microsoft project help

1. This exercise begins with information for a Hydrogen Development Project. Working in Microsoft Project, you will create the task list, including summary tasks and their sub-tasks, create links between tasks and their predecessors, add resources, and make changes to the original plan. Each student is required to submit their own, unique Project file.

A. Enter the tasks, including the specified duration, specified predecessors, and specified resources from the HW8DataFile. Make the Start date of the project: July 1, 2015.

B. Make corrections to the lowest level on the subtasks first, to be able to meet the bolded dates. (You may have to make changes such as SS, FS or FF; or other minor corrections.) After you make your corrections, identify the Original Finish Date for the entire project. Save the baseline at this point.

C. The investors in the company sense the urgency to get this product to market faster to meet the growing need for alternative fuels. They want you to cut down the time it takes to get to the beginning of production, Task 96, by 10%. Think carefully about the variety of tasks, and then make the changes to get the 10% reduction. Document the changes (ID number, task name, duration change). Identify the new finish date.

For your written response to B and C, submit a Word document. Remember to make your changes in response to C in the project.

2. This exercise begins with information for an IT Consultant Business Startup. Working in Microsoft Project, you will create the task list, including summary tasks and their sub-tasks, create links between tasks and their predecessors, add resources, and make changes to the original plan. Each student is required to submit their own, unique Project file.

A. Enter the tasks, including the specified duration, specified predecessors, and specified resources from the HW9Data file. Make the Start date of the project: June 29, 2015.

B. Your business in charge of the IT Consultant Business Startup will be observing a week holiday for the week of the 4th of July and for the week of Labor Day. Be sure to enter the working exceptions for these holidays through the working time of the project, not through individual tasks or resources. After you make your corrections, identify the Original Finish Date for the entire project. Save the baseline at this point.

C. Your CEO feels the cost for the project to be excessive. Due to other projects planned, the CEO has asked for you to reduce the total cost for the project. The target budget for this operation is $55,000. Think carefully about the duration of the tasks and the resources required to make the project a success. Document the changes (ID number, task name, duration change, resource change, etc.) you plan on making to get the project under $55,000. Justify why you made the changes you did. Identify the new final cost of the project.

Computer Engineering, Engineering

  • Category:- Computer Engineering
  • Reference No.:- M91332642
  • Price:- $70

Guranteed 36 Hours Delivery, In Price:- $70

Have any Question?


Related Questions in Computer Engineering

Does bmw have a guided missile corporate culture and

Does BMW have a guided missile corporate culture, and incubator corporate culture, a family corporate culture, or an Eiffel tower corporate culture?

Rebecca borrows 10000 at 18 compounded annually she pays

Rebecca borrows $10,000 at 18% compounded annually. She pays off the loan over a 5-year period with annual payments, starting at year 1. Each successive payment is $700 greater than the previous payment. (a) How much was ...

Jeff decides to start saving some money from this upcoming

Jeff decides to start saving some money from this upcoming month onwards. He decides to save only $500 at first, but each month he will increase the amount invested by $100. He will do it for 60 months (including the fir ...

Suppose you make 30 annual investments in a fund that pays

Suppose you make 30 annual investments in a fund that pays 6% compounded annually. If your first deposit is $7,500 and each successive deposit is 6% greater than the preceding deposit, how much will be in the fund immedi ...

Question -under what circumstances is it ethical if ever to

Question :- Under what circumstances is it ethical, if ever, to use consumer information in marketing research? Explain why you consider it ethical or unethical.

What are the differences between four types of economics

What are the differences between four types of economics evaluations and their differences with other two (budget impact analysis (BIA) and cost of illness (COI) studies)?

What type of economic system does norway have explain some

What type of economic system does Norway have? Explain some of the benefits of this system to the country and some of the drawbacks,

Among the who imf and wto which of these governmental

Among the WHO, IMF, and WTO, which of these governmental institutions do you feel has most profoundly shaped healthcare outcomes in low-income countries and why? Please support your reasons with examples and research/doc ...

A real estate developer will build two different types of

A real estate developer will build two different types of apartments in a residential area: one- bedroom apartments and two-bedroom apartments. In addition, the developer will build either a swimming pool or a tennis cou ...

Question what some of the reasons that evolutionary models

Question : What some of the reasons that evolutionary models are considered by many to be the best approach to software development. The response must be typed, single spaced, must be in times new roman font (size 12) an ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As