Ask Question, Ask an Expert

+61-413 786 465

info@mywordsolution.com

Ask Other Engineering Expert

Question 1

The Level Book extract below shows results of a closed level traverse around a property that picks up levels of the ground and some features around the property boundary.

BS

IS

FS

Rise

Fall

RL

Dist

Notes

2.510

 

 

 

 

 

0

BM #234         RL 73.452

 

2.260

 

 

 

 

 

A.    Peg

 

1.990

 

 

 

 

 

B.     Peg

3.210

 

1.420

 

 

 

85m

CP- C. Mark on Access hole

 

2.850

 

 

 

 

 

D. Peg

 

2.400

 

 

 

 

 

E. Access hole cover

1.600

 

1 SO0

 

 

 

159in

CP- F. Peg

 

1.450

 

 

 

 

 

G. Peg

 

1.500

 

 

 

 

 

H. Stormwater Inlet

0.720

 

1.660

 

 

 

230m

CP- I. Peg NW of building

 

0.840

 

 

 

 

 

J.       Peg

 

0.810

 

 

 

 

 

K.    Peg

 

 

0.620

 

 

 

276m

BM #74           RL 75.992

a. Complete the Level Book entries and calculate the reduced levels.

b. Determine the level misclose.

c. Determine the maximum allowable misclose for this engineering survey using the formula based on the number of instrument stations used in the work.

d. Calculate the adjustments required if the misclose is acceptable.

e. Apply the adjustments and prepare a list of reduced levels for the Pegs/Marks A to K.

Question 2

Aq

D

Cq

The figure above shows three stations, A. B and C. The horizontal distances between the stations have been surveyed and the following results obtained.

AB = 91.437m

BC = 72.697m

CA = 128.443m

The position of Station B in relation to A and B needs to be checked. To do this, Station D is located 62.429m from A so that the distance DB can be used to check the position of the peg B.

a. Calculate the horizontal distance DB.

b. Calculate slope distance that should be obtained when DB is measured if D is known to be 3.348m below B.

c. Comment on the maximum accuracy of measurement you would expect in measuring BD, if a steel tape is used, care is taken and adjustments are made for slope, tension and temperature.

Question 3

A closed survey traverse was made of four stations A, B, C and D The survey data and requirements for the survey are shown below.

a. Adjust the observed angles and partial coordinates of the traverse and determine the coordinates of the four stations and present the computations in the format shown in Table 6.1 of the text book

b. Show any additional calculations made on calculation sheets.

c. Comment on the quality of the traverse on both angle measurements and distance measurements.

d. Sketch the traverse showing the north point coordinates for each station and adjusted bearings and distances for each line.

The bearing of Line AB is 283°05'52"

The Coordinates of Station A are 232.570E 516.255N

The maximum allowable error for the angle misclose is allow ±20 (n)°3 seconds, using a 1" theodolite. The accuracy of the survey coordinates close must be better than 1 in 2500.

All calculations should be to 4 decimal places in metres for distances, and angles and bearings should be calculated to the nearest second. Results should be reported to three decimal places and to the nearest second.

The following information was obtained from Field Books:

Line

Horizontal length (m)

AB

64.885

BC

22.321

CD

42.316

DA

42.254

Means of FL and FR
observed horizontal
angles

Angle (DMS)

 

ABC

80°19'04"

 

BCD

119°42'59"

 

CDA

100°17'05"

 

DAB

59°41'08"

 





Question 4

A project modification requires establishment of a new survey control point because lines of sight to existing survey marks are obscured. It is proposed to set up the new control point (Station F) by intersection, setting up a theodolite at existing survey control points (Station C and Station D) whose coordinates are known.

