1. Given the following table, make a PERT diagram, and determine the project time and the critical path. Provide a justification on how you obtain your project time and critical path.
Task Time Preceding Tasks
A 1 None
B 2 A
C 3 A
D 4 B
E 5 B, C
F 2 C
G 2 D, E, F