Smart Grid Fundamentals Coursework Assignment

Part 1 - Microgrid design

This part of the coursework consists of the design of a large microgrid that can supply a DC load. Your goal is to design a microgrid that can operate exclusively on renewable energy.

To do so you will need the following information:

  • Assume that all days in the year are the same, and within each day there are four time periods, with the properties shown in Table 1.1.
  • Solar PV can be built for a capital cost of £2000/kW (all costs included).
  • Wind can be built for a capital cost of £1500/kW (all costs included).
  • Battery storage can be built for £400/kWh + £100/kW. For example, the capital cost to build a 10 kW storage plant that can store 20 kWh, will be: 20kWh x £500/kWh + 10kW x £100/kW = £11,000

Assume that battery storage system will have a round trip efficiency of 85%.

The allowed depth of discharge of the battery is 80%. This means that the state of charge of the battery should not be allowed to go below 20%.

Assume that the operating costs for the resulting system are negligible, that the system will last for 25 years, and that you can obtain a 25 year loan at 5% interest for this project.

Table 1.1: Load, wind and solar data

Time

Load (kW)

Wind (kW/kW)

Solar (kW/kW)

12am-6am

10

0.90

0.05

6am-12pm

20

0.30

0.40

12pm-6pm

25

0.20

0.40

6pm-12am

15

0.60

0.05

Note that in Table 1.1, kW/kW refers to generated output (in kW) per unit of installed capacity (in kW).

Given these assumptions, you are required to:

a) Give an expression for the total initial cost of the microgrid.

b) Calculate a suitable value of the battery capacity and power rating considering its efficiency and allowed depth of discharge. Use manufacturer's data for actual lead acid batteries to select a battery bank that can be purchased in the market and that is reasonably close to your calculations.

c) Provide a charge/discharge schedule for the battery. Note that in order for the schedule to be a feasible solution, the amount of energy in the battery will need to be the same at the beginning and the end of each day (since this pattern repeats day after day).

d) Calculate a suitable power rating of the wind generator. Use manufacturer's data for actual DC wind generators to select a power rating that can be purchased in the market and that is reasonably close to your calculations.

e) Calculate a suitable power rating of the solar PV system. Use manufacturer's data for actual PV panels to select a power rating that can be purchased in the market and that is reasonably close to your calculations. Specify how many panels would be required.

f) What would be the total initial cost of the microgrid? Can this cost be reduced to a minimum? If so, explain how and provide calculations to support your answer.

g) Calculate the annual loan repayment amount, given the total initial cost, the loan period of 20 years and the annual interest rate of 5% for the configuration that you found to give the minimum initial cost.

h) What would be the minimum price in £/kWh at which the generated energy can be sold to the customer to recover the annual loan repayment amount given the total annual load in kWh?

i) Discuss your solution. What factors might have changed your answer?

In the report, please ensure that you:

1. Clearly explain your method (including computer code, if appropriate). Explain your equations.

2. Clearly describe your solution, paying particular attention to ensure that your solution is feasible. Use tables and, if appropriate, graphics to present your results. Show what each resource is doing during each of the four time periods.

Part 2 - Economic dispatch and optimal power flow analysis

2.1 - Power system data

Consider that in a simple power system there are four power plants. The generating plants capacity, type and marginal costs are:

1. 1100 MW nuclear plant with marginal cost of £10/MWh, connected to bus 1.

2. 600 MW coal plant with marginal cost of £20/MWh, connected to bus 2.

3. 400 MW natural gas plant with marginal cost of £30/MWh, connected to bus 3.

4. 100 MW of diesel units marginal cost of £150/MWh, connected to bus 5.

Every day there are four 6-hour periods of demand:

  • 12am-6am: 800 MW
  • 6am-12pm: 1200 MW
  • 12pm-6pm: 1920 MW
  • 6pm-12am: 1600 MW

The system consists of a network with 5 buses. The load above is distributed evenly among the five buses. The transmission lines (branches) have the data shown in Table 2.1.

