Ask Question, Ask an Expert

+61-413 786 465

info@mywordsolution.com

Ask Civil Engineering Expert

A 2m x 2m footing has to carry a column load of 1000 kN. The ground water table is at a depth of 2m, and the saturated unit weight of the stiff clay layer is 21 kN/m3. Consolidation test was conducted on the undisturbed clay sample, and one increment of loading data with time is presented in the following table. At "0" time, the sample height was 2.314 cm, and the void ratio was 0.7. Perform the following tasks:

TASK 1: What is the sample height and void ratio after 24 hours?

TASK 2: What is the Compression Index Cc during this load increment?

TASK 3: What is the Coefficient of Consolidation, Cv ?

TASK 4: If the modulus of elasticity of the top sand layer is 35,000 kPa, then what is the strain in that layer after the construction of the footing?

TASK 5: What is the consolidation settlement of the clay layer due to 1000 kN load? Assume that the soil is normally consolidated.

TASK 6: What is the total settlement under the footing?

TASK 7: How long will it take for that settlement to occur?

TASK 8: How long will it take for the clay layer to settle 60% of the above settlement?

TASK 9: What is the excess pore water pressure in the clay layer right after the application of the load?

TASK 10: What is the remaining excess pore water pressure at 4 m into the clay layer after the time calculated in Task 8?

TASK 11: (a) Draw a soil element in the middle of the clay layer and show all stresses. Assume that the horizontal stress 50% of the vertical stress. (b) Draw the Mohr's Circle for this stress state. (c) Determine the pole and show all steps. (d) What are the principal stresses? (e) What is the maximum shear stress? (f) What are the stress conditions on a plane inclined at 40 degrees to the horizontal? (g) Show the stress conditions of (f) on the element drawn in (a).

Civil Engineering, Engineering

  • Category:- Civil Engineering
  • Reference No.:- M9885468

Have any Question?


Related Questions in Civil Engineering

Civilyou are provided with bill of quantities prepared

Civil You are provided with bill of quantities prepared separately, priced and submitted by 3 con- tractors (A,B,C found on LMS) in respect of a proposed project (see appendix for drawings). The site is located on Mt. Al ...

The drainage system of a cantilever wall shown in below

The drainage system of a cantilever wall shown in below figure, became blocked after a heavy rainstorm and the groundwater level, which was originallybelow the base, rose to1.5 (m) below the surface. Determine the stabil ...

Masonry design assignmentquestion 1 - derivation of seismic

MASONRY DESIGN ASSIGNMENT Question 1 - Derivation of seismic actions on building a) Determine the storey seismic weights (Wi) for each suspended level of the building, hence the seismic weight (Wt) of the entire building ...

Task details the client is doing masters in civil

Task Details: The client is doing Masters in Civil Engineering. He needs a Technical Paper on Earthquake pertaining to Geology and Rock Mechanics. There should be a through discussion of Earthquake in relation to the men ...

Assignment -ewb design report format - cover page - the as

Assignment - EWB Design Report Format - Cover page - The as EWB project Table of content Introduction about -EWB and CRDT (Cambodian Rural development team) Background about Cambodia - Economic, Weather, People - living ...

Masonry design assignmentquestion 1 - derivation of seismic

MASONRY DESIGN ASSIGNMENT Question 1 - Derivation of seismic actions on building a) Determine the storey seismic weights (Wi) for each suspended level of the building, hence the seismic weight (Wt) of the entire building ...

Assessment taskpractical investigationinstructions- it is

Assessment Task Practical Investigation Instructions: - It is very important that you read these instructions. - The hardcopy of the Assignment report, with the Assignment cover sheet, should be submitted to the Assignme ...

1 aimthe assignment aims to develop the ability to analyse

1. Aim The assignment aims to develop the ability to analyse, evaluate, research plan and manage a major building project through individual and group participation (ideally 4-6 people).Refer to vUWS for the DA plans and ...

Assignmenta continuous three spans beam with

Assignment A continuous three spans beam with centre-to-centre distance of 6 m supports 150 mm thick one-way slabs as shown below. The beams have clear spans of 8 m, 9 m, and 8 (face-to-face of 400 mm square columns). Th ...

Aimthis assignment aims to demonstrate the structural

Aim: This assignment aims to demonstrate the structural design requirements of a glazed façade in a multi-storey building. Among other requirements, the glazed façade is required to comply with Australian Standard AS 204 ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As