Question 1

Earned Value Management

Question 1 (a) --- Project 1

You are managing a project that is scheduled to take 12 months to complete and has a budgeted actual cost (BAC) of $1,500,000.

At the Status Date, the project has the following characteristics:

Planned value (PV)

$450,000

Actual cost (AC)

$520,000

Percentage of work completed

28%

Calculate the following quantities: 28%

Earned Value (EV)

Cost Variance (CV)

Schedule Variance (SV)
Cost performance index (CPI)
Schedule performance index (SPI)

Using your results, apply the three (3) formulae listed in Section 7.4.2.2 of the text to the calculation of the Estimate at Completion (EAC) of the project.

These formulae are as follows:

 EAC=AC + (BAC - EV)

 EAC=BAC/CPI

 EAC= AC + [(BAC-EV) / (CPI x SPI)].

Question 1 (b) --- Project 2

You are managing a second project that has the same time and cost specifications as those in Question 1 (a), but which is 40% complete at the Status Date, when Actual Costs are $550,000.

Its specifications are below

Budgeted Actual Cost (BAC): $1,500,000. Schedule time to complete: 12 months

At the Status Date, the project has the following characteristics:

Planned value (PV)
Actual cost (AC)
Percentage of work completed

Calculate the following quantities:

Earned Value (EV)

Cost Variance (CV)
Schedule Variance (SV)
Cost performance index (CPI)
Schedule performance index (SPI)

Using your results, apply the three (3) formulae listed in Section 7.4.2.2 of the text to the calculation of the Estimate at Completion (EAC) of the project.

These formulae are as follows:

 EAC=AC + (BAC - EV)
 EAC=BAC/CPI
 EAC= AC + [(BAC-EV) / (CPI x SPI)].

Question 1 (c)

Compare the two projects from the point view of project performance, paying particular attention to the following:

Cost Variance (CV) (2 marks per project)
Schedule Variance (SV) (2 marks per project)
Cost performance index (CPI) (2 marks per project)
Schedule performance index (SPI) (2 marks per project)
Estimated Actual Cost (EAC) of the project (2 marks per project)

A brief assessment of the overall project performance, including any necessary measures required to successfully complete the project

Total Marks per project 15 marks per project

SUB- TOTAL FOR Question 1 (c)

Question 1 (d)

There has been considerable discussion about Earned Value Project Management in the literature. Using at least two (2) literature sources to support your discussion, discuss your views about at least two (2) positive aspects of Earned Value Management and at least two (2) potential issues with its use as a project control tool. Form an opinion about the value of Earned Value Management as a project management tool.

Marking:

Positive aspects of Earned Value Management

Issues with the use of Earned Value Management

Development of opinion

Use of references to support your answer

Question 2

Developing a Revised Project Management Plan and Report to Management

Background

You have recently been appointed as a project manager in a large engineering organisation. Some examples of such an organisation include, but are not limited to:

- Consultant
- Government organisation
- Construction company
- Installation company
- Asset management provider
- Maintenance services provider
- Other.

The organisation may be operating in one or more engineering disciplines, such as civil, mechanical, electrical, environmental, mechatronic, biomedical, or other discipline, or in construction or surveying.

Your organisation has asked you to review the management of a medium sized project (up to $5 million in value), which is to be completed within two (2) years of its commencement. The project has at least 20 main activities.

The project commenced eight (8) months ago. The first six (6) weeks were spent developing the project charter and preparing the original project management plan. Project execution (carrying out the work) commenced immediately the project management plan was completed and approved.

There will be a one (1) month project closing period at the end of the project. During this time, equipment will be tested and commissioned (if relevant to your project), and the project will be finalised.

The project deadline is firm, subject to any justifiable contingencies.

The existing business case and project charter are not detailed. Similarly, the project management plan, including a basic Gantt chart and high level budget is not well detailed or described.

There are a number of issues with the project:

1. To date, the project is two (2) months behind schedule. Part of this delay has resulted from poor understanding of lead times for delivery of particular project components. There are no other significant factors that should impact on project delivery.

2. Because there is only a quite basic project plan and time schedule, there is poor sequencing of critical activities. They do not have clear scheduled completion dates.

3. There have been delays in procuring some critical project resources. There may be alternative suppliers.

4. While there were a number of specialised personnel for particular aspects of the project available at the start of the project, they were not booked ahead of when they were required.

Most of these resources are now booked for several months ahead. Few alternatives are available.

5. As a result of the influence of a number of stakeholders, there has been significant scope creep, which with the current rate of progress will delay delivery by one (1) month. This scope creep also threatens to impact on the project's business case.

6. Some components of the project have not been delivered or built to the required quality specification. Consequently, there have been delays while defects have been rectified.

7. Communication between project manager, project sponsor, stakeholders, contractors, consultants and other key personnel has not been good. There are therefore a number of cases where key information has not been communicated well. This poor communication has impacted on project progress.