Coordinates for the known control points are

Station C: 271.74E     72.81N

Station D: 431.23E     154.97N

The peg for the new control point was placed at F after checking that there were clear lines of sight to station C and station D, and checking that the location of F allowed the obscured project area to be observed. When the peg at F was securely placed, the observations were made from station C and station D to obtain the angles FCD and FDC. Observations were taken FL and FR, and each angle was measured three times. The results of these observations of the internal angles of Triangle FCD obtained from the Field Book were:

Angle FCD 48°01 '14" and Angle FDC 72°58'46" Compute the following:

a. Bearing and distance of CD

b. Coordinates of the new Station F

c. Bearing and distance CF

d. Bearing and distance DF

Question 5

The following list shows obsen-ations of an angle that was repeated six times to increase the precision of the mean.

a. Determine the mean of this set of 6 observations.

b. Determine the standard deviation of this set of 6 observations

c. Use the t-distribution table to determine whether any of the observations in this set of six should be considered outliers, that should be disregarded in calculating the mean and standard deviation of the set of observations. Use the 95% acceptance criterion to accept that errors in observations are due to random variations only.

d. If outliers are found, recalculate the mean and standard deviation of the reduced set of acceptable observations and calculate the standard error of the mean.

e. Explain what the value of the standard error of the mean indicates about the true value of the measurement if it is assumed that the variation is due only to random variation

Observation

Observed value (DMS)

1

233°18'01"

2

233°18'43"

3

233°18'43"

4

233°18'44"

5

233°18'45"

6

233°18'41"

Question 6

The height difference between two points A and B is measured with a total station and following results are obtained.

With the total station at A

Slope distance = 256.347 m

Zenith angle = 92°25'51"

Height of the instrument at A = 1.550 m Height of the reflector at B = 1.405 m

With the total station at BI Slope distance = 256.352 m Zenith angle = 87°37'42"

Height of the instrument at B = 1.625 m Height of the reflector at A = 1.530 m

If the height of point A is 19.072 in, calculate the height of point B.

Other Engineering, Engineering

  • Category:- Other Engineering
  • Reference No.:- M91522645
  • Price:- $75

Priced at Now at $75, Verified Solution

Have any Question?


Related Questions in Other Engineering

Projection of planes1 a regular pentagon of 25 mm side has

Projection of Planes 1. A regular pentagon of 25 mm side has one side on the ground. Its plane is inclined at 45° to H.P. and perpendicular to the V.P. Draw its projections. 2. Draw the projection of a circle of 50 mm di ...

Engineering analysis homework -for every problem provide

Engineering Analysis Homework - For every problem, provide The MATLAB script/function files that solve the problems. Problem 1: Write a script that solves the problem. For (c), show results of the evaluation of every ind ...

Projectflow processing of liquor in a mineral refining

Project Flow Processing of Liquor in a Mineral Refining Plant The aim of this project is to design a flow processing system of liquor (slurry) in a mineral (aluminum) refining plant. Aluminum is manufactured in two phase ...

Task 1using the lab kit design a circuit for the processor

Task 1: Using the lab kit, design a circuit for the processor to control the output of a connected 7-segment LED display device. You will be provided with a standard common anode 7-segment display of the type FND-507 (or ...

Introduction to engineering design assignment -

Introduction to Engineering Design Assignment - Drafting Question 1 - Field notes and traverse drawing may be an outdated form of keeping and presenting information on the position of features on a site. Modern electroni ...

Mine safety amp environmental engineering assignment -part

Mine Safety & Environmental Engineering Assignment - Part 1 - Questions 1. Occupational health and safety is the primary factor that needs to be considered in the mining industry. Discuss this statement. 2. Define the fo ...

Assignment 11 what is the purpose of ore reserve and

ASSIGNMENT 1 1. What is the purpose of ore reserve and resource estimation? Why are resource and reserve estimates important to the mining industry? 2. What is meant by ore? What is meant by the term waste? How is the di ...

Control theory - lab reportsfor experiments 1 to 4 you must

Control Theory - Lab Reports For experiments 1 to 4 you must undertake the following: a) At the start of each section (including the pre-lab activities) there are a number learning outcomes. That is, what students should ...

Part 1configure verify and troubleshoot wan links and ip

Part 1 Configure, verify and troubleshoot WAN links and IP services Answer to all questions below: 1. What is the name of the Safe Work Australia code of practise that provides guidance on how to manage the risks of elec ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As