12-1 Using the information in Table 12-7, construct a PERT network and answer each of the following questions:

 

Activity

Predecessor

Time Estimates

(weeks)

 

Secure state approval

 

4

 

Identify 20-bed unit to be used

A

1

 

Move existing residence

B

1

 

Clean space

C

2

 

Develop architectural plan

A

9

 

Install heating and ventilation system

E

4

 

Install security systems

E

2

 

Move walls; renovate

F

4

 

Identify new equipment

A

1

 

Order new equipment

I

1

K

 

 Unpack and inspect new equipment

J

1

 

Install new equipment

D,K,H

3

 

Reassign staff

A

1

N

 

Identify new staffing needs

M

1

 

Advertise for new staff

N

3

 

Interview for new staff

O

2

 

Select new hires

P

3

R

 

 Develop care plan protocols

M

1

 

Train staff

R, Q, M, L

1

 

Modify quality assurance plans

S

2

U

 

Coordinate with hospital discharge planners

T

4

 

Complete Internal Audit

U,G

1

a. What is the expected project completion data?

b. What is the scheduled start and completion date for each activity?

c. Which activities are on the critical path?

d. How long can noncritical path activities be delayed without jeopardizing the overall completion date for this project?

12-2 Assess the impact of the following changes to the time estimates provided in question 12-1. Individually, what is the impact if:

Activity

Predecessor

New Time Estimate

O. Advertise for new staff

N

4

P. Interview for new staff

O

6

Q. Select new staff

P

1

Collectively, what is the impact of these changes?

  • 12-3 As project manager for the example included in question 12-1, what would you recommend to preserve the original project completion date if activity A was reestimated to take 8 weeks, not the original 4 weeks? Provide details.
  • 13-1 A representative of a reputable financial services company has approached you as manager of a four-person group of anesthesiologists with an opportunity to purchase a 10-year annuity due for each member of the group. The annuity due would pay $40,000 each year beginning 5 years from now (i.e., at time = 5). What is the most you would be willing to pay now, per each physician, for this investment? Assume an appropriate discount rate of 7%.
  • 13-2 The hospital's marketing and finance departments have just provided you, as chief financial officer, with pro forma income statements for your proposed sonogram center. These statements appear in the following. Pro forma Income Statement (000)

Time

t + 1

t + 2

t + 3

t + 4

Service Revenues (net)

$425

$500

$580

$700

Expenses

$400

$450

$525

$600

Depreciation Expense

mce_markernbsp;35

mce_markernbsp;35

mce_markernbsp;35

mce_markernbsp;35

Net Income

($ 10)

mce_markernbsp;15

mce_markernbsp;20

mce_markernbsp;65

  • What is the project's IRR? Assume an initial investment of $175,000 and an appropriate discount rate of 6%. The hospital is operated as a not-for-profit facility.
  • 13-3 The chief operating officer (COO) of a small, not-for-profit community hospital has to make a recommendation to the board of trustees on choosing among three project options for an unrestricted gift of $250,000 that has just been received. The board has established a time horizon of 5 years on this project. The options are described in the following.
    • a. Purchase a 5-year treasury note at an interest rate (annual) of 7%.
    • b. Purchase the practice of a young physician (the hospital's third highest admitter). Estimates of projected cash flows for the practice (post-purchase), are: Probability of Cash Flow

Time

60%

20%

20%

t + 1

mce_markernbsp;40,000

$20,000

mce_markernbsp;60,000

t + 2

mce_markernbsp;60,000

$30,000

mce_markernbsp;80,000

t + 3

mce_markernbsp; 75,000

$40,000

$100,000

t + 4

$100,000

$50,000

$125,000

t + 5

$100,000

$50,000

$125,000

c. Purchase an upgraded analyzer for the laboratory. Based on forecasts of laboratory utilization, the net cash flows for this project are:

Time

Net Cash Flow

t + 1

$75,000

t + 2

$75,000

t + 3

$50,000

t + 4

$50,000

t + 5

$50,000

  • Which investment should the COO recommend and why?

Science, Academics

  • Category:- Science
  • Reference No.:- M91391063

Have any Question?


Related Questions in Science

Physiology signature assignment -for your signature

Physiology: Signature Assignment - For your signature assignment, compose a 3- to 4-page case analysis (in addition to a title, abstract, and a reference page) written in APA format with at least 3 references, with one n ...

Course descriptionthis course provides an opportunity for

Course Description This course provides an opportunity for nursing students to enhance their knowledge of historical and contemporary issues relevant to Aboriginal and Torres Strait Islander people. This course will expl ...

Individual work - personal reflectionreflect on the roles

Individual work - personal reflection Reflect on the roles you performed in this group task and reflect on the ways you impacted on the group. Describe some of the things that you did that were helpful to the group. Desc ...

A do research or find a peer-reviewed scholarly journal

A. Do research or find a peer-reviewed, scholarly journal article that is related to leadership and motivation with emphasis on morality, write a short summary of the content of the article. If it is not a scholarly jour ...

Rationalesafety and risk management are critical aspects of

Rationale Safety and Risk Management are critical aspects of a workplace and breaches are punishable under Work Health and Safety Law. This task encourages students to analyse and conceptualise responses to safety breach ...

Rationalesafety and risk management are critical aspects

Rationale Safety and Risk Management are critical aspects of a workplace and breaches are punishable under Work Health and Safety Law. This task encourages students to analyse and conceptualise responses to safety breach ...

Midterm exam questions -q1 you are asked to evaluate a

Midterm Exam Questions - Q1. You are asked to evaluate a construction/building project in an area corresponding to the sketch map below. The area has mildly hilly topography and thin soil cover. The bedrock in area X is ...

Assignment -in addition to turning in your isite journal

Assignment - In addition to turning in your iSite journal entry as usual, a short paper with emphasis on writing in a scientific format, properly acknowledging resources, and an overview of the process of thermoregulatio ...

Critical appraisal requirementscritically appraise review

Critical appraisal requirements Critically appraise (review) the literature pertaining to human factors related to work performance and critically analyse the relationship between these and quality and safety in health c ...

Question in a 3 page paper compare and contrast food

Question: In a 3 page paper compare and contrast food insecurity issues in urban environments vs. rural environments. Discuss the role of food security as compared to food justice. The response must be typed, single spac ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As