Table 2.1: Transmission line data

From Bus

To Bus

R

X

Power limit (MW)

1

2

0

0.1

400

1

3

0

0.1

400

2

3

0

0.1

400

2

5

0

0.1

300

3

4

0

0.1

300

4

5

0

0.1

300

Given this information, do the following.

2.2 - Economic dispatch / power flow problem

a) Solve the simple economic dispatch problem for each time period. Report the system marginal price.

b) Solve the DC power flow problem for this system at each time period.

c) For each time period report (in a table) the flows on the transmission lines for your solution.

2.3 - Optimal power flow

a) Solve the optimal power flow problem for this system at each time period.

b) For each time period report (in a table) the flows on the transmission lines for your solution.

c) For each time period report (in a table) the locational marginal prices (LMPs).

2.4 - Discussion

a) What is the impact on this power system of having transmission line constraints?

b) How might smart grid technology impact this power system?

c) How should this system be upgraded to improve its operation?

General guidance and Information

You should produce a report addressing Parts 1 and 2, reflecting as appropriate the structure of this coursework brief. The maximum word count for your report is 2000 words, excluding the cover page. Your report should briefly introduce each sub-problem, describe the method(s) used, and present the results obtained, including where appropriate details of the calculations made and computer code used (if any), ensuring that the specific questions asked in parts 1 and 2 are answered.

If you are including computer code, please ensure that the computer code that you have written is inserted within a numbered textbox, so that it can be referred to from within the text as if it was a figure (for example, you may write "see the computer code in Figure 2")

You are free to use specialist software tools that may be available to you to solve the problems involved in this coursework. Details of suitable tools will be given in the lectures.

You can include screenshots of the software package used and computer generated plots, if appropriate. You are only allowed to work on your own, no team work is permissible.

Other Engineering, Engineering

  • Category:- Other Engineering
  • Reference No.:- M92747684

Have any Question?


Related Questions in Other Engineering

Part 1configure verify and troubleshoot wan links and ip

Part 1 Configure, verify and troubleshoot WAN links and IP services Answer to all questions below: 1. What is the name of the Safe Work Australia code of practise that provides guidance on how to manage the risks of elec ...

Task 1using the lab kit design a circuit for the processor

Task 1: Using the lab kit, design a circuit for the processor to control the output of a connected 7-segment LED display device. You will be provided with a standard common anode 7-segment display of the type FND-507 (or ...

Homework - risk and decision management1 you are working

Homework - Risk and Decision Management 1) You are working program X. The total budget allocated to the program is $100 M and it is to be completed in 24 mo. range (R) and passenger capacity (C) are two key performance p ...

Operations engineering assignment -please select only one

Operations Engineering Assignment - Please select only one of the following case studies for your assignment: CASE A. Tesla Motors Tesla is an innovative manufacturer that designs, assemble and sells fully electric vehic ...

Engineering analysis assignment -for every problem provide

Engineering Analysis Assignment - For every problem, provide The MATLAB script/function files that solve the problems. Problem 1: Plot the function f(t) = (x+5) 2 /(4+3x 2 ) for -3 ≤ x ≤ 5. using plot command. Use the ar ...

Control theory - lab reportsfor experiments 1 to 4 you must

Control Theory - Lab Reports For experiments 1 to 4 you must undertake the following: a) At the start of each section (including the pre-lab activities) there are a number learning outcomes. That is, what students should ...

Mine safety amp environmental engineeringpart 1 questions1

Mine Safety & Environmental Engineering Part 1. Questions 1. Occupational health and safety is the primary factor that needs to be considered in the mining industry. Discuss this statement. 2. Define the following terms ...

Assignment 11 what is the purpose of ore reserve and

ASSIGNMENT 1 1. What is the purpose of ore reserve and resource estimation? Why are resource and reserve estimates important to the mining industry? 2. What is meant by ore? What is meant by the term waste? How is the di ...

Engineering materials term paper assignment -conduct a

ENGINEERING MATERIALS TERM PAPER ASSIGNMENT - Conduct a thorough literature search and write a 15-20 page technical review paper on the evolution of the engineering materials used in the manufacturing of any one of the f ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As