Ask Other Engineering Expert

CONSTRUCTION SITE OPERATIONS FINAL EXAM

This Examination is part of the assessment for the non OH&S component of the Construction Site Operations.

BACKGROUND -

Your company (a contracting firm) has been contracted by City of Sunshine to construct a Track and field Pavilion & associated Works as part of an upgrade to the services provided in the area. (Sunshine). City of Sunshine is the Client and the funding is provided by grants from the State Government. The new Track and field Pavilion will assist the community to engage in leisure activities in the area - where possible, all SubContractors, day labourers, relevant materials and Plant and Equipment hire are to be sourced from the local district.

During the 'Pre-Tendering' phase, all tenderers had adequate time and sufficient guidance to thoroughly inspect the site, fully review all the geotechnical information and the detailed plans for the Project and access to all relevant technical and non-technical data they needed to be fully prepared to make an informed bid. They were also given an assessment of the availability and skills of labour in the area as well as the type of material (although untested) and equipment located there. All tenderers were required to acknowledge, in writing, that they had appropriate access and professional guidance to all the necessary information they required to be able to make an informed bid.

FURTHER INFORMATION -

A. Construction time for the project was specified as 12 months. AS 4000 has been selected as the General Conditions of Contract for the project.

B. Your company has engaged a site management team (Project Manager, Contracts Administrator, Site Engineer, Site Foreman, Accounts Clerk). Client has assigned a Project Manager (Client) to act as Superintendent and a design engineer to resolve any design issues during construction. Client also has other stakeholders (local tennis club; Community leader; Council Member).

C. Early in the construction several errors are found in the plans provided by the Client. Significant redesign is required before work can continue. These errors were notified by the Contractor and Superintendent issued direction to clarify the ambiguities and corrected the errors. Contractor has submitted claims during first month for additional cost (estimated additional cost $15,000) but maintained the time for completion at 12 months.

D. During excavation and preparation of both the 'green field' and 'brown field' areas, 'objects of antiquity' were uncovered in the area where tennis pavilion to be constructed. During second month, object of antiquity was found and it was removed and handed over to the client. This set back the project by 10 days. Contractor has spent $80,000 in dealing with the removal of "object of antiquity"

E. During third month, Client decided to change the material for seating to be used in the pavilion. Your company has already ordered the material as per original drawing. Superintendent chose to direct the changes under AS 4000. Estimated additional cost in respect of this change is $100,000.

F. Your company has made progress and completed 50% of the original works (earned value) in 6 Months' time.

G. The weather is ideal for construction - the expectation, based on previous weather records of the area, had been that up to 10% of the time could be lost because of adverse weather. This has been built into the contract price by your company. As at end of 6 months there has been no claim for EOT in respect of inclement weather.

H. Expenditure Profile (AUD in thousands)

Month

1

2

3

4

5

6

7

8

9

10

11

12

Planned

50

100

120

120

120

130

130

130

120

120

100

50

Actual

65

160

235

120

130

130

 

 

 

 

 

 

Note:

1. Actual cost during first month includes claim for resolving errors.

2. Actual cost during second month includes claim for dealing with object of antiquity.

3. Actual cost during third month includes claim for change in design for seating material.

EXAM QUESTIONS -

Question 1: Project Risk and Communication

a. Your company has been requested by Client to prepare and submit a communication management plan. Prepare a communication management plan involving site management team and client's team and stakeholders.

b. Client Project Manager prepared a project risk matrix for the project to prepare the initial project budget. Prepare a project risk for this project.

Question 2: Application of AS 4000

a. AS4000 details specific lines of communication for the effective processing of all progress payments (Monthly). Detail this process as outlined by AS4000, specifically identifying all relevant clauses that authorise the process. Explain security of payment act and its application in your claim.

b. Explain how your company submitted the claims for dealing with ambiguities and errors in the documents with relevant clauses from AS 4000.

c. Your company decided to make 'Claims for Variation' for the additional works arising from the re-design of the seating. Your claim should include possible surplus material or other alternative ways to deal with your order. What is the relevant clause under which Superintendent must have issued the direction to change the seating material? Explain with reasons.

d. Explain how your company dealt with discovery of 'object of antiquity' and how the Superintendent dealt with the claims for additional cost and time.

e. Your company noticed that the bolts shown on the drawings to fix the seating's were specified as galvanized iron bolts. Your company advised the Client that stainless steel bolts would be appropriate to avoid corrosion. Superintendent is considering your company's suggestion. Explain how the Superintendent and your company go about implementing the change of material for bolt.

