1. A civil engineering has modelled the deflection behaviour of a cantilever beam using a second-order differential equation. Cantilevers are beams that are fixed at one end and may have a weight suspended from the other end. The weight causes the beam to bend in such a way that the deflection downwards, y, is related to the horizontal distance, x, from the fixed end, according to a differential equation of the form:

where k is determined by the stiffness of the beam and a is the length of the beam. (All distances are in metres.)

a. For a beam that is 1.5 m long, find y in terms of x and k.

b. When x = 1.5, y = 0.031. Find the value of k.

c. The quantity dy/dx gives the inclination of the beam to the horizontal. Find the angle of the beam to the horizontal when x = 0.75 m; that is, approximately at the mid-point of the beam.

2. A civil engineer needs to know the population growth pattern of a town for the purpose of infrastructure planning. He has noted that the rate of growth of the town's population (N) is 5% of its population at any time t years. If its population is currently N0 = 100 000 people (at t = 0), find the following items for using in the infrastructure planning process:

a. the population (Nt) at any time t in terms of initial population (N0) and t

b. the population in 20 years time.

3. A civil engineer is analysing a hemispherical water reservoir of radius "a".

1341_Differential equations for the initial value problem.png

a. Show that the volume of water with a depth of h is given by Πh2/3(3a-h)

A certain hemispherical bowl has a radius of 10 metres.

b. The bowl is being filled with water at a rate of 30 m3 per minute. When the depth is 4 m, find the rate (in m per minute) at which the depth of the water is increasing.

c. Find, using calculus, the approximate change in the volume of the water in the bowl, when the depth of the water in the bowl increases from 4 to 4.01 m.

4. Use Euler's method to obtain an approximation to the value of y (2) using a step size of (i) h = 0.5 (ii) h = 0.1 (iii) 0.01.

dy/dx = y + x/yx

Where, y(1) = 2

Comment on the precision of your result (use a spreadsheet for you calculation and attach the calculation table with your assignment).

5. Two boats, A and B, start at a common point (0, 0) and move with velocity vectors

vA(t) = ti+ (t2 - t) j and vB(t) = -ti+ (t2 + t) j; t ?[0, 4].

Distance is measured in metres and time in seconds.

a. How far apart are they at t = 2?

b. What is the angle between their respective directions at t = 2?

c. At what time, if any, are the acceleration vectors of the two boats perpendicular to each other?

6. Identify the level curves of f(x, y) = √x2 + y2. Sketch a few of them.

7. Find the partial derivatives ∂f/∂x, ∂f/dy, ∂2f/∂2x, ∂f/∂y2, ∂2f/∂y∂x, ∂2f/∂x∂y for the function

f(x,y) = exy + xy

8. Find the volume V of the solid bounded by the three coordinate planes and the plane 3x+2y+5z = 6.

9. a. Find the two coupled first order differential equations for the following initial value problem

3x2y"-xy'+y=0; where y(1)=4 and y'(1)=2

b. Sketch a slope field diagram for the differential equation for the stated values of x

dy/dx = -x

x = -3, -2, -1, 0, 1, 2, 3

10. Use three numerical methods and n = 4 for approximating the value of the following integral.

02ex2dx

 

Civil Engineering, Engineering

  • Category:- Civil Engineering
  • Reference No.:- M91421675
  • Price:- $70

Priced at Now at $70, Verified Solution

Have any Question?


Related Questions in Civil Engineering

Assignmenta continuous three spans beam with

Assignment A continuous three spans beam with centre-to-centre distance of 6 m supports 150 mm thick one-way slabs as shown below. The beams have clear spans of 8 m, 9 m, and 8 (face-to-face of 400 mm square columns). Th ...

Assessment taskpractical investigationinstructions- it is

Assessment Task Practical Investigation Instructions: - It is very important that you read these instructions. - The hardcopy of the Assignment report, with the Assignment cover sheet, should be submitted to the Assignme ...

Civilyou are provided with bill of quantities prepared

Civil You are provided with bill of quantities prepared separately, priced and submitted by 3 con- tractors (A,B,C found on LMS) in respect of a proposed project (see appendix for drawings). The site is located on Mt. Al ...

1 aimthe assignment aims to develop the ability to analyse

1. Aim The assignment aims to develop the ability to analyse, evaluate, research plan and manage a major building project through individual and group participation (ideally 4-6 people).Refer to vUWS for the DA plans and ...

Masonry design assignmentquestion 1 - derivation of seismic

MASONRY DESIGN ASSIGNMENT Question 1 - Derivation of seismic actions on building a) Determine the storey seismic weights (Wi) for each suspended level of the building, hence the seismic weight (Wt) of the entire building ...

Aimthis assignment aims to demonstrate the structural

Aim: This assignment aims to demonstrate the structural design requirements of a glazed façade in a multi-storey building. Among other requirements, the glazed façade is required to comply with Australian Standard AS 204 ...

The drainage system of a cantilever wall shown in below

The drainage system of a cantilever wall shown in below figure, became blocked after a heavy rainstorm and the groundwater level, which was originallybelow the base, rose to1.5 (m) below the surface. Determine the stabil ...

Masonry design assignmentquestion 1 - derivation of seismic

MASONRY DESIGN ASSIGNMENT Question 1 - Derivation of seismic actions on building a) Determine the storey seismic weights (Wi) for each suspended level of the building, hence the seismic weight (Wt) of the entire building ...

Task details the client is doing masters in civil

Task Details: The client is doing Masters in Civil Engineering. He needs a Technical Paper on Earthquake pertaining to Geology and Rock Mechanics. There should be a through discussion of Earthquake in relation to the men ...

Aimthis assignment aims to demonstrate the structural

Aim: This assignment aims to demonstrate the structural design requirements of a glazed façade in a multi-storey building. Among other requirements, the glazed façade is required to comply with Australian Standard AS 204 ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As