Design of Temporary Structures Assignment 1-

Problem No. 1 - What total load will a AS 550 steel shore be able to carry if the outside diameter is 2.5 inches and a wall thickness of 0.154 inches? The unsupported length of the shore is 10 feet. Solve for both ASD and LRFD criteria. (Assume Fy = 50,000 psi and E = 29000)

Problem No. 2 - Assuming that the manufacturer's specification for the shore in Problem No. 1 is 9400 pounds and all other criteria (i.e., OD and ID) are the same, and assuming a factor of safety of 3, what is the actual strength of the steel.

Problem No. 3 - Referring to sample Problem 8.4 on page 8-7, if the depth of the slab is increased to 12 inches, is this still an acceptable solution?

Problem No. 4 - Referring to sample Problem 8.4 on page 8-7, if the depth of the slab is increased to 12 inches and the shoring frames are increased to 6 feet in width, is this still an acceptable solution?

Assignment 2-

Problem Statement: Here's a little problem that has been sitting on my desk. The East Wall of the Elizabeth River is beginning to fail and needs to be replaced. The masonry wall (the East Wall) has deteriorated and is to be replaced with the concrete wall that is shown on the attached. As part of this project, the low flow channel (the half pipe in the middle of the channel) is to be replaced with a 36" RCP that will be basically cut in two and used as the low flow channel. The 6 inch thick concrete channel on the east side is to be replaced as well as the wall. The section is 500 feet long. Therefore, your assignment is:

1. Design the formwork for the East Wall. A control joint is to be placed every 25 feet. The construction of the wall will require 2 pours; one for the foundation of the wall with a key way and a second pour for the vertical section of the wall. The forms will be wood (Doug Fir) and may be reused if you wish. You will need designs for both sections. You may assume that the existing wall has been removed and that you have unlimited access to the both sides of the wall (i.e., the channel side and the road side) and are not responsible for excavation or backfill.

2. Provide a narrative for your construction sequence for building this project. This should include the order of construction, how you will do the entire project (including the channel and the low flow channel) and how you expect to construct the entire project. You have 40 working days to complete the entire project. A schedule summarizing the construction sequence for the complete project should be attached. You may assume a S day week and 40 hours per week. Also, you may assume no weather delays. The project will be constructed during June and July.

3. Provide a set of plans for your formwork. These plans should be done in AutoCAD and must be your original work. You may not use a manufacturer's drawing that you have downloaded. Also, the plans should be done in a professional manner as though were supplying these as a submittal to the Engineer.

Attachment:- Assignment.rar

Other Engineering, Engineering

  • Category:- Other Engineering
  • Reference No.:- M91768434

Have any Question?


Related Questions in Other Engineering

Register design a cpu register is simply a row of

Register design A CPU register is simply a row of flip-flops (i.e. SR, JK, T, etc) put side by side in an array to make the size of register required. For example, an 8 bit register has 8 flip-flops side by side for stor ...

A detailed review of spatial modulation and simulation

A Detailed Review of Spatial Modulation and Simulation Learning Outcomes a. Learn how to model mobile communication channels d. Discern knowledge development and directions on the recent advances in 4G to the research pr ...

Mine safety amp environmental engineering assignment -part

Mine Safety & Environmental Engineering Assignment - Part 1 - Questions 1. Occupational health and safety is the primary factor that needs to be considered in the mining industry. Discuss this statement. 2. Define the fo ...

Projectflow processing of liquor in a mineral refining

Project Flow Processing of Liquor in a Mineral Refining Plant The aim of this project is to design a flow processing system of liquor (slurry) in a mineral (aluminum) refining plant. Aluminum is manufactured in two phase ...

Learning outcomes evaluate multiuser communication and

Learning Outcomes Evaluate multiuser communication and resource sharing techniques; Apply the techniques of, and report on, digital communication applications using Matlab and hardware devices. Assignment Description The ...

Operations engineering assignment -please select only one

Operations Engineering Assignment - Please select only one of the following case studies for your assignment: CASE A. Tesla Motors Tesla is an innovative manufacturer that designs, assemble and sells fully electric vehic ...

Select a risk problem from the list below and prepare a

Select a risk problem from the list below and prepare a risk management plan in accordance with AS/NZS ISO 31000:2009. Please ensure that: - Establish the context clearly, in accordance with the Standard; - Define your s ...

Engineering materials term paper assignment -conduct a

ENGINEERING MATERIALS TERM PAPER ASSIGNMENT - Conduct a thorough literature search and write a 15-20 page technical review paper on the evolution of the engineering materials used in the manufacturing of any one of the f ...

Task 1using the lab kit design a circuit for the processor

Task 1: Using the lab kit, design a circuit for the processor to control the output of a connected 7-segment LED display device. You will be provided with a standard common anode 7-segment display of the type FND-507 (or ...

Control theory - lab reportsfor experiments 1 to 4 you must

Control Theory - Lab Reports For experiments 1 to 4 you must undertake the following: a) At the start of each section (including the pre-lab activities) there are a number learning outcomes. That is, what students should ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As