Ask Other Engineering Expert

Learning Outcomes

This assignment has been devised to allow students to demonstrate progress towards achieving the following unit learning outcomes:

Demonstrate familiarity with the Office of Government Commerce (OGC) framework and its impact on the Project Management discipline

Demonstrate knowledge of engineering project management tools and techniques such as: Work breakdown structures (WBS), Network diagrams, Critical path analysis.

Explain the importance of achieving organizational value from engineering projects and managing project risk

Explain the importance of the benefits management process to engineering projects and the techniques available for understanding both tangible and intangible benefits and measuring their delivery.

Task

Your team is nearing the completion of the project. Through this assignment, you should demonstrate key knowledge areas of project management as listed in PMBOK.

Working individually, the five individual submissions from your team members should complete all the tasks as listed below. There are five tasks in total. Each member of the team will complete one different task so that all the five tasks would be properly addressed within a team.

Task 1

1. List out the local government's legal prerequisite for starting your engineering project and justify the need of each requirement.

2. What are the potential dangers of proceeding with a project that has no SMART objectives? As a project manager develop an iron triangle policy for your project scope. Justify each of the factors

3. Assume any Engineering project and develop activities that can be mapped with the "Activity" and "predecessors" column mentioned below. For example, Task A as "Polishing sample", Task B as Characterization etc. till "K". Determine the critical path for the assumed project using MS project.

Activity

Duration (weeks)

Predecessors

A

2

--

B

1

--

C

2

B

D

2

A,B

E

3

A,C

F

2

A

G

1

A

H

1

C,G

I

1

H

J

3

I

K

4

C,F

Show the task column and predecessor's column of the project your team has been doing in for last 10 weeks as entered in MS PROJECT. The predecessor's column should show all the four types of task relationships. Explain the logic for choosing S-S, F-F & S-F relationship for at least 2 task each.

4. During the project review meeting, being a project manager you reported an up to date project completion status, which is 50% of the total project duration. The client wanted you to finish the project 10 days earlier than the original plan. Show the status of the project at 50% in MS PROJECT. This application should be for the project that your team has been doing for the last 10 weeks. Include snapshot of tracking Gnatt, show snap shot of tracking table with base line and actual date. Also, include snapshot of crashed project showing the new finish date, tracking cost table. From the tracking cost table find out the cost of crashing for the crashed activities.

Task 2

1. Do you require white card for the project your team has been working for last 10 weeks? If yes, elaborate the requirements to acquire white card in your project. If no, analyze the other requirements for skilled workers.

2. As a finance manager develop an iron triangle for cost management for your project. Justify each of the factors.

3. Assume any Engineering project and develop activities that can be mapped according to the following network diagram. For example, Task A is "Polishing sample", Task B is Characterization etc. Determine the critical path in MS project.

2290_figure.jpg

In MS PROJECT, show the critical path of the project your team has been doing for last 10 weeks. Explain the critical bottleneck activities from project start to end date. For the other activities, how much delay can be tolerated without delaying project completion? Include the MS project snapshots wherever necessary.

4. Explain the Earned value (EV) analysis in your project. Use MS project to show EV projections.

Task 3

1. As a Resource manager, develop an iron triangle for resource management for your project. Justify each of the factors.

2. Under uncontrollable circumstances, one of risk in your project could not be avoided. Due to this critical activity in your project has been impacted and lead to a delay of 10 days. For this scenario:
- Perform project crashing such that the project meet the deadline
- Develop a mitigation and contingency plan to avoid that risk in future.

3. In a project John has been assigned to tasks A to G. John cannot work more than 8 hrs a day. He must finish task A before starting any other task. The project manager has specified the dates by which he must finish each task. These dates are marked in RED. For example, activity A must finish by 5th may and B by 12th May and so on. John has planned his work as per the following table where against each activity he wrote numbers of hour he would be working for that activity. You as a project manager were not happy with John's work plan and reconfigured his plan. Why did you reconfigure John's work plan? Reconfigure work plan for John using MS Project. Assume real activities from A to G and proceed your work. For example, Task A as "Polishing sample , Task B as Characterization and so on for the complete project.

1377_figure1.jpg

4. For the project your team has been working on for the last 10 weeks, show the status of your project at 50% project completion. Due to unavoidable circumstances, impose a delay of 10 days now at few of the tasks. Show the cost and duration variance before imposing delay, after imposing delay and implementation of fast tracking with the help of appropriate snapshot of MS PROJECT.

