1. Consider the following project network and activity times (in weeks):

608_029826EC-6BD2-4A39-B2DA-4E649B9F08B7.jpeg

Activity

A

B

C

D

E

F

G

H

Time

5

3

7

6

7

3

10

8

a. Identify the critical path.

b. How much time will be needed to complete this project?

c. Can activity D be delayed without delaying the entire project? If so, by how many weeks?

d. Can activity C be delayed without delaying the entire project? If so, by how many weeks?

e. What is the schedule for activity E?

2. Davison Construction Company is building a luxury lakefront home in the Finger Lakes region of New York. Coordination of the architect and subcontractors will require a major effort to meet the 44-week (approximately 10-month) completion date requested by the owner. The Davison project manager prepared the following project network:

608_029826EC-6BD2-4A39-B2DA-4E649B9F08B7.jpeg

Estimates of the optimistic, most probable, and pessimistic times (in weeks) for the activities are as follows:

Activity

Optimistic

Most Probable

Pessimistic

A

4

8

12

B

6

7

8

C

6

12

18

D

3

5

7

E

6

9

18

F

5

8

17

G

10

15

20

H

5

6

13

a. Find the critical path.

b. What is the expected project completion time?

c. Based only on the critical path, what is the estimated probability the project can be completed in the 44 weeks as requested by the owner?

d. Based only on the critical path, what is the estimated probability the building project could run more than 3 months late? Use 57 weeks for this calculation.

e. What should the construction company tell the owner?

3. Embassy Club Condominium, located on the west coast of Florida, is undertaking a summer renovation of its main building. The project is scheduled to begin May 1, and a September 1 (17-week) completion date is desired. The condominium manager identified the following renovation activities and their estimated times:

Activity

Immediate Predecessor

Time

A

-

3

B

-

1

C

-

2

D

A, B, C

4

E

C, D

5

F

A

3

G

D, F

6

H

E

4

a. Draw a project network.

b. What are the critical activities?

c. What activity has the most slack time?

d. Will the project be completed by September 1?

4. At a local university, the Student Commission on Programming and Entertainment (SCOPE) is preparing to host its first rock concert of the school year. To successfully pro¬duce this rock concert, SCOPE has listed the requisite activities and related information in the following table (duration estimates measured in days).

Activity

Immediate Predecessor(s)

Optimistic

Most Probable

Pessimistic

A: Negotiate contract with selected musicians

-

8

10

15

B: Reserve site

-

7

8

9

C: Manage travel logistics for music group

A

5

6

10

D: Screen & hire security personnel

B

3

3

3

E: Arrange advertising

B, C

1

5

9

F: Hire parking staff

D

4

7

10

G: Arrange concession sales

E

3

8

10

a. Draw the project network.
b. Compute the expected duration and variance of each activity.
c. Determine the critical path in the project network.
d. What is the expected duration and variance of the critical path?
e. What is the likelihood that the project will be completed within 30 days?
f. If activity B is delayed by six days beyond its early start time, how does this affect the expected project duration?

5. The manager of the Oak Hills Swimming Club is planning the club's swimming team program. The first team practice is scheduled for May 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are as follows:

Activity Description  Immediate Predecessor Optimistic Time (weeks) Most Probable Pessimistic
A Meet with board - 1 1 2
B Hire coaches A 4 6 8
C Reserve pool A 2 4 6
D Announce program B. C 1 2 3
E Meet with coaches B 2 3 4
F Order team suits A 1 2 3
G Register swimmers D 1 2 3
H Collect fees G 1 2 3
I Plan first practice E, H, F 1 1 1

a. Draw a project network.
b. Develop an activity schedule.
c. What are the critical activities, what is the expected project completion time?
d. If the club manager plans to start the project on February 1, what is the probability the swimming program will be ready by the scheduled May 1 date (13 weeks)? Should the manager begin planning the swimming program before February 1?

6. The product development group at Landon Corporation has been working on a new computer software product that has the potential to capture a large market share. Through outside sources, Landon's management learned that a competitor is working to introduce a similar product. As a result, Landon's top management increased its pressure on the product development group.

The group's leader turned to PERT/CPM as an aid to scheduling the activities remaining before the new product can be brought to the market. The project network is as follows:

608_029826EC-6BD2-4A39-B2DA-4E649B9F08B7.jpeg

The activity time estimates (in weeks) are as follows:

Activity Optimistic Most Probable Pessimistic
A 3 4 5
B 3 3.5 7
C 4 5 6
D 2 3 4
E 6 10 14
F 7.5 8.5 12.5
G 4.5 6 7.5

7.

