Ask Computer Engineering Expert

Mobile App (Work Breakdown Structure)

This assignment contains two deliverables: a summary document to be delivered in a word processor document format and a Work Breakdown Structure (WBS) to be delivered in a project file.

Overview:

Imagine that you work as the project manager for an IT department. Your organization has recently approved the development of a mobile application. As the project manager, you will manage the development of the project. The project will include user experience (UX) design by a consultant, graphic design by a team of two contracted designers, and in-house application development by a team of three programmers and a database developer.

Deliverable 1: Summary (MS Word or open source equivalent)

A. Write a one to two page summary document in which you:

a. Summarize the project requirements and other assumptions (i.e., budget, human resources, workload, environmental dependencies, etc.).
b. Define a work breakdown structure and describe the methodology behind constructing one.

Deliverable 2: WBS (MS Project or open source equivalent)

A. Use Microsoft Project or an open source equivalent to create a WBS which addresses the following:

a. Contain at least five main tasks, one for each of the PMBOK process areas.
b. Contain at least thirty line items distributed in five or more work packages.
c. Contain Work Breakdown Structure Code for each task.
d. Present duration estimates for each task that results in a duration estimate for the project not to exceed the requirements described in the overview.

Deliverable one of your assignment must follow these formatting requirements:

• Be typed, double spaced, using Times New Roman font (size 12), with one-inch margins on all sides; citations and references must follow APA or school-specific format. Check with your professor for any additional instructions.

• Include a cover page containing the title of the assignment, the student's name, the professor's name, the course title, and the date. The cover page and the reference page are not included in the required assignment page length.

The specific course learning outcomes associated with this assignment are:

• Explain and apply the phases of the project management life cycle.
• Develop processes that initiate technology projects, including project selection and defining project scope.
• Analyze and develop project schedules with appropriate techniques and software tools.
• Use technology and information resources to research issues in information systems and technology.
• Write clearly and concisely about Information Technology Project Management topics using proper writing mechanics and technical style conventions.

Computer Engineering, Engineering

  • Category:- Computer Engineering
  • Reference No.:- M92054257
  • Price:- $45

Priced at Now at $45, Verified Solution

Have any Question?


Related Questions in Computer Engineering

Does bmw have a guided missile corporate culture and

Does BMW have a guided missile corporate culture, and incubator corporate culture, a family corporate culture, or an Eiffel tower corporate culture?

Rebecca borrows 10000 at 18 compounded annually she pays

Rebecca borrows $10,000 at 18% compounded annually. She pays off the loan over a 5-year period with annual payments, starting at year 1. Each successive payment is $700 greater than the previous payment. (a) How much was ...

Jeff decides to start saving some money from this upcoming

Jeff decides to start saving some money from this upcoming month onwards. He decides to save only $500 at first, but each month he will increase the amount invested by $100. He will do it for 60 months (including the fir ...

Suppose you make 30 annual investments in a fund that pays

Suppose you make 30 annual investments in a fund that pays 6% compounded annually. If your first deposit is $7,500 and each successive deposit is 6% greater than the preceding deposit, how much will be in the fund immedi ...

Question -under what circumstances is it ethical if ever to

Question :- Under what circumstances is it ethical, if ever, to use consumer information in marketing research? Explain why you consider it ethical or unethical.

What are the differences between four types of economics

What are the differences between four types of economics evaluations and their differences with other two (budget impact analysis (BIA) and cost of illness (COI) studies)?

What type of economic system does norway have explain some

What type of economic system does Norway have? Explain some of the benefits of this system to the country and some of the drawbacks,

Among the who imf and wto which of these governmental

Among the WHO, IMF, and WTO, which of these governmental institutions do you feel has most profoundly shaped healthcare outcomes in low-income countries and why? Please support your reasons with examples and research/doc ...

A real estate developer will build two different types of

A real estate developer will build two different types of apartments in a residential area: one- bedroom apartments and two-bedroom apartments. In addition, the developer will build either a swimming pool or a tennis cou ...

Question what some of the reasons that evolutionary models

Question : What some of the reasons that evolutionary models are considered by many to be the best approach to software development. The response must be typed, single spaced, must be in times new roman font (size 12) an ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As