You have been charged with delivering a revised project management plan to deliver the project on time; and with providing a report to the Project Sponsor explaining the actions you have taken.

Your Task

Question 2 (a) Developing a Revised Project Plan

(maximum 2500 words)

1. Define your organisation and project.

Nominate an organisation of your choice, and the engineering discipline or disciplines in which it is operating.

Nominate a suitable project (for example, road development, subdivisional development, power station, mobile phone network, mining, provision of industrial equipment, installation, maintenance, surveying) to use as an example.

2. Prepare a revised project charter, including an updated business case. This document should include an executive summary of the revised project charter.

3. Prepare an updated project management plan for completing the project within its original timeline.

The project management plan should include plans for all phases/stages of the project based on the following Project Management Knowledge Areas:

- project integration management
- project scope management
- project time management
- project cost management
- project quality management
- project human resource management
- project communications management
- project procurement management.

Notes:

- The project charter should include a revised business case for the project and link the project with your organisation's strategic plan. On the basis of this business case, the project sponsor will make a decision about the future of the project.
- You may assume that the project sponsor has allowed the project timeline to be increased by one (1) month to allow for the scope creep already approved. However, further scope creep is not permitted.
- The project scope management plan should include a Work Breakdown Structure and a section on controlling scope creep. Normally three (3) levels should be sufficient for the Work Breakdown Structure.
- The project time management plan should include a Gantt chart showing the major project activities (up to about 30 activities).
- The project cost management plan should include all costs reasonably expected to be incurred in delivering the project. These costs may include estimates for ensuring completion of the project.

SUB- TOTAL FOR QUESTION 2 (a) 200 MARKS

Question 2 (b) Report to Project Sponsor

Write a report to your Project Sponsor that:

- succinctly outlines the steps you have taken to deliver the project within its original timeframe (as extended by permitted scope creep of one (1) month)
- explains why they have been taken
- demonstrates how they will enable the project to be completed within its original timeframe
- discusses the additional costs that will be incurred to achieve this target

Written Communication

Abstract and table of contents
Structure
Language, style, spelling
Completion in within word count
Setting out and referencing

SUB- TOTAL FOR WRITTEN COMMUNICATION 50 MARKS

Other Engineering, Engineering

  • Category:- Other Engineering
  • Reference No.:- M92253915
  • Price:- $130

Priced at Now at $130, Verified Solution

Have any Question?


Related Questions in Other Engineering

Register design a cpu register is simply a row of

Register design A CPU register is simply a row of flip-flops (i.e. SR, JK, T, etc) put side by side in an array to make the size of register required. For example, an 8 bit register has 8 flip-flops side by side for stor ...

A detailed review of spatial modulation and simulation

A Detailed Review of Spatial Modulation and Simulation Learning Outcomes a. Learn how to model mobile communication channels d. Discern knowledge development and directions on the recent advances in 4G to the research pr ...

Mine safety amp environmental engineering assignment -part

Mine Safety & Environmental Engineering Assignment - Part 1 - Questions 1. Occupational health and safety is the primary factor that needs to be considered in the mining industry. Discuss this statement. 2. Define the fo ...

Projectflow processing of liquor in a mineral refining

Project Flow Processing of Liquor in a Mineral Refining Plant The aim of this project is to design a flow processing system of liquor (slurry) in a mineral (aluminum) refining plant. Aluminum is manufactured in two phase ...

Learning outcomes evaluate multiuser communication and

Learning Outcomes Evaluate multiuser communication and resource sharing techniques; Apply the techniques of, and report on, digital communication applications using Matlab and hardware devices. Assignment Description The ...

Operations engineering assignment -please select only one

Operations Engineering Assignment - Please select only one of the following case studies for your assignment: CASE A. Tesla Motors Tesla is an innovative manufacturer that designs, assemble and sells fully electric vehic ...

Select a risk problem from the list below and prepare a

Select a risk problem from the list below and prepare a risk management plan in accordance with AS/NZS ISO 31000:2009. Please ensure that: - Establish the context clearly, in accordance with the Standard; - Define your s ...

Engineering materials term paper assignment -conduct a

ENGINEERING MATERIALS TERM PAPER ASSIGNMENT - Conduct a thorough literature search and write a 15-20 page technical review paper on the evolution of the engineering materials used in the manufacturing of any one of the f ...

Task 1using the lab kit design a circuit for the processor

Task 1: Using the lab kit, design a circuit for the processor to control the output of a connected 7-segment LED display device. You will be provided with a standard common anode 7-segment display of the type FND-507 (or ...

Control theory - lab reportsfor experiments 1 to 4 you must

Control Theory - Lab Reports For experiments 1 to 4 you must undertake the following: a) At the start of each section (including the pre-lab activities) there are a number learning outcomes. That is, what students should ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As