Q1: Level 1 WBS Elements With reference to the referenced example job drawings list at least 5 Level 1 Elements of a potential WBS.

Q2: Level 2 WBS Headings Select 5 of the Level 1 Elements from Q1 and list potential Level 2 Headings under each. Use of the example DPTI WBS can be made for typical headings, however relevance to the example drawings must be maintained.

Q3: Level 3 WBS ItemsSelect at least 2 of the Level 1 Elements and their respective Level 2 Headings and make a comprehensive listing of Level 3 Items under each that exist on the drawings.

Q4: Referencing the source of your answers

Mark up the specific drawing detail / note (on the drawing) with a reference and include this in the table of answers to demonstrate the source of the your answers to questions 1-3.

Q5: Progress Claim Format

One of the uses of a well structured WBS is the recording and valuing of progress on the project. Research the format that this valuation may take and complete this format with a maximum of 20 cost items (Level 3 items). It is expected that you will need to research the following in preparation for your answer

  • What is the purpose of a progress claim
  • What key information should be included
  • What summary information should be presented

NOTE: The cost items only need to be examples of a format and no specific accuracy of 

Complete a WBS and quantity measurement for drainage elements (structures and culverts only) including appropriate units from the drawing "SEMP-J150-L1-001 Rev C". 

Further complete a WBS and quantity measurement for signage elements including appropriate units from the drawing "SEMP-J150-L1-003 Rev C".

Q7: Earthworks Calculation

For the given table of measured cross sections calculate the total cut and fill quantities.

The answer should incorporate a complete tabular calculation.

Calculate the cut to fill quantity and the import / export volumes.

Q8: Site inspection

Source and provide photos of a typical urban intersection (plan and street view). By viewing the photos of the site list at least 5 scope items that may be required that are not described on the design drawings and describe your basis for including them.

Q9: Summary of Project Scope for Review purposes

The effective briefing of management participants in tender reviews is an important skill. The success of the review process in the workflow may depend upon the summary of scope and existing conditions. With reference to the example drawings from Tutorial 1 and the above photos prepare a one page summary to brief the review teamList the different resource types commonly used in first principle estimates and provide at least 5 examples of resources for each type. For 2 of the 5 examples of each type describe the work activity / role that this resource may play in a typical civil construction project.

Q11: First principle estimate

Prepare a first principle estimate for the following activities

The following client provided WBS is to be used as the basis of pricing

Item Description Qty Unit Rate Amt

1 General Civil Works

1.1

Excavation to stockpile of soil 

materials, lead = 1km 500 m3

1.2

Supply and place 250mm of PM1/20 

gravel to hardstand 10,000 m2

Subtotal - General Civil Works

PROJECT TOTAL

Assume the following cost rates for resources

Resource Name Resource Descriptionf 6

Q10: Resource Types

List the different resource types commonly used in first principle estimates and provide at least 5 examples of resources for each type. For 2 of the 5 examples of each type describe the work activity / role that this resource may play in a typical civil construction project.

Q11: First principle estimate

Prepare a first principle estimate for the following activities

The following client provided WBS is to be used as the basis of pricing

Item Description Qty Unit Rate Amt

1 General Civil Works

1.1

Excavation to stockpile of soil materials, lead = 1km 500 m3

1.2

Supply and place 250mm of PM1/20 gravel to hardstand 10,000 m2

Subtotal - General Civil Works

PROJECT TOTAL

Assume the following cost rates for resources

Resource Name Resource Description Cost Unit lab Labour 50.00 hr exc30 Excavator 30t 130.00 hr grader Grader 140 equiv 140.00 hr truck Tandem tipper 85.00 hr roller 12t smooth drum 95.00 hr w/c 12,000l water cart 100.00 hr PM2/20 Quarry Rubble 15.00 tonne

Q12: Types of risk

Briefly y describe the difference between inherent and contingent risk.

List and describe a contingent risk that may apply to the first principle estimate in Q11.Q13: Inherent Risk Ranging

Provide 3 example direct cost items (Level 3) and insert into the example layout provided. Undertake ranging of the quantity and rates with discussion of the basis of this ranging. Calculate statistically possibly L-ML-H amounts for each item.

Q14: Contingent Risk Identification

Provide 3 example examples of contingent risk items for a roadworks project. Insert a range of costs for each (just insert "example" data) and discuss the basis of this ranging. 

Indicate a percentage likelihood for each item based upon your approach to the ranging and the nature of contingent risk item selected.

Computer Engineering, Engineering

  • Category:- Computer Engineering
  • Reference No.:- M91609057

Have any Question?


Related Questions in Computer Engineering

Does bmw have a guided missile corporate culture and

Does BMW have a guided missile corporate culture, and incubator corporate culture, a family corporate culture, or an Eiffel tower corporate culture?

Rebecca borrows 10000 at 18 compounded annually she pays

Rebecca borrows $10,000 at 18% compounded annually. She pays off the loan over a 5-year period with annual payments, starting at year 1. Each successive payment is $700 greater than the previous payment. (a) How much was ...

Jeff decides to start saving some money from this upcoming

Jeff decides to start saving some money from this upcoming month onwards. He decides to save only $500 at first, but each month he will increase the amount invested by $100. He will do it for 60 months (including the fir ...

Suppose you make 30 annual investments in a fund that pays

Suppose you make 30 annual investments in a fund that pays 6% compounded annually. If your first deposit is $7,500 and each successive deposit is 6% greater than the preceding deposit, how much will be in the fund immedi ...

Question -under what circumstances is it ethical if ever to

Question :- Under what circumstances is it ethical, if ever, to use consumer information in marketing research? Explain why you consider it ethical or unethical.

What are the differences between four types of economics

What are the differences between four types of economics evaluations and their differences with other two (budget impact analysis (BIA) and cost of illness (COI) studies)?

What type of economic system does norway have explain some

What type of economic system does Norway have? Explain some of the benefits of this system to the country and some of the drawbacks,

Among the who imf and wto which of these governmental

Among the WHO, IMF, and WTO, which of these governmental institutions do you feel has most profoundly shaped healthcare outcomes in low-income countries and why? Please support your reasons with examples and research/doc ...

A real estate developer will build two different types of

A real estate developer will build two different types of apartments in a residential area: one- bedroom apartments and two-bedroom apartments. In addition, the developer will build either a swimming pool or a tennis cou ...

Question what some of the reasons that evolutionary models

Question : What some of the reasons that evolutionary models are considered by many to be the best approach to software development. The response must be typed, single spaced, must be in times new roman font (size 12) an ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As