As with all Trident courses, you're expected to provide references and citations. It's recommended you use the sources listed in the Module. Resist the temptation to browse the Web, looking for "clues." There's a lot of confusing stuff out there, and much of it is irrelevant. This Module contains all the information you need. Study it - use it!

Case Assignment

The Galaxy project consists of 8 interdependent tasks, labeled A through H. You've consulted experts, and have determined an optimistic, likely and pessimistic completion time (in days) for each of the tasks. The dependencies, and the times, are listed below.

Task

Precursor(s)

Optimistic

Likely

Pessimistic

A

(start)

2

6

9

B

A

18

19

20

C

A

10

12

14

D

A

12

18

24

E

(start)

13

14

16

F

B, C, D

8

12

16

G

D, E

6

8

10

H

F, G

17

20

21

(end)

H




1. Draw a path diagram for the project.

2. Calculate the expected length of each task. Fill in the following worksheet.

Task

Optimistic (O)

Likely (L)

Pessimistic (P)

Expected Task

A

2

6

9


B

18

19

20


C

10

12

14


D

12

18

24


E

13

14

16


F

8

12

16


G

6

8

10


H

17

20

21


3. Use the following worksheet to determine the lengths of all possible paths. Determine the critical path. What is its length?

Path (Listing of tasks on the path)

Expected Path Length

















The Mojo Project consists of 14 interrelated tasks, A through N. Their estimated normal completion times, normal costs, crash times and crash costs are given below. (Times in weeks; costs in thousands of dollars.)

Task

Predecessors

Normal Time

Normal Cost

Crash Time

Crash Cost

A

(start)

3

4

2

5

B

(start)

5

6

4

7

C

A

2

3

2

4

D

A

4

8

3

10

E

A

3

5

2

7

F

B

9

14

7

16

G

B

4

5

3

7

H

C, D

4

7

2

9

I

D

6

2

5

3

J

F

12

10

11

15

K

H

4

6

3

7

L

E, I, J

10

18

8

20

M

K, L

8

10

6

14

N

G

7

5

6

8

Use an online application (e.g., Sporkforge, 2014) to find the critical path, using the estimated normal times. Copy the output of the app into your upload as an image.

4. Which tasks are on the critical path?

5. What is the expected completion time of the project?

Instead of being finished in 4 weeks, task D takes 8 weeks.

6. Which (if any) tasks should be crashed, to make up the lost time? Why?

7. What is the additional cost of crashing the project?

Assignment Expectations

• For Part 1; Draw a PERT-CPM diagram clearly showing all the paths, plus the critical path. You may draw the diagram by hand, and paste a scanned image into your upload, but it must be totally legible.

• For Part 2; A PERT-CPM diagram is not required. Use an online app; paste an image of the app output into your paper.

• Show, and explain, all the calculations supporting your answers.

• Unambiguously state your answers.

Engineering Mathematics, Engineering

  • Category:- Engineering Mathematics
  • Reference No.:- M92019533

Have any Question?


Related Questions in Engineering Mathematics

Q undirected vs directed connectivitya prove that in any

Q: Undirected vs. directed connectivity. (a) Prove that in any connected undirected graph G = (V, E) there is a vertex v ? V whose removal leaves G connected. (Hint: Consider the DFS search tree for G.) (b) Give an examp ...

All these questions should be answered in matlab 1 generate

All these questions should be answered in MATLAB !!! 1. Generate a set of 3 random patterns of dimension 12 where each value is +1 or -1.(3 random 12*12 matrix) 2. Create a 12-unit Hopfield network (a 12x12 matrix) from ...

I have these questions for a homework assignment and have

I have these questions for a homework assignment and have to show work. This works with MIPS coding language and is the class Introduction to Computer Architecture. 1. Find the 2's complement representation (in 32-bit he ...

Question 1 - many spas many componentsconsider 4 types of

Question 1 - Many spas, many components Consider 4 types of spa tub: Aqua-Spa (or FirstSpa, or P1), Hydro-Lux (or SecondSpa, or P2), ThirdSpa (or P3) and FourthSpa (or P4), with the production of products P1, ..., P4 in ...

Analytical methods for engineers assignment - calculusthis

ANALYTICAL METHODS FOR ENGINEERS ASSIGNMENT - CALCULUS This assignment assesses Outcome - Analyse and model engineering situations and solve problems using calculus. Questions - Q1. Differentiate the following functions ...

Clculus assignment -q1 find the total differential of w

CALCULUS ASSIGNMENT - Q1. Find the total differential of w = x 3 yz + xy + z + 3 at (x, y, z) = (1, 2, 3). Q2. Find the value of the double integral ∫∫ R (6x + 2y 2 )dA where R = {(x, y)| - 2 ≤ y ≤ 1, y 2 ≤ x ≤ 2 - y. Q3 ...

Numerical analysis assignment -q1 define the following

Numerical Analysis Assignment - Q1. Define the following terms: (i) Truncation error (ii) Round-off error Q2. Show that if f(x) = logx, then the condition number, c(x) = |1/logx|. Hence show that log x is ill-conditioned ...

Question what is the signed binary sum of 1011100 and

Question : What is the signed binary sum of 1011100 and 1110101 in decimal? Show all of your work. What is the hexadecimal sum of 9A88 and 4AF6 in hexadecimal and decimal? Show all of your work.

Question a signal starts at point x as it travels to point

Question : A signal starts at point X. As it travels to point Y, it loses 8 dB. At point Y, the signal is boosted by 10 bB. As the signal travels to point Z, it loses 7 dB. The dB strength of the signal at point Z is -5 ...

Show all your work not just the answerswhen you multiply 21

(SHOW ALL YOUR WORK, not just the answers) When you multiply: 21 x 68 you most likely do: 8x1 + 8x20 + 60x1 + 60x20 = 1, 428 So, there are 4 multiplications and then 3 additions. How long would it take a computer to do t ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As