Ask Other Engineering Expert

  1. Three projects are considered, as follows:

Project 1

 

Optimistic

Expected

Pessimistic

Initial investment

$250,000

$270,000

$290,000

Annual O&M costs

$70,000

$74,000

$77,000

Annual revenue

$120,000

$110,000

$100,000

End of life salvage value

$25,000

$5,000

-$5,000

Project life

8 years

8 years

8 years

Interest rate

5%

6%

8%

Project 2

 

Optimistic

Expected

Pessimistic

Initial investment

$210,000

$250,000

$290,000

Annual O&M costs

$60,000

$70,000

$80,000

Annual revenue

$200,000

$160,000

$130,000

End of life salvage value

$45,000

$15,000

-$2,000

Project life

8 years

8 years

8 years

Interest rate

5%

6%

8%

Project 3

 

Optimistic

Expected

Pessimistic

Initial investment

$350,000

$400,000

$450,000

Annual O&M costs

$100,000

$130,000

$160,000

Annual revenue

$280,000

$250,000

$200,000

End of life salvage value

$50,000

$25,000

$0

Project life

8 years

8 years

8 years

Interest rate

5%

6%

8%

Find the NPV for each estimate for each project in the table above.

  1. For the same set of project data (question 1) determine the IRR for each outcome for each project.
  2. For the same set of three potential projects (question 1), develop a table of alternative combinations of projects based on the expected values of each project.
    a. Identify the combinations of projects which are permissible if the initial investment budget limit is: $550,000.
    b. For the alternatives which satisfy the budget limit criterion, perform a Present Value of incremental investment analysis to determine the preferred alternative. Interest rate is 6%.
    Duration is 8 years.
  3. For the same set of three projects (question 1) determine the project which would be selected usingthe following project slection criteria. The probablity of the outcomes are as described in the table below.

Criterion

Optimistic

Expected

Pessimistic

Probability

0.2

0.6

0.2

a. Expected value criterion.

b. Maximax criterion.

c. Laplace criterion.

  1. In 1984 a particular machine of capacity x cost $35,000. Estimate the cost of a similar machine with capacity 1.25x in 1990, using the Producer Price Index, table 3.5. Use a power law parametric estimation relationship with m = 0.65.
  2. Consider the project described by the parameters described below.

Initial investment

$250,000

Annual O&M costs

$70,000

Annual revenue

$120,000

End of life salvage value

$25,000

Project life

8 years

Interest rate

5%

Find the sensitivity of the NPV of this project to variations of BOTH end of life salvage value (salvage values of $5,000, $10,000, $15,000, $20,000, $25,000) and interest rate (calculate for interest rates of 4%, 8%, 12%, 16%, 20%). Both sets of variations operate simultaneously; i.e. a matrix of results is expected.

  1. A tool costs $15,000 to buy and in five years is estimated to have a salvage value of $500. Annual fixed costs are $1,700. The cost of consumables per hour of operation is $83.50 and the operator costs $62.00 per hour. Interest is 7.5%. The cycle time per unit of production is 0.01 hours. Determine the cost contribution of the machine in the manufacture of units if annual production is:
    a. 20,000 units.
    b. 60,000 units.
    c. 150,000 units.
    d. 200,000 units.
    e. Determine the total cost per unit of production for each of the above production quantities.  

You are considering a design with two alternatives. Interest is 10%.
Alternative A has parameters: Initial cost $48,000; Cost of maintenance in the first year $950; Annual increase in the cost of maintenance $1,050; Annual operating costs $3,100; Salvage value at the end of each year is 75% of the salvage value at the end of the previous year.

Alternative B has parameters: Initial cost $45,000; Cost of maintenance in the first year $1,300; Annual increase in the cost of maintenance $1,250; Annual operating costs $3,700; Salvage value at the end of each year is 70% of the salvage value at the end of the previous year.

Download:- Assignment.rar

Other Engineering, Engineering

  • Category:- Other Engineering
  • Reference No.:- M9752289

Have any Question?


Related Questions in Other Engineering

Register design a cpu register is simply a row of

Register design A CPU register is simply a row of flip-flops (i.e. SR, JK, T, etc) put side by side in an array to make the size of register required. For example, an 8 bit register has 8 flip-flops side by side for stor ...

A detailed review of spatial modulation and simulation

A Detailed Review of Spatial Modulation and Simulation Learning Outcomes a. Learn how to model mobile communication channels d. Discern knowledge development and directions on the recent advances in 4G to the research pr ...

Mine safety amp environmental engineering assignment -part

Mine Safety & Environmental Engineering Assignment - Part 1 - Questions 1. Occupational health and safety is the primary factor that needs to be considered in the mining industry. Discuss this statement. 2. Define the fo ...

Projectflow processing of liquor in a mineral refining

Project Flow Processing of Liquor in a Mineral Refining Plant The aim of this project is to design a flow processing system of liquor (slurry) in a mineral (aluminum) refining plant. Aluminum is manufactured in two phase ...

Learning outcomes evaluate multiuser communication and

Learning Outcomes Evaluate multiuser communication and resource sharing techniques; Apply the techniques of, and report on, digital communication applications using Matlab and hardware devices. Assignment Description The ...

Operations engineering assignment -please select only one

Operations Engineering Assignment - Please select only one of the following case studies for your assignment: CASE A. Tesla Motors Tesla is an innovative manufacturer that designs, assemble and sells fully electric vehic ...

Select a risk problem from the list below and prepare a

Select a risk problem from the list below and prepare a risk management plan in accordance with AS/NZS ISO 31000:2009. Please ensure that: - Establish the context clearly, in accordance with the Standard; - Define your s ...

Engineering materials term paper assignment -conduct a

ENGINEERING MATERIALS TERM PAPER ASSIGNMENT - Conduct a thorough literature search and write a 15-20 page technical review paper on the evolution of the engineering materials used in the manufacturing of any one of the f ...

Task 1using the lab kit design a circuit for the processor

Task 1: Using the lab kit, design a circuit for the processor to control the output of a connected 7-segment LED display device. You will be provided with a standard common anode 7-segment display of the type FND-507 (or ...

Control theory - lab reportsfor experiments 1 to 4 you must

Control Theory - Lab Reports For experiments 1 to 4 you must undertake the following: a) At the start of each section (including the pre-lab activities) there are a number learning outcomes. That is, what students should ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As