1. A work breakdown structure is
a hierarchy of tasks, subtasks, and work packages
a Cost and Performance tracking schedule
a structure that is incompatible with the Critical Path Method
a simple list of the activities making up a project

2. The vertical axis on a Gantt chart is usually which of the following?
Activities
Time
Cost
Profit

3. Which of the following identifies a key principle of Reengineering?
Organize around tasks.
Downsize (layoff) workers and do the same amount of work as before.
Merge information processing work into the real work that produces the information.
Capture information both at the source and where it is interpreted.

4. At the onset, a project originates as which of the following?
A Gantt chart
A series of milestones
Critical path method (CPM)
A statement of work (SOW)

5. Consulting firms typically use which of the following techniques to plan and monitor the engagements of the firm or specific projects?
CPM/PERT
Qualitative forecasting
Materials requirements planning (MRP)
Quantitative layout

6. A Responsibility Chart specifically identifies which of the following?
Planning the tasks for a project
Customer satisfaction
Commitment to quality
Level of inventory

7. Which of the following would be the result of subdividing a project?
Job orders
Work events
Job categories
Tasks

8. Which project progress technique includes the essential features of a project plan, budgeted cost of work scheduled and budgeted cost of work performed?
Earned value management
Critical path method
Cost analysis
Gantt chart

9. An example of a graphic project report utilized within project management is:
Project proposal
Equipment and supplies chart
Humphrey chart
Cost and performance tracking schedule

English, Academics

  • Category:- English
  • Reference No.:- M92285013
  • Price:- $10

Priced at Now at $10, Verified Solution

Have any Question?


Related Questions in English

Using the following four resource documents prepare a case

Using the following four resource documents, prepare a case analysis regarding the premise "Airline Deregulation - 40 years Later - Pro or Con?" Airlines Move to Meet Regulatory Shifts (1978)/Aviation Week A Law That Cha ...

Question evaluate the cultural competence of the healthcare

Question: Evaluate the cultural competence of the healthcare organization presented in the Integrated Safety-Net Health Care System case study using a population health approach. Please also read the supplemental Interpr ...

Question commitment is very important in every work we do

Question: Commitment is very important in every work we do. If we commit to something that we will do, we must fulfill that commitment. Usually, we make commitment to the tasks to let others know that we will complete th ...

What is lust what is the difference between lust and love

What is lust? What is the difference between lust and love? Why is lust bad? Cite passages from bothOkholm and De Young. Describe what it means to think of love in terms of "gift", and explore how we might change aspects ...

Write a one-page not including cover and reference pages

Write a one-page (not including cover and reference pages) APA-formatted report on two of the following four topics: Topic 1: Open Skies - Explain what is meant by "Open Skies," and discuss the evolution of these interna ...

Read the two supporting documents focusing on airline

Read the two supporting documents focusing on airline globalization in 2018: Aviation Benefits: Contributing To Global Economic Prosperity/Uniting Aviation Aviation Benefits - 2017/ICAO (middle of page) Using the section ...

Read the following articles addressing the two space

Read the following articles addressing the two space treaties: "Outer Space Treaty of 1967" and "The Moon Treaty of 1979": The Outer Space Treaty Has Been Remarkably Successful - but Is It Fit for the Modern Age?/The Con ...

You have read the lottery by jackson and a good man is hard

You have read "The Lottery" by Jackson and "A Good Man is Hard to Find" by O''Connor. Now it is time to argue who does conflict better. In at least two well-structure paragraphs, please respond to the following prompt: W ...

Question your final draft must be added to the dropbox on

Question: Your final draft must be added to the dropbox on CourseDen (labeled "Essay One") by 8PM on the due date. Your final draft should be between 500-1000 words and should adhere to MLA format. Purpose: In this assig ...

Question part i the first part of this assignment will help

Question: Part I: The first part of this assignment will help you "flesh out" your topic. Take 10-15 minutes to free write about your topic. Chapters 4 and 5 in your textbook can help you decide what kind of free writing ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As