 608_029826EC-6BD2-4A39-B2DA-4E649B9F08B7.jpeg

Activity

A

B

C

D

E

F

G

H

Time

5

3

7

6

7

3

10

8

The crashing data for this project are as follows:

  Time (days) Cost ($)
Activity Normal Crash Normal Crash
A 3 2 800 1400
B 2 1 1200 1900
C 5 3 2000 2800
D 5 3 1500 2300
E 6 4 1800 2800
F 2 1 600 1000
G 2 1 500 1000

a. Find the critical path and the expected project completion time.

b. What is the total project cost using the normal times?

8. Consider the following project network and activity times (in weeks):

608_029826EC-6BD2-4A39-B2DA-4E649B9F08B7.jpeg

Activity

A

B

C

D

E

F

G

H

Time

5

3

7

6

7

3

10

8

The crashing data for this project are as follows:

  Time (days) Cost ($)
Activity Normal Crash Normal Crash
A 3 2 800 1400
B 2 1 1200 1900
C 5 3 2000 2800
D 5 3 1500 2300
E 6 4 1800 2800
F 2 1 600 1000
G 2 1 500 1000

9. Refer to Problem 8. Assume that management desires a 12-day project completion time.

a. Formulate a linear programming model that can be used to assist with the crashing Dicisions.

b. What activities should be crashed

c. What is the total project cost for the 12-day completion time?

10. Office Automation, Inc., developed a proposal for introducing a new computerized office system that will standardize the electronic archiving of invoices for a particular company. Contained in the proposal is a list of activities that must be accomplished to complete the new office system project. Use the following relevant information about the activities:

      Time (weeks) Cost ($1000s)
Activity Description Immediate Predecessor Normal Crash Normal Crash
A Plan needs _ 10 8 30 70
B Order equipment A 8 6 120 150
C Install equipment B 10 7 100 160
D Set up training lab A 7 6 40 50
E Conduct training course D 10 8 50 75
F Test system C, E 3 3 60 _

a.Develop an activity network.

b.Develop an activity schedule.

c.What are the critical activities, and what is the expected project completion time?

d.Assume that the company wants to complete the project in six months or 26 weeks. What crashing decisions do you recommend to meet the desired completion time at the least possible cost? Work through the network and attempt to make the crashing decisions by inspection.
e.Develop an activity schedule for the crashed project.
f.What added project cost is required to meet the six-month completion time?

Science, Academics

  • Category:- Science
  • Reference No.:- M92500509

Have any Question?


Related Questions in Science

Critical appraisal requirementscritically appraise review

Critical appraisal requirements Critically appraise (review) the literature pertaining to human factors related to work performance and critically analyse the relationship between these and quality and safety in health c ...

A do research or find a peer-reviewed scholarly journal

A. Do research or find a peer-reviewed, scholarly journal article that is related to leadership and motivation with emphasis on morality, write a short summary of the content of the article. If it is not a scholarly jour ...

Case study now that you understand the basic concepts of

Case Study: Now that you understand the basic concepts of sustainability, resiliency, and biomimicry, please go to Ask Nature.org. Choose an example from the natural world and apply it to the human world. Why did you cho ...

Question in a 3 page paper compare and contrast food

Question: In a 3 page paper compare and contrast food insecurity issues in urban environments vs. rural environments. Discuss the role of food security as compared to food justice. The response must be typed, single spac ...

Course descriptionthis course provides an opportunity for

Course Description This course provides an opportunity for nursing students to enhance their knowledge of historical and contemporary issues relevant to Aboriginal and Torres Strait Islander people. This course will expl ...

Individual work - personal reflectionreflect on the roles

Individual work - personal reflection Reflect on the roles you performed in this group task and reflect on the ways you impacted on the group. Describe some of the things that you did that were helpful to the group. Desc ...

Assignment -in addition to turning in your isite journal

Assignment - In addition to turning in your iSite journal entry as usual, a short paper with emphasis on writing in a scientific format, properly acknowledging resources, and an overview of the process of thermoregulatio ...

Physiology signature assignment -for your signature

Physiology: Signature Assignment - For your signature assignment, compose a 3- to 4-page case analysis (in addition to a title, abstract, and a reference page) written in APA format with at least 3 references, with one n ...

Midterm exam questions -q1 you are asked to evaluate a

Midterm Exam Questions - Q1. You are asked to evaluate a construction/building project in an area corresponding to the sketch map below. The area has mildly hilly topography and thin soil cover. The bedrock in area X is ...

Quesiton researchers have attempted to devise a method to

Quesiton: Researchers have attempted to devise a method to place a monetary value on ecosystem goods and services (ecosystem capital). They hope that these efforts will make people aware that: ecosystem goods and service ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As