Ask Question, Ask an Expert

+61-413 786 465

info@mywordsolution.com

Ask Computer Engineering Expert

Question 1. The following information is extracted from a project to develop a state-of-the-art alternative power energy storage device.

Activity Duration Predecessors Resources

A 4 days -- 1 research engineer

B 3 days A 1 marketing specialist

C 5 days A 1 design engineer

D 3 days A 1 design engineer

E 3 days B 1 prototype builder

F 2 days D 1 test engineer

The owner has stipulated that in order to provide continuity throughout the project, the same individual must handle all activities under his or her discipline. Activities on this project cannot be split.

(a) Identify any resource conflicts in the above project. State the activities involved, the time frame of the conflict(s), which resources are involved, and the quantity required.

(b) Given the owner's stipulation regarding project continuity and the need to minimize project duration, how can this conflict be resolved? What will be the effect on the project duration?

Question 2. The following data were obtained from an information systems project to upgrade and expand a local area network.

Activity Duration Predecessors Task Budget

A 3 days --- $4,920

B 6 days --- $7,680

C 3 days A $15,140

D 2 days B $4,980

E 3 days B $5,630

F 2 days C and D $2,270

At the end of Day 7, the status of the project is as follows.

Activity % Complete Actual Cost

A 100% $4,200

B 100% $8,740

C 100% $18,250

D 65% $2,600

E 10% $560

F 0% $0

(a) Calculate the cost and schedule variances and indexes for Tasks A, B, C, D, and E.

(b) As project manager, write a brief summary of the status of the project at this time.

Question 3. You are project manager for three different projects.

Project A: This project is in the execution stage of the project. It is behind schedule by 6 weeks; it was scheduled to be completed in 10 weeks. The sponsor is desperate to accomplish something on this project. The budget is limited to the original amount, and all soft predecessors have already been removed.

Project B: This project is behind schedule by 10 weeks. It was to have been completed in 2 months. The sponsor has additional funds to help complete the project on time if needed but does not want to increase risk to the project.

Project C: This project is scheduled to take 18 weeks to complete. You are in the planning stage of the project. You need to reduce the schedule for this project by 5 weeks. This project has a number of predecessors that were created by the project team's preference. The sponsor insists on having all the work done on time without unduly increasing risk or costs to the project.

For each of the project above, choose an appropriate schedule compression technique. Explain your choice.

Computer Engineering, Engineering

  • Category:- Computer Engineering
  • Reference No.:- M91339558
  • Price:- $20

Guranteed 24 Hours Delivery, In Price:- $20

Have any Question?


Related Questions in Computer Engineering

Submit your solution as a plain-text file with a c

Submit your solution as a plain-text file with a .c extension in the name. Name timer - counts down to zero from a user supplied number. Description Displays a count down to zero from a number supplied by the user at the ...

Explain why a u s recession that occurs as the rest of the

Explain why a U. S. recession that occurs as the rest of the world is expanding will tend to reduce the U. S. Trade deficit.

Sometimes when we visit super markets we may share our

Sometimes when we visit super markets, we may share our personal details to get (for example) "Loyalty cards" and other benefits. Do you think sharing such details is a good approach? Give arguments for both cases: "shar ...

Say that a processor addresses bytes with 64 bits addresses

Say that a processor addresses bytes with 64 bits addresses, has 8 byte words, and 1024 cache entries that are each 8 words long. a) How would the bits of the address be used to indicate the set, line, word and byte? b) ...

A is the event that your friend is sick today and b is the

A is the event that your friend is sick today and B is the event that you pass this test. These events are independent and Not mutually exclusive. Calculate the probability that your friend is sick today OR you pass this ...

What are the characteristics of perfect competition and

What are the characteristics of perfect competition, and does is exist in the real world?

Reminder all files must be closed when you are done with

Reminder: All files must be closed when you are done with them, even if it stops early due to an IOError. If you're using with, this will happen automatically. If you're trying to close things manually using .close(), th ...

Suppose that relations r and s contain 20 and 30 blocks

Suppose that relations r and s contain 20 and 30 blocks respectively, and the block nested-loop join algorithm is used to natural-join r and s. What is the cost in terms of number of seeks and number of block transfers i ...

Question suppose you want to implement a sudoku game that

Question : Suppose you want to implement a Sudoku game that includes nine rows and nine columns of squares. Which layout would be the best one to use and why? The response must be typed, single spaced, must be in times n ...

String firstnamearraychar gradearrayassuming that this text

String firstName[ARRAY]; char grade[ARRAY]; Assuming that this text file is already inputted into the program. Write a loop that will display the students that have "A" or "B" next to their names. If the stuent has a "A" ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As