Q1. Which of the following factors does NOT directly influence the workability of fresh concrete?

1. Exposure classification

2. Aggregate shape

3. Level of hydration

4. Cement content

5. Water content

Q2. What particle shapes are considered desirable for aggregates used in a concrete mix?

1. Angular and elongated

2. Rounded, irregular and angular

3. Irregular and elongated

4. Rounded, flaky and elongated

Q3. Which of the following items is NOT one of the key components used in making Portland cement?

1. Fly ash

2. Calcium carbonate

3. Silica

4. Iron Oxide

5. Alumina

Q4. Which of the following items is included in the cement making process, to control the rate at which the cement hydrates when mixed with water?

1. Alumina

2. Gypsum

3. Limestone

4. Magnesium

Q5. Is the following statement true or false?

Generally, if water is drinkable, it is suitable for making concrete?

1. True

2. False

Q6. You are a local government Engineer responsible for the design and construction of a footpath and bikeway in the local parklands. Your design calculations indicate a requirement for 25 MPa reinforced concrete. Soil tests show the parklands contain non-aggressive soils, and you will not be using a membrane under the concrete. (Your footpath will not be submerged in water.)

Using the attached tables, calculate the Target Strength in MPa based on the minimum requirement for Characteristic Strength considering both strength and durability.

(Round your answer to one decimal place. Do not include the MPa unit or any spaces or commas.)

Table 1: Minimum characteristic strength for durