Engineering Management Assignment: Project Management Plan

HOUSE CONSTRUCTION PROJECT

PROJECT BRIEF - Project Background

You are a project manager for a medium-sized house construction company, and you just got a phone call from the company owner saying that he is with a customer who wants to know the indicative price for a 200 m2 house to be constructed in a section he owns. He wants you to call him back with to him a quick estimate of how much it will cost and how long it will take to complete the project. He also told you that you will be the project manager assigned to this project if and when the company owner closes the deal later.

What you are required to do:

To develop a Project Management Plan from the information given and set up the project using Microsoft Project.  You are required to submit the following for marking:

i. A Project Management Plan report AND

ii. a Microsoft Project 2010 ( or later version) file of the Project schedule (i.e. WBS, Gantt Chart and Network diagram) and all planning information

Your Project Management Plan report must cover

  • 10 project management knowledge areas
  • answer the key questions in the project brief
  • The role of the Engineer & Society
  • Environment & Sustainability issues relevant to the project
  • Any ethical issues
  • List all assumptions made

 Please refer to the following:

  • Marking Guide for the actual distribution of marks
  • Project Details and Key questions

PROJECT DETAILS & KEY QUESTIONS

ESTIMATING

You are a project manager for a medium-sized house construction company, and you just got a phone call from the company owner saying that he is with a customer who wants to know the indicative price for a 200 m2 house to be constructed in a section he owns. He wants you to call him back with to him a quick estimate of how much it will cost and how long it will take to complete the project. He also told you that you will be the project manager assigned to this project if and when the company owner closes the deal later.

1. Having been in the construction business and with this company for a good while, you know that direct cost is about $1,000 per m2. The indicative price is around twice the direct costs, plus or minus 10%. What is the indicative price you will give your manager?

2. You were about to make the call when suddenly an incoming email popped in from Finance about price adjustment of 10% for all direct costs because of inflation over the past several years. What will be the new indicative price?

3. A typical house 100 m2 to 300 m2 will take about 3 to 4 working months (or 12 to 16 working weeks) to complete. What indicative schedule, in working months or working weeks, will you give the owner?

4. After giving the indicative price to your boss, you went down to do a more detailed estimate. First you need WBS. Create and sketch aWBS from the following:

Foundation

Site preparation and excavation

Reinforced concrete

Framing and Roofing

Rough framing

Siding, windows, insulation, plaster

Roof

Plumbing

Plumbing rough in

Plumbing fixtures

Electrical and Heating

Wiring rough in

Lighting and heating fixtures

Finishing

Painting

Finish hardware and chattels

Floor and carpet

Interior decorating

5. Using the apportioning method, determine the cost of all the project tasks.

Foundation        

Site preparation and excavation                3%

Reinforced concrete       4%

Framing and Roofing     

Rough framing  12%

Siding, windows, insulation, plaster         14%

Roof      9%

Plumbing            

Plumbing rough in           6%

Plumbing fixtures            4%

Electrical and Heating    

Wiring rough in 4%

Lighting and heating fixtures       8%

Finishing             

Painting                8%

Finish hardware and chattels      12%

Floor and carpet               8%

Interior decorating          8%

Total      100%

The owner came back saying the client is very excited because it falls very much within his budget. He now wants a more detailed estimate and a proposal.

6. Estimate the cost of Foundation work given the following:

  • Site Preparation and Excavation will need 3 men to work over 5 days. Each personnel costs $200 per day. A mini-bulldozer is also needed for 2 days at $1,000 a day, and about $1,500 for various materials.3 marks
  • Reinforced Concrete foundation will need 4 men to complete the work over 4 days. 18 m3 of reinforced concrete at $300 per m3 will be needed.2 marks

a. From your detailed estimate, how much is the total cost of Foundation work?

b. What is the variance (%) between your two estimates (i.e., apportioning vs. detailed method)?

c. What does the variance say about your company's estimating methods?

7. Estimate the duration of Painting work given the following:

  • From the house plan, it was estimated that there will be about 1,350 m2 of surface to be painted.
  • You can put up to 3 personnel to work on painting and each of them can finish 56 m2 of surface a day

a. How soon will it take to complete all the Painting work?

b. How many days longer will it for the Painting work to finish if you are able to get only 2 personnel for it?

8. Your detailed (bottom-up) estimate shows the following:

  • Labour, Materials and Equipment

Labour                  $65,600

Materials             $6,500

Equipment          $155,900

a. What is the Direct Cost from the project?

  • Direct Overhead Cost from the project is 25% of the Direct Cost

b. What is the Total Direct Costs from the project? (N.B. Total Direct Costs is equal to Total Direct Cost plus Direct Overhead Cost)

  • General and Administrative (G&A) Overhead is 20% of Total Direct Cost
  • Management Contingency is 10% of Total Direct Cost
  • Profit is 30% of Total Direct Cost

c. What is the Total Bid Price for this project?

d. What is the variance (%) between the Indicative Price and the Total Bid Price for this project? (N.B. Remember in #1, your Indicative Price may vary within + or - 10% of estimate and so the from Total Bid Price will be different depending on what you used).

Attachment:- Management Assignment.rar

Other Engineering, Engineering

  • Category:- Other Engineering
  • Reference No.:- M92003080

Have any Question?


Related Questions in Other Engineering

Register design a cpu register is simply a row of

Register design A CPU register is simply a row of flip-flops (i.e. SR, JK, T, etc) put side by side in an array to make the size of register required. For example, an 8 bit register has 8 flip-flops side by side for stor ...

A detailed review of spatial modulation and simulation

A Detailed Review of Spatial Modulation and Simulation Learning Outcomes a. Learn how to model mobile communication channels d. Discern knowledge development and directions on the recent advances in 4G to the research pr ...

Mine safety amp environmental engineering assignment -part

Mine Safety & Environmental Engineering Assignment - Part 1 - Questions 1. Occupational health and safety is the primary factor that needs to be considered in the mining industry. Discuss this statement. 2. Define the fo ...

Projectflow processing of liquor in a mineral refining

Project Flow Processing of Liquor in a Mineral Refining Plant The aim of this project is to design a flow processing system of liquor (slurry) in a mineral (aluminum) refining plant. Aluminum is manufactured in two phase ...

Learning outcomes evaluate multiuser communication and

Learning Outcomes Evaluate multiuser communication and resource sharing techniques; Apply the techniques of, and report on, digital communication applications using Matlab and hardware devices. Assignment Description The ...

Operations engineering assignment -please select only one

Operations Engineering Assignment - Please select only one of the following case studies for your assignment: CASE A. Tesla Motors Tesla is an innovative manufacturer that designs, assemble and sells fully electric vehic ...

Select a risk problem from the list below and prepare a

Select a risk problem from the list below and prepare a risk management plan in accordance with AS/NZS ISO 31000:2009. Please ensure that: - Establish the context clearly, in accordance with the Standard; - Define your s ...

Engineering materials term paper assignment -conduct a

ENGINEERING MATERIALS TERM PAPER ASSIGNMENT - Conduct a thorough literature search and write a 15-20 page technical review paper on the evolution of the engineering materials used in the manufacturing of any one of the f ...

Task 1using the lab kit design a circuit for the processor

Task 1: Using the lab kit, design a circuit for the processor to control the output of a connected 7-segment LED display device. You will be provided with a standard common anode 7-segment display of the type FND-507 (or ...

Control theory - lab reportsfor experiments 1 to 4 you must

Control Theory - Lab Reports For experiments 1 to 4 you must undertake the following: a) At the start of each section (including the pre-lab activities) there are a number learning outcomes. That is, what students should ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As