Question 3: Earned Value Analysis

a. Based on the information provided in section H and other sections under "Further Information" carry out earned value analysis at the end of 6th month and calculate PV; EV; AC; CV; SV; CPI, SPI; BAC.

b. Estimate the cost at completion (EAC) using different methods;

I. If the CPI is expected to be the same for the remainder of the project,

II. If future work will be accomplished at the planned rate; and

III. If both the CPI and SPI influence the remaining work;

Question 4: Report

a. Prepare a draft monthly report to the client detailing the status of the project as at the end of 6th month.

Question 5 : Estimating VOWD (Value of Work Done) and Accruals

In a water pipeline project, following information has been provided to the Contract administrator.

Contract Scope: Procure, deliver, install and test 3 Km long 300mm dia pipeline from point A to point B as shown in the drawings and specification.

Contract period: 8 Months

Bill of Quantities

Description

Qty

Unit

Rate

Currency

Amount (USD)

Amount (AUD)

Procurement and delivery of 300mm dia pipes at site

3000

M

200

USD

600,000

 

Excavate trench and lay the pipe as specified.

3000

M

120

AUD

 

360,000

Testing of pipeline as specified

3000

M

30

AUD

 

90,000

Rates are inclusive of overheads and profit.

At the end of 4th month into the project,

  • 30% of pipes have been delivered to the site and accepted by the Superintendent as complying with the specification.
  • Contractor has laid 20% of the pipes and tested 50% of the laid pipes.
  • Invoices for 20% of delivery of pipes (3KM total); 10% of pipe in place; 0% for testing have been paid at the end of 3rd month.

Exchange rate for the end of 3rd month; 1AUD = 0.75 USD as paid in invoices.

Exchange rate for the end of 4th month (as provided by finance department); 1AUD = 0.80 USD

a. Estimate the VOWD (in AUD) as at end of 4th month and accrual (accounting) (in AUD).

Attachment:- Assignment File.rar

Other Engineering, Engineering

  • Category:- Other Engineering
  • Reference No.:- M92828556
  • Price:- $50

Priced at Now at $50, Verified Solution

Have any Question?


Related Questions in Other Engineering

Register design a cpu register is simply a row of

Register design A CPU register is simply a row of flip-flops (i.e. SR, JK, T, etc) put side by side in an array to make the size of register required. For example, an 8 bit register has 8 flip-flops side by side for stor ...

A detailed review of spatial modulation and simulation

A Detailed Review of Spatial Modulation and Simulation Learning Outcomes a. Learn how to model mobile communication channels d. Discern knowledge development and directions on the recent advances in 4G to the research pr ...

Mine safety amp environmental engineering assignment -part

Mine Safety & Environmental Engineering Assignment - Part 1 - Questions 1. Occupational health and safety is the primary factor that needs to be considered in the mining industry. Discuss this statement. 2. Define the fo ...

Projectflow processing of liquor in a mineral refining

Project Flow Processing of Liquor in a Mineral Refining Plant The aim of this project is to design a flow processing system of liquor (slurry) in a mineral (aluminum) refining plant. Aluminum is manufactured in two phase ...

Learning outcomes evaluate multiuser communication and

Learning Outcomes Evaluate multiuser communication and resource sharing techniques; Apply the techniques of, and report on, digital communication applications using Matlab and hardware devices. Assignment Description The ...

Operations engineering assignment -please select only one

Operations Engineering Assignment - Please select only one of the following case studies for your assignment: CASE A. Tesla Motors Tesla is an innovative manufacturer that designs, assemble and sells fully electric vehic ...

Select a risk problem from the list below and prepare a

Select a risk problem from the list below and prepare a risk management plan in accordance with AS/NZS ISO 31000:2009. Please ensure that: - Establish the context clearly, in accordance with the Standard; - Define your s ...

Engineering materials term paper assignment -conduct a

ENGINEERING MATERIALS TERM PAPER ASSIGNMENT - Conduct a thorough literature search and write a 15-20 page technical review paper on the evolution of the engineering materials used in the manufacturing of any one of the f ...

Task 1using the lab kit design a circuit for the processor

Task 1: Using the lab kit, design a circuit for the processor to control the output of a connected 7-segment LED display device. You will be provided with a standard common anode 7-segment display of the type FND-507 (or ...

Control theory - lab reportsfor experiments 1 to 4 you must

Control Theory - Lab Reports For experiments 1 to 4 you must undertake the following: a) At the start of each section (including the pre-lab activities) there are a number learning outcomes. That is, what students should ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As