Q1. A specialty software development firm is planning to offer one of four new software products and wishes to maximize profit, minimize risk, and increase market share. If a weight of 65% is assigned to profit potential, 20% to profitability risk, and 15% to market share, identify the product that would be best for the firm to introduce.

New product

Profit potential ($)

Profit risk ($)

Market share

SW1

80k

40k

High

SW2

120k

30k

Low

SW3

160k

60k

Medium

SW4

120k

40k

Medium

Q2. The following payoff matrix indicates the expected profits associated with three decision options and three states of nature:

 

State of nature

S1

S2

S3

 

Option

T1

30

50

60

T2

40

60

20

T3

60

20

40

Select the decision option that should be selected for i) the maximin rule, ii) the maximax rule, iii) the Laplace rule, iv) the Hurwicz rule with α=0.25.

Q3. An item of energy-efficient equipment can be installed for $20,000, and which is expected to have a salvage value of $5,000 after 20 years, is expected to save $8,000 in energy costs per year.
i) What is the rate of return if the equipment is in operation for 20 years?
ii) For what lifetime will the equipment give a return of 10% ?

Q4. A manufacturing plant has the capacity to assemble 500,000 units per year. At present it is operating at 75% of capacity. The annual income is $500,000. The annual fixed cost is $150,000 and the variable cost $0.40 per unit assembled.
i) What is the annual profit or loss of the centre?
ii) At what volume of output does the centre break even?
iii) What will be the profit or loss at 70%, 80% and 90% of capacity on the basis of constant income per unit and constant variable cost per unit?

Q5. A used automobile can be purchased by a student to provide transportation to and from university for $10,000 as-is (i.e. without warranty). First year maintenance cost is expected to be $400 and the maintenance costs will increase by $100 per year thereafter. Operation costs for the automobile will be
$2,000 for every year the automobile is used and its salvage value decreases by 15% per year.
i) What is the economic life of the vehicle without considering the varying value of money over time?
ii) What is the economic life of the vehicle if the rate of interest is 5%?

Q6. A component manufacturer has a demand of 160 units per week. No shortages are allowed. It costs $250 to initiate manufacturing to produce at a rate of 500 units per week. The unit production cost is $40. The holding cost is $0.25 per unit. Determine
i) the minimum cost production quantity,
ii) the minimum cost procurement level if production lead time is 12 weeks.

Q7. Customers arrive at a rate of 180 per hour at either of two vending machines, each of which can service 240 customers per hour. Assuming a Poisson distribution for arrivals and an exponential distribution for the service time, determine the expected waiting time per customer. Recalculate if one of the vending machines is broken and cannot be used.

Q8. In Question 7 above, if the cost of operating a vending machine over its lifetime is $100 per day, and the cost of having customers waiting for service is 50 cents per minute, what is the optimum number of vending machines?

Q9. A survey taken over 20 days showed the number of defective cars on a highway as per Table I, below. A sample of 150 cars was taken during each day. Construct a c-chart for the data. Is there any assignable cause of variation during this period?

Day

Defective cars

Day

Defective cars

1

12

11

9

2

15

12

7

3

13

13

13

4

7

14

10

5

14

15

6

6

17

16

18

7

8

17

15

8

21

18

5

9

12

19

14

10

14

20

12

Q10. Eight maintenance activities, their normal durations in weeks, and the crew sizes for the normal conditions are as follows:

Activity

Duration (weeks)

Crew size

AC

4

6

BC

6

8

BE

3

3

CD

2

3

CE

4

2

DF

6

4

EF

5

5

FG

4

8

i) Represent the maintenance project in the form of an activity-event network.
ii) Identify the critical path and find the minimum time for project completion.
iii) Extra crew members can be used to expedite activities BC, DF and EF at a cost given below:

Extra crew

Weeks saved

Crash cost per week

1

1

$100

2

2

$125

3

2

$150

4

3

$200

If there is a penalty cost of $1,200 per week beyond the minimum maintenance time of 16 weeks, then recommend the minimum-cost schedule.

Other Engineering, Engineering

  • Category:- Other Engineering
  • Reference No.:- M92284141
  • Price:- $60

Guranteed 36 Hours Delivery, In Price:- $60

Have any Question?


Related Questions in Other Engineering

Register design a cpu register is simply a row of

Register design A CPU register is simply a row of flip-flops (i.e. SR, JK, T, etc) put side by side in an array to make the size of register required. For example, an 8 bit register has 8 flip-flops side by side for stor ...

A detailed review of spatial modulation and simulation

A Detailed Review of Spatial Modulation and Simulation Learning Outcomes a. Learn how to model mobile communication channels d. Discern knowledge development and directions on the recent advances in 4G to the research pr ...

Mine safety amp environmental engineering assignment -part

Mine Safety & Environmental Engineering Assignment - Part 1 - Questions 1. Occupational health and safety is the primary factor that needs to be considered in the mining industry. Discuss this statement. 2. Define the fo ...

Projectflow processing of liquor in a mineral refining

Project Flow Processing of Liquor in a Mineral Refining Plant The aim of this project is to design a flow processing system of liquor (slurry) in a mineral (aluminum) refining plant. Aluminum is manufactured in two phase ...

Learning outcomes evaluate multiuser communication and

Learning Outcomes Evaluate multiuser communication and resource sharing techniques; Apply the techniques of, and report on, digital communication applications using Matlab and hardware devices. Assignment Description The ...

Operations engineering assignment -please select only one

Operations Engineering Assignment - Please select only one of the following case studies for your assignment: CASE A. Tesla Motors Tesla is an innovative manufacturer that designs, assemble and sells fully electric vehic ...

Select a risk problem from the list below and prepare a

Select a risk problem from the list below and prepare a risk management plan in accordance with AS/NZS ISO 31000:2009. Please ensure that: - Establish the context clearly, in accordance with the Standard; - Define your s ...

Engineering materials term paper assignment -conduct a

ENGINEERING MATERIALS TERM PAPER ASSIGNMENT - Conduct a thorough literature search and write a 15-20 page technical review paper on the evolution of the engineering materials used in the manufacturing of any one of the f ...

Task 1using the lab kit design a circuit for the processor

Task 1: Using the lab kit, design a circuit for the processor to control the output of a connected 7-segment LED display device. You will be provided with a standard common anode 7-segment display of the type FND-507 (or ...

Control theory - lab reportsfor experiments 1 to 4 you must

Control Theory - Lab Reports For experiments 1 to 4 you must undertake the following: a) At the start of each section (including the pre-lab activities) there are a number learning outcomes. That is, what students should ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As