Problem 1

The following data were obtained from a project to create a new portable electronic.

Activity Duration Predecessors
A 5 Days ---
B 6 Days ---
C 8 Days ---
D 4 Days A, B
E 3 Days C
F 5 Days D
G 5 Days E, F
H 9 Days D
I 12 Days G

Step 1: Construct a network diagram for the project.

Step 2: Answer the following questions:

a) What is the Scheduled Completion of the Project?

b) What is the Critical Path of the Project?

c) What is the ES for Activity D?

d) What is the LS for Activity G?

e) What is the EF for Activity B?

f) What is the LF for Activity H?

g) What is the float for Activity I?

Problem 2

The following data were obtained from a project to build a pressure vessel:

Activity Duration Predecessors
A 6 weeks ---
B 6 weeks ---
C 5 weeks B
D 4 weeks A, C
E 5 weeks B
F 7 weeks D, E, G
G 4 weeks B
H 8 weeks F
I 5 weeks G
J 3 week I

Step 1: Construct a network diagram for the project.

Step 2: Answer the following questions:

a) Calculate the scheduled completion time.

b) Identify the critical path

c) What is the slack time (float) for activity A?

d) What is the slack time (float) for activity D?

e) What is the slack time (float) for activity E?

f) What is the slack time (float) for activity G?

Problem 3

The following data were obtained from a project to design a new software package:

Activity Duration Predecessors
A 5 Days ---
B 8 Days ---
C 6 Days A
D 4 Days C, B
E 5 Days A
F 4 Days D, E, G
G 4 Days B, C
H 3 Day G

Step 1: Construct a network diagram for the project.

Step 2: Answer the following questions:

a) Calculate the scheduled completion time.

b) Identify the critical path(s)

c) What is the slack time (float) for activity B?

d) What is the slack time (float) for activity D?

e) What is the slack time (float) for activity E?

f) What is the slack time (float) for activity G?

Problem 4

The following data were obtained from an in-house MIS project:

Activity Duration Predecessors
A 5 Days ---
B 8 Days ---
C 5 Days A
D 4 Days B
E 5 Days B
F 3 Day C, D
G 7 Days C, D
H 6 Days E, F, G
I 9 Days E, F

Step 1: Construct a network diagram for the project.

Step 2: Answer the following questions:

a) Calculate the scheduled completion time.

b) Identify the critical path

c) What is the slack time (float) for activity A?

d) What is the slack time (float) for activity D?

e) What is the slack time (float) for activity E?

f) What is the slack time (float) for activity F?

Computer Engineering, Engineering

  • Category:- Computer Engineering
  • Reference No.:- M91355810
  • Price:- $20

Guranteed 24 Hours Delivery, In Price:- $20

Have any Question?


Related Questions in Computer Engineering

Michelle walker is looking to invest in a three-year bond

Michelle Walker is looking to invest in a three-year bond that makes semi-annual coupon payments at a rate of 5.225 percent. If these bonds have a market price of $990.00, what yield to maturity can she expect to earn?  ...

Take screenshots of functions running in clisplet x1 x2 xn

Take screenshots of functions running in cLISP, Let x1, x2, ...xN be a set of input features. A linear function that represent those features, will have a following form: Fw(x1, x2, .. xn)= w0 + w1 * x1 + w2 * x2 +... + ...

Assignment - dijkstra algorithmdijkstras algorithm finds

Assignment - Dijkstra Algorithm Dijkstra's algorithm finds the shortest path from a given node to all other nodes. 1) We observe that we can modify this algorithm to stop as soon as a particular node is reached; thus pro ...

Question in ruby as in java 8 or scala an interface mix-in

Question : In Ruby, as in Java 8 or Scala, an interface (mix-in) can provide method code as well as signatures. (It can't provide data members; that would be multiple inheritance.) Explain why dynamic typing makes this f ...

In this project you will format a document you will select

In this project, you will format a document. You will select and format text and then use the Find and Replace command to correct errors in the document. You will convert text to a numbered list as well as a bulleted lis ...

What is the difference between dekkers algorithm and igloo

What is the difference between Dekkers Algorithm and Igloo approach? Please provide examples that can explain this.

Question this discussion focuses on mapping cloud security

Question: This discussion focuses on mapping cloud security controls to existing frameworks or regulations. You will need to create 1 new thread AND post AT LEAST 2 comments on other students' threads. Here's how to get ...

What is the solution for chapter 15 3e for java programming

What is the solution for chapter 15 3e for java programming 8th edition Create a JFrame that holds fjive buttons with the names of five different fonts. Include a sexth button that the user can click to make a font large ...

Introduction to software developmentmenu-driven

Introduction to Software Development Menu-Driven Programs TASKS: Language translator. Design a program that display the following menu: Select a language and I will say Good Morning English Italian Spanish German End the ...

Question suppose we are given a chain of n nodes as shown

Question : Suppose we are given a "chain" of n nodes as shown below. Each node i is "neighbors" with the node to its left and the node to its right (if they exist). An independent set of these nodes is a subset of the no ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As