1. Allen Machines specializes in developing weed-harvesting equipment that is used to clear small lakes of weeds. Allen Machines is contemplating the construction of a machine that would harvest weeds on narrow rivers and waterways. The activities and time in weeks necessary to build one of these experimental machines are shown in the table below.

Activity

Immediate Predecessors

Time in Weeks

A

none

4

B

A

3

C

B

2

D

A

4

E

A

2

F

E

2

G

B, C

2

H

D,F

1

1. What is the minimum possible time required for completing the project?

2. What is the latest possible time that Activity E may be started without delaying the completion of the project?

3. What is the latest finish time for Activity H?

4. What is/are the critical path(s)?

2. The following is the activity and associated costs for the renovation of the local high school football stadium. The times are in weeks.

Activity

Immediate Predecessor

Time

Cost ($)

A

-

8

20,000

B

-

4

12,000

C

A

6

15,000

D

B

2

15,000

E

B

3

10,000

F

C, D

7

50,000

G

C, D

5

35,000

H

E, F

1

1,000

1. What is the critical path and total time required for this project?

2. How much of the total (cumulative) budget would be spent in Week 8 (Period 8) with the earliest start budget?

3. Precision Manufacturing has a government contract to produce stainless steel rods for use in military aircrafts. Each rod is required to be 35 millimeters in diameter. Each hour, random samples of size n = 5 rods are measured to check process control. Four hours of observations yielded the following:

 

Diameter

Time

Rod 1

Rod 2

Rod 3

Rod 4

Rod 5

9 A.M.

34.5

34.9

37.9

36

35.9

10 A.M.

35.1

34.7

33

35.4

34.9

11 A.M.

38.9

35

37.9

38.3

36.5

Noon

25

35.2

32.1

38.1

35

1. Construct the xbar-chart and the R-chart.

2. Is the process in control?

4. Modern Electronics specializes in manufacturing modern electronic components. It also builds the equipment that produces the components. Modern Electronics is considering building a new facility but the estimated profits would be impacted by the type of market that develops. The probability for a strong market is 0.3; for a fair market is 0.3; and for a poor market is 0.4. You are responsible for advising the president of Modern Electronics on the type facility that should be built or to not build a facility at all. The table shows the estimated profits under each market and for each size facility.

 

Estimated Profits

 

Strong Market

Fair Market

Poor Market

Build a large facility

30,000

25,000

-20,000

Build a medium-size facility

27,500

25,000

-10,000

Build a small facility

15,000

12,500

-1000

Do not build a facility

0

0

0

1. What is your recommendation to the president based on expected value that maximizes profits (EMV).

2. Provide a second recommendation to the president that minimizes regret.

5. Consulting income at Kaplan Associates for the period February - July is shown in the table below. Assume that the initial forecast for February is $90,000.Use Exponential smoothing to forecast August's income.

Month

Income ($1,000)

February

90.0

March

88.5

April

74.8

May

91.7

June

91.3

July

92.8

1. Use a smoothing constant of α = 0.1.

2. Use a smoothing constant of α = 0.6.

3. Analysis of the forecasting errors indicates which forecasting constant is best in this situation?

6. Johnson Construction Company is in the process of installing power lines to a large housing development. The company wants to minimize the total length of wire used, which would minimize the company's cost. The housing development is shown below. Each house has been numbered, and the distances between houses are given in hundreds of feet.

1688_graph.png

1. What do you recommend to Johnson Construction Company?

7. The storm drains in the Cedar Rapids, Iowa, have been upgraded following the devastating floods of 2008. The network of storm drains and the capacities are shown below. Determine the maximum flow (in hundreds of gallons of water per minute) from node 1 to node 5. Remember that the arc has both capacity and reverse capacity.

From Node

To Node

Fluid Flow

1

2

125

2

1

100

1

3

250

3

1

100

1

4

250

4

1

450

1

5

200

5

1

75

2

4

100

4

2

300

3

4

150

4

3

250

3

5

190

5

3

400

4

5

50

5

4

100

8. From the States Data Setthe following output for Collegeand for the Bachelors was created.

College Bachelors
Mean 62.264 Mean 26.804
Startdard Error L033743973 Standard Error  0.67272298
Median 62.8 Median  25.5
Mode 65.4 Mode  25.5
Standard Deviation 7.309673769 Star:lard Deviation  4.75690519
Sample Variance 53.43133061 Sample Variance  2262814694
Kirtosis -0.098148498 Kurtosis  -0.1516374
Skewness -0.396540362 Skewness  0.33372521
Range 31.7 Range   22L4
Minimum 45.7 Minimmn  15.3
Maximum 77.4 Max imun  36.7
Sun 3113.2 Strn  1340.2
Count 50 Curd 50

1. Which variable has the greatest relative variation?

9. You are a consultant working for Kaplan Consulting. The U.S. Department of Laborhas requested assistance in evaluating the impact of economic stimulus on the unemployment rate. From theStates Data Setthe following t test was conducted to answer the question:
"Has there been a significant reduction in the national unemployment rate between January and March?"

