Measurements of Economic Worth

There are several methods of economic worth used to compare alternatives. If you decide to use present worth analysis, then you have indicate a preference to use a single sum of money at a time called "the present" as the basis for comparison. If you decide a future worth analysis, then you prefer to use a single sum equivalent at a time called "the future" as the basis for comparison. If instead of expressing an investment's economic worth as a single sum equivalent, you prefer to think in terms of an annualized figure, then the annual worth would be preferred. Some prefer to express the net economic worth as a rate or percentage, which is known as the internal rate of return (IRR). Finally, some prefer to have the net economic worth expressed as a percentage of the investment required - the benefit cost ratio.

The nine DCF methods may be described as follows:

1. The present worth (PW) method converts all cash flow to a single sum equivalent at time zero using i = MARR (minimum attractive rate of return)

2. The future worth (FW) method converts all cash flow to a single sum equivalent at the end of the planning horizon using i = MARR.

3. The annual worth (AW) method converts all cash flow to an equivalent uniform annual series of cash flows over the planning horizon using i = MARR.

4. The internal rate of return (IRR) method determines the interest rate that yields a future worth (or present worth or annual worth) of zero.

5. The external rate of return (ERR) method determines the interest rate that equates the future worth of the invested capital to the future worth of recovery capital (when the later is computed using the MARR).

6. The modified internal rate of return (MIRR) method determines the interest rate that equates the PW of invested capital (where the present worth is calculated using a finance rate) to the future worth of recovered capital (where the future worth is calculated using the MARR).

7. The discounted payback period (DPBP) method determines how long it takes for the cumulative present worth to be positive using i =MARR.

8. The capitalized worth (CW) determines the present worth (using i = MARR) when the planning horizon is infinitely long.

9. The benefit/cost ratio (B/C) method determines the ratio of the present worth of benefits (saving or positive-valued cash flows) to the negative of the present worth of the investment(s) or negative-valued cash flows using i = MARR.

Other Engineering, Engineering

  • Category:- Other Engineering
  • Reference No.:- M9529015

Have any Question?


Related Questions in Other Engineering

Load fault level analysis amp protection design of a remote

LOAD, FAULT LEVEL ANALYSIS & PROTECTION DESIGN OF A REMOTE AREA MICROGRID Assignment Please undertake the following analyses: 1. Calculate the 3-phase fault levels on Bus 2, Bus 3 and Bus 4 with the main supply connected ...

Introduction to engineering design assignment -

Introduction to Engineering Design Assignment - Drafting Question 1 - Field notes and traverse drawing may be an outdated form of keeping and presenting information on the position of features on a site. Modern electroni ...

A detailed review of spatial modulation and simulation

A Detailed Review of Spatial Modulation and Simulation Learning Outcomes a. Learn how to model mobile communication channels d. Discern knowledge development and directions on the recent advances in 4G to the research pr ...

Engineering analysis assignment -for every problem provide

Engineering Analysis Assignment - For every problem, provide The MATLAB script/function files that solve the problems. Problem 1: Plot the function f(t) = (x+5) 2 /(4+3x 2 ) for -3 ≤ x ≤ 5. using plot command. Use the ar ...

Assignment -problem 1 - given is the lcc difference

Assignment - Problem 1 - Given is the LCC difference equation that represents some LTI system: y(n) - ¾y(n-1) - ¼y(n-2) = x(n) + x(n-1)   a) Find the impulse response of the system (solve the LCCDE). b) Draw a block diag ...

Engineering analysis homework -for every problem provide

Engineering Analysis Homework - For every problem, provide The MATLAB script/function files that solve the problems. Problem 1: Write a script that solves the problem. For (c), show results of the evaluation of every ind ...

Assignment 11 what is the purpose of ore reserve and

ASSIGNMENT 1 1. What is the purpose of ore reserve and resource estimation? Why are resource and reserve estimates important to the mining industry? 2. What is meant by ore? What is meant by the term waste? How is the di ...

Question 1 define rock mechanics discuss the main

Question 1 . Define rock mechanics. Discuss the main objectives of the application of rock mechanics in mining. Question 2. Define stress. Draw a diagram and define the normal and shear stress by resolving the resultant ...

Question - show that the zero-point energy of a simple

Question - Show that the zero-point energy of a simple harmonic oscillator does not contribute to its entropy or heat capacity, but does contribute to its energy and Helmholtz function.

Part 1configure verify and troubleshoot wan links and ip

Part 1 Configure, verify and troubleshoot WAN links and IP services Answer to all questions below: 1. What is the name of the Safe Work Australia code of practise that provides guidance on how to manage the risks of elec ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As