Question 1. The following information is extracted from a project to develop a state-of-the-art alternative power energy storage device.

Activity Duration Predecessors Resources

A 4 days -- 1 research engineer

B 3 days A 1 marketing specialist

C 5 days A 1 design engineer

D 3 days A 1 design engineer

E 3 days B 1 prototype builder

F 2 days D 1 test engineer

The owner has stipulated that in order to provide continuity throughout the project, the same individual must handle all activities under his or her discipline. Activities on this project cannot be split.

(a) Identify any resource conflicts in the above project. State the activities involved, the time frame of the conflict(s), which resources are involved, and the quantity required.

(b) Given the owner's stipulation regarding project continuity and the need to minimize project duration, how can this conflict be resolved? What will be the effect on the project duration?

Question 2. The following data were obtained from an information systems project to upgrade and expand a local area network.

Activity Duration Predecessors Task Budget

A 3 days --- $4,920

B 6 days --- $7,680

C 3 days A $15,140

D 2 days B $4,980

E 3 days B $5,630

F 2 days C and D $2,270

At the end of Day 7, the status of the project is as follows.

Activity % Complete Actual Cost

A 100% $4,200

B 100% $8,740

C 100% $18,250

D 65% $2,600

E 10% $560

F 0% $0

(a) Calculate the cost and schedule variances and indexes for Tasks A, B, C, D, and E.

(b) As project manager, write a brief summary of the status of the project at this time.

Question 3. You are project manager for three different projects.

Project A: This project is in the execution stage of the project. It is behind schedule by 6 weeks; it was scheduled to be completed in 10 weeks. The sponsor is desperate to accomplish something on this project. The budget is limited to the original amount, and all soft predecessors have already been removed.

Project B: This project is behind schedule by 10 weeks. It was to have been completed in 2 months. The sponsor has additional funds to help complete the project on time if needed but does not want to increase risk to the project.

Project C: This project is scheduled to take 18 weeks to complete. You are in the planning stage of the project. You need to reduce the schedule for this project by 5 weeks. This project has a number of predecessors that were created by the project team's preference. The sponsor insists on having all the work done on time without unduly increasing risk or costs to the project.

For each of the project above, choose an appropriate schedule compression technique. Explain your choice.

Computer Engineering, Engineering

  • Category:- Computer Engineering
  • Reference No.:- M91339558
  • Price:- $20

Guranteed 24 Hours Delivery, In Price:- $20

Have any Question?


Related Questions in Computer Engineering

Does bmw have a guided missile corporate culture and

Does BMW have a guided missile corporate culture, and incubator corporate culture, a family corporate culture, or an Eiffel tower corporate culture?

Rebecca borrows 10000 at 18 compounded annually she pays

Rebecca borrows $10,000 at 18% compounded annually. She pays off the loan over a 5-year period with annual payments, starting at year 1. Each successive payment is $700 greater than the previous payment. (a) How much was ...

Jeff decides to start saving some money from this upcoming

Jeff decides to start saving some money from this upcoming month onwards. He decides to save only $500 at first, but each month he will increase the amount invested by $100. He will do it for 60 months (including the fir ...

Suppose you make 30 annual investments in a fund that pays

Suppose you make 30 annual investments in a fund that pays 6% compounded annually. If your first deposit is $7,500 and each successive deposit is 6% greater than the preceding deposit, how much will be in the fund immedi ...

Question -under what circumstances is it ethical if ever to

Question :- Under what circumstances is it ethical, if ever, to use consumer information in marketing research? Explain why you consider it ethical or unethical.

What are the differences between four types of economics

What are the differences between four types of economics evaluations and their differences with other two (budget impact analysis (BIA) and cost of illness (COI) studies)?

What type of economic system does norway have explain some

What type of economic system does Norway have? Explain some of the benefits of this system to the country and some of the drawbacks,

Among the who imf and wto which of these governmental

Among the WHO, IMF, and WTO, which of these governmental institutions do you feel has most profoundly shaped healthcare outcomes in low-income countries and why? Please support your reasons with examples and research/doc ...

A real estate developer will build two different types of

A real estate developer will build two different types of apartments in a residential area: one- bedroom apartments and two-bedroom apartments. In addition, the developer will build either a swimming pool or a tennis cou ...

Question what some of the reasons that evolutionary models

Question : What some of the reasons that evolutionary models are considered by many to be the best approach to software development. The response must be typed, single spaced, must be in times new roman font (size 12) an ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As