A double pipe concentric heat exchanger operating in counter-current mode is constructed in 5 m lengths fitted in series. Each section consists of an outer pipe of 100 mm inside diameter, and an inner pipe of 55 mm outside diameter and wall thickness of 3mm. Both pipes are made of steel with a thermal conductivity k of 16 W/mK. Steam is supplied to the shell side at 393 K and the condensate is not sub-cooled (discharged at 393 K). The duty of the exchanger is to heat 12,000 kg/hour of process fluid from an inlet temperature of 283 K to an outlet temperature of 353 K. The heat transfer coefficient of condensing steam is 8000 W/m2K.

Physical properties of the process fluid at the mean bulk temperature of 318K are as follows:

Thermal conductivity k = 0.17 W/mK

Density ? = 800 kg/m3

Viscosity ? = 0.3 mNs/m2

The specific heat capacity Cp of the process fluid is not known at the mean bulk fluid temperature but is a linear function of temperature, and must be calculated using the following information, Cp at 300K is 1.98 kJ/kgK, and Cp at 400K is 2.65 kJ/kgK

To estimate the film coefficient for the inner pipe, use the Nusselt correlation as given below:

Hence or otherwise determine

(i) The flow velocity of the process fluid

(ii) The inside heat transfer coefficient

(iii) The overall heat transfer coefficient U

(iv) The heat transferred based on the heating of the process fluid

(v) The number of heat exchanger sections required to meet the duty

Civil Engineering, Engineering

  • Category:- Civil Engineering
  • Reference No.:- M91096394

Have any Question?


Related Questions in Civil Engineering

Assignmenta continuous three spans beam with

Assignment A continuous three spans beam with centre-to-centre distance of 6 m supports 150 mm thick one-way slabs as shown below. The beams have clear spans of 8 m, 9 m, and 8 (face-to-face of 400 mm square columns). Th ...

Masonry design assignmentquestion 1 - derivation of seismic

MASONRY DESIGN ASSIGNMENT Question 1 - Derivation of seismic actions on building a) Determine the storey seismic weights (Wi) for each suspended level of the building, hence the seismic weight (Wt) of the entire building ...

The drainage system of a cantilever wall shown in below

The drainage system of a cantilever wall shown in below figure, became blocked after a heavy rainstorm and the groundwater level, which was originallybelow the base, rose to1.5 (m) below the surface. Determine the stabil ...

Aimthis assignment aims to demonstrate the structural

Aim: This assignment aims to demonstrate the structural design requirements of a glazed façade in a multi-storey building. Among other requirements, the glazed façade is required to comply with Australian Standard AS 204 ...

Task details the client is doing masters in civil

Task Details: The client is doing Masters in Civil Engineering. He needs a Technical Paper on Earthquake pertaining to Geology and Rock Mechanics. There should be a through discussion of Earthquake in relation to the men ...

Assignment -ewb design report format - cover page - the as

Assignment - EWB Design Report Format - Cover page - The as EWB project Table of content Introduction about -EWB and CRDT (Cambodian Rural development team) Background about Cambodia - Economic, Weather, People - living ...

1 aimthe assignment aims to develop the ability to analyse

1. Aim The assignment aims to develop the ability to analyse, evaluate, research plan and manage a major building project through individual and group participation (ideally 4-6 people).Refer to vUWS for the DA plans and ...

Civilyou are provided with bill of quantities prepared

Civil You are provided with bill of quantities prepared separately, priced and submitted by 3 con- tractors (A,B,C found on LMS) in respect of a proposed project (see appendix for drawings). The site is located on Mt. Al ...

Masonry design assignmentquestion 1 - derivation of seismic

MASONRY DESIGN ASSIGNMENT Question 1 - Derivation of seismic actions on building a) Determine the storey seismic weights (Wi) for each suspended level of the building, hence the seismic weight (Wt) of the entire building ...

Assessment taskpractical investigationinstructions- it is

Assessment Task Practical Investigation Instructions: - It is very important that you read these instructions. - The hardcopy of the Assignment report, with the Assignment cover sheet, should be submitted to the Assignme ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As