One of the tools used to manage large projects is known as the critical path method (CPM). In CPM the manager builds a network of all phases of a project and then evaluates the network to determine critical aspects of the project. In a CPM network, each vertex is an event, such as the start or completion of a task. The arcs connecting the vertices represent the duration of the activity. Unlike the examples in the text, they also store the name of the activity. To better understand the concept, let's look at a possible CPM plan to build a house. The network for this project is shown in Figure 11-26.

921_Steps for Building a House.jpg


Figure: Steps for Building a House

In the plan we see that it will take 10 days to prepare the building plan (A) and 5 days to get it approved (B). Furthermore, we can't start building until we have selected the contractor (C). We could construct the shortest path from the start to the end for our plan, but it would be of little value. On the other hand, if we determined the maximum path-that is, the path with the greatest sum of the weights-we would know which steps in our plan are critical. If a critical step slips even one day, we slip our end date. We can slip noncritical dates, however, without slipping our end date, so long as the slip does not change the critical path for the project.
Modify Algorithm 11-12, "Minimum Spanning Tree of a Graph," to determine the maximum path through the graph. Then provide a menu that allows the project manager to answer the following questions:

a. What is the shortest possible completion time (SPCT)? The SPCT is the longest path through the graph from beginning to end.

b. What is the earliest start time (EST) for each activity? The EST is the sum of the weights in the maximum spanning tree up to the activity.

c. What is the latest start time (LST) for each activity? The LST is the SPCT for the whole project minus the SPCT for the rest of the project (starting from the current activity).

d. What is the slack time for each activity? The slack time is LST - EST.

e. Is an activity a critical path item? (Critical path items have a slack time of zero.)

f. What is the critical path for the project? (The critical path is the sub graph consisting of the maximum spanning tree.)

Engineering Mathematics, Engineering

  • Category:- Engineering Mathematics
  • Reference No.:- M91914482

Have any Question?


Related Questions in Engineering Mathematics

Q undirected vs directed connectivitya prove that in any

Q: Undirected vs. directed connectivity. (a) Prove that in any connected undirected graph G = (V, E) there is a vertex v ? V whose removal leaves G connected. (Hint: Consider the DFS search tree for G.) (b) Give an examp ...

All these questions should be answered in matlab 1 generate

All these questions should be answered in MATLAB !!! 1. Generate a set of 3 random patterns of dimension 12 where each value is +1 or -1.(3 random 12*12 matrix) 2. Create a 12-unit Hopfield network (a 12x12 matrix) from ...

I have these questions for a homework assignment and have

I have these questions for a homework assignment and have to show work. This works with MIPS coding language and is the class Introduction to Computer Architecture. 1. Find the 2's complement representation (in 32-bit he ...

Question 1 - many spas many componentsconsider 4 types of

Question 1 - Many spas, many components Consider 4 types of spa tub: Aqua-Spa (or FirstSpa, or P1), Hydro-Lux (or SecondSpa, or P2), ThirdSpa (or P3) and FourthSpa (or P4), with the production of products P1, ..., P4 in ...

Analytical methods for engineers assignment - calculusthis

ANALYTICAL METHODS FOR ENGINEERS ASSIGNMENT - CALCULUS This assignment assesses Outcome - Analyse and model engineering situations and solve problems using calculus. Questions - Q1. Differentiate the following functions ...

Clculus assignment -q1 find the total differential of w

CALCULUS ASSIGNMENT - Q1. Find the total differential of w = x 3 yz + xy + z + 3 at (x, y, z) = (1, 2, 3). Q2. Find the value of the double integral ∫∫ R (6x + 2y 2 )dA where R = {(x, y)| - 2 ≤ y ≤ 1, y 2 ≤ x ≤ 2 - y. Q3 ...

Numerical analysis assignment -q1 define the following

Numerical Analysis Assignment - Q1. Define the following terms: (i) Truncation error (ii) Round-off error Q2. Show that if f(x) = logx, then the condition number, c(x) = |1/logx|. Hence show that log x is ill-conditioned ...

Question what is the signed binary sum of 1011100 and

Question : What is the signed binary sum of 1011100 and 1110101 in decimal? Show all of your work. What is the hexadecimal sum of 9A88 and 4AF6 in hexadecimal and decimal? Show all of your work.

Question a signal starts at point x as it travels to point

Question : A signal starts at point X. As it travels to point Y, it loses 8 dB. At point Y, the signal is boosted by 10 bB. As the signal travels to point Z, it loses 7 dB. The dB strength of the signal at point Z is -5 ...

Show all your work not just the answerswhen you multiply 21

(SHOW ALL YOUR WORK, not just the answers) When you multiply: 21 x 68 you most likely do: 8x1 + 8x20 + 60x1 + 60x20 = 1, 428 So, there are 4 multiplications and then 3 additions. How long would it take a computer to do t ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As