1. What is the Null and the Alternative Hypotheses?

2. What is your level of alpha (α)?

3. What is your decision about the hypothesis based on the software output?

4. Has there been a significant reduction in the national unemployment rate between January and February?

10. The Governor of a southern state has asked Kaplan Consulting to determine if the state were able to increase the percentage of its population with a Bachelor's Degree to 45%, what might be the expected median household income based on 2000 data? Here is the output from the Regression procedure from Excel.

Regression Statistics

 

 

 

Multiple R

0.713833536

 

 

 

R Square

0.515577153

 

 

 

Adjusted R Square

0.505479912

 

 

 

Standard Error

4M3.14n79

 

 

 

Observations

50

 

 

 

 

 

 

 

 

 

Coefficients Standard Error

t Stat

P-value

Intercept

15606.01508              3717163791

4193361138

0.000115689

Bachelors

976.2529817         136.5876943

7147444626

437107E-09

1. What would be the predicted median household income if the percentage of the population in the state were 45% or 45?

Math, Academics

  • Category:- Math
  • Reference No.:- M91905399

Have any Question?


Related Questions in Math

Assignment -question 1 let t and or 0 1 be a boolean

Assignment - Question 1. Let (T, ∧, ∨,', 0, 1) be a Boolean Algebra. Define ∗ : T × T → T and o : T × T → T as follows: x ∗ y := (x ∨ y)' x o y := (x ∧ y)' (a) Show, using the laws of Boolean Algebra, how to define x ∗ y ...

Questions - provide solution to the following questionsq1

Questions - Provide solution to the following questions: Q1. Evaluate the following: ∫xsin3xdx Q2. If , then for what value of α is A an identity matrix? Q3. The line y = mx + 1 is a tangent to the curve y 2 = 4x. Find t ...

Question 1 what is the nth order approximation using taylor

Question: 1. What is the nth order approximation using Taylor series? 2. What is Error Propagation? 3. Please explain what the total numerical error is? Please illustrate how the change of step size will affect the total ...

Assignment - provide solution to the following questionsq1

Assignment - Provide solution to the following questions: Q1. Evaluate the following: ∫xsin3x dx Q2. If , then for what value of α is A an identity matrix? Q3. The line y = mx + 1 is a tangent to the curve y 2 = 4x. Find ...

Question you will recommend a course of action regarding

Question: You will recommend a course of action regarding strategic planning in light of the issue the healthcare organization is facing. Be sure to address the following: 1. Provide a brief summary of the issue facing t ...

Mathematics- algebraic geometry problemlet k denotes an

Mathematics- Algebraic Geometry Problem Let K denotes an algebraically closed field and let P 1 be constructed as in Example 5.5(a) in Gathmanns notes, i.e. P 1 is the gluing of X 1 = A 1 and X 2 = A 1 along  the open su ...

Assignment - solving the five question in the very details

Assignment - Solving the five question in the very details, thanks a lot. Question - Let a ∈ P n be a point. Show that the one-point set {a} is a projective variety, and compute explicit generators for the ideal I p ({a} ...

1 suppose that n 10088821 is a product of two distinct

1. Suppose that n = 10088821 is a product of two distinct primes, and Φ(n) = 10082272. Determine the prime factors of n. 2. It is easy to show that the converse of Fermat's Theorem does not hold; i.e., the congruence a n ...

Instructionsthe aim of the assignment is that the

Instructions The aim of the assignment is that the student/group studies and applies numerical methods such as Euler's method, the Improved Euler's method and the Runge-Kutta method to solve first-order differential equa ...

Question 1 - for the ivp of ode y t-1e-y y1 0 find an

Question 1 - For the I.V.P of ODE y' = (t-1)e -y , y(1) = 0, find an approximation to y(1.2) using the following numerical methods with Δt = 0.1. Compare the numerical solution with the exact solution and compute the err ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As