Task 4

1. As a Quality manager, develop an iron triangle for quality management for your project. Justify each of the factors.

2. Assume any Engineering project and develop activities that can be mapped according to the following network diagram. For example, Task A is "Polishing sample", Task B is "Characterization" etc. Determine the critical path in MS project and perform
- crashing by resources and
- crashing by activities

566_figure2.jpg

3. (a) Consider you are a project manager for a company. The client wants tracking to be done to ensure project completes on time. List out the obstacles while tracking the project and give a brief explanation on each possible solution to avoid the conflicts.
(b) Perform the following tasks in MS project & use snapshots wherever necessary.
- Show tracking of your project in MS project by setting baseline as 70%.
- Due to obstacles while execution of the project, some of the tasks are incomplete. Use tracking module in MS project and show the tasks, which are affected & highlight the amount of work completed of the affected tasks.

4. List all the health and safety and the environmental laws (HSE) that you need to abide in the project. List out all such activities in your project that you are required to abide by HSE. Develop a mitigation and contingency plan where ever required.

Task 5 (For team member 5)

1. As a project manager develop an iron triangle for project integration management for your project. Justify each of the factors.

2. Provide the MS PROJECT resource sheet of the project your team has been working on for last 10 weeks. Which resources in the sheet are most susceptible to over allocation and why? Explain with at least four different techniques to remove resource over allocation in your project and shows its application. How these techniques would affect your project end date. Use MS project.

3. For the project your team has been working

(a) One of the work resource has two different cost rates for two different tasks assigned to the resource. Provide the snapshots of MS PROJECT showing two different rates for the resource. Also, provide the snapshot of MS PROJECT showing the cost of assigned tasks to the resource with different cost rates.

(b) Consider the fixed costs resources in your project and show its assignment to the required tasks in MS project.

4. (a) Impose a baseline at 30% project completion and perform split tasks for 5 activities in your project. Ensure that the project end date is not effected. Explain the reasons for this split tasking.

(b) At 70% of project completion, you have identified a 9-day delay in the project due to some unforeseen circumstances. Considering the uncertainties and the variance in the project, what is the probability that the project can be completed on time (as per the planned schedule), one day before the schedule and one date later than the schedule? Provide screenshots of MS project wherever required.

Attachment:- Assignment.rar

Other Engineering, Engineering

  • Category:- Other Engineering
  • Reference No.:- M92830038
  • Price:- $145

Guranteed 48 Hours Delivery, In Price:- $145

Have any Question?


Related Questions in Other Engineering

Register design a cpu register is simply a row of

Register design A CPU register is simply a row of flip-flops (i.e. SR, JK, T, etc) put side by side in an array to make the size of register required. For example, an 8 bit register has 8 flip-flops side by side for stor ...

A detailed review of spatial modulation and simulation

A Detailed Review of Spatial Modulation and Simulation Learning Outcomes a. Learn how to model mobile communication channels d. Discern knowledge development and directions on the recent advances in 4G to the research pr ...

Mine safety amp environmental engineering assignment -part

Mine Safety & Environmental Engineering Assignment - Part 1 - Questions 1. Occupational health and safety is the primary factor that needs to be considered in the mining industry. Discuss this statement. 2. Define the fo ...

Projectflow processing of liquor in a mineral refining

Project Flow Processing of Liquor in a Mineral Refining Plant The aim of this project is to design a flow processing system of liquor (slurry) in a mineral (aluminum) refining plant. Aluminum is manufactured in two phase ...

Learning outcomes evaluate multiuser communication and

Learning Outcomes Evaluate multiuser communication and resource sharing techniques; Apply the techniques of, and report on, digital communication applications using Matlab and hardware devices. Assignment Description The ...

Operations engineering assignment -please select only one

Operations Engineering Assignment - Please select only one of the following case studies for your assignment: CASE A. Tesla Motors Tesla is an innovative manufacturer that designs, assemble and sells fully electric vehic ...

Select a risk problem from the list below and prepare a

Select a risk problem from the list below and prepare a risk management plan in accordance with AS/NZS ISO 31000:2009. Please ensure that: - Establish the context clearly, in accordance with the Standard; - Define your s ...

Engineering materials term paper assignment -conduct a

ENGINEERING MATERIALS TERM PAPER ASSIGNMENT - Conduct a thorough literature search and write a 15-20 page technical review paper on the evolution of the engineering materials used in the manufacturing of any one of the f ...

Task 1using the lab kit design a circuit for the processor

Task 1: Using the lab kit, design a circuit for the processor to control the output of a connected 7-segment LED display device. You will be provided with a standard common anode 7-segment display of the type FND-507 (or ...

Control theory - lab reportsfor experiments 1 to 4 you must

Control Theory - Lab Reports For experiments 1 to 4 you must undertake the following: a) At the start of each section (including the pre-lab activities) there are a number learning outcomes. That is, what students should ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As