (high-density) up to 80%.
- Ground Level - Garage, laundry/storage room, kitchen, powderroom, bathroom, loungeand dining.
- Level 1 - Master Bedroom with ensuite, two other bedrooms, main bathroom, and a study.
- The site has a 12 metres street frontage (width) and a total area of 480m2.
- The block has a uniformly falling 1:25 slope along the length of the block (from street frontage to rear). Due to this slope a section of the ground level floor will be suspended.
- The ownerhas received a relaxation to build the house 400mm from one side of the block, which is directly adjacent to the neighbouring property. The neighbouring property has also received arelaxation of 400mm on this common boundary. In order to receive the building approval the building certifier has advised that this wall will need to be constructed to achieve a 60min fire rating.
- Front (street facing) and back boundary clearances are set at 4 meters each, with the remaining side boundary clearance to be at least 2m
- Due to poor soil conditions the footings must be constructed using bored piers.
- Framework is a mixture of main structural steel beams and columns with structural timber framing and infill.
- Power and water services are connected at the street frontage, both via underground.
- Stormwater and sewer are connected at the rear of the block.
- A solar hot water system and solar power system will be located on the roof.
- The roof is a butterfly skillion roof falling toward the centre of the building, with abox gutter running down the middle length of the roof.
- A small 9m2 backyard shed must be located on the block.
- The house must accommodate a family of four.
- The remaining design and material selections are your choice.

Question 1

Obtain or view with permission a set of approved house drawings, which will serve as a guide and example to complete Question 1. Then, the draw by hand (not CAD) design drawings to document the project above.

Enough drawings should be provided to sufficiently document the project, and at minimum would include:

1. A site plan
2. A floor plan for each level
3. Roof plan, showing also any plant and equipment on the roof.
4. Elevation view (either side or front elevation)
5. Section view (along the length of the home, including footing detail)
6. In-Ground Services Plan, showing connection to infrastructure to house entry point.
7. A detailed design of the required fire wall.

Maximum paper format is A3.

Time should be taken to draw accurately and neatly and list all the items that would normally be found on design plans.

Question 2 (Maximum number of slides is 10)

Build a 1:50 scale model of the house project showing the main structural and non-structural materials, services and built in furniture as covered by this subject. Photograph the model in the process of being built (just like stages in a project) and prepare a PowerPoint ‘slide show' with annotations and a voice commentary explaining the features of your model.

Marks for the model will be based on your ability to fashion component members to reasonable scale and representation of typical building works rather than showing modelling expertise. However, you are strongly encouraged to get ‘crafty' and apply your best efforts. Recommended resources forprocuring yourmodel materials can be anything from things around the house as well as going to craft, hobby and hardware stores for specificitems (E.g. Spotlight, Bunnings, Craft shops etc.).

Civil Engineering, Engineering

  • Category:- Civil Engineering
  • Reference No.:- M92324820
  • Price:- $120

Guranteed 48 Hours Delivery, In Price:- $120

Have any Question?


Related Questions in Civil Engineering

Assignment -ewb design report format - cover page - the as

Assignment - EWB Design Report Format - Cover page - The as EWB project Table of content Introduction about -EWB and CRDT (Cambodian Rural development team) Background about Cambodia - Economic, Weather, People - living ...

Assessment taskpractical investigationinstructions- it is

Assessment Task Practical Investigation Instructions: - It is very important that you read these instructions. - The hardcopy of the Assignment report, with the Assignment cover sheet, should be submitted to the Assignme ...

Task details the client is doing masters in civil

Task Details: The client is doing Masters in Civil Engineering. He needs a Technical Paper on Earthquake pertaining to Geology and Rock Mechanics. There should be a through discussion of Earthquake in relation to the men ...

Aimthis assignment aims to demonstrate the structural

Aim: This assignment aims to demonstrate the structural design requirements of a glazed façade in a multi-storey building. Among other requirements, the glazed façade is required to comply with Australian Standard AS 204 ...

Masonry design assignmentquestion 1 - derivation of seismic

MASONRY DESIGN ASSIGNMENT Question 1 - Derivation of seismic actions on building a) Determine the storey seismic weights (Wi) for each suspended level of the building, hence the seismic weight (Wt) of the entire building ...

Masonry design assignmentquestion 1 - derivation of seismic

MASONRY DESIGN ASSIGNMENT Question 1 - Derivation of seismic actions on building a) Determine the storey seismic weights (Wi) for each suspended level of the building, hence the seismic weight (Wt) of the entire building ...

Aimthis assignment aims to demonstrate the structural

Aim: This assignment aims to demonstrate the structural design requirements of a glazed façade in a multi-storey building. Among other requirements, the glazed façade is required to comply with Australian Standard AS 204 ...

Assignmenta continuous three spans beam with

Assignment A continuous three spans beam with centre-to-centre distance of 6 m supports 150 mm thick one-way slabs as shown below. The beams have clear spans of 8 m, 9 m, and 8 (face-to-face of 400 mm square columns). Th ...

The drainage system of a cantilever wall shown in below

The drainage system of a cantilever wall shown in below figure, became blocked after a heavy rainstorm and the groundwater level, which was originallybelow the base, rose to1.5 (m) below the surface. Determine the stabil ...

Civilyou are provided with bill of quantities prepared

Civil You are provided with bill of quantities prepared separately, priced and submitted by 3 con- tractors (A,B,C found on LMS) in respect of a proposed project (see appendix for drawings). The site is located on Mt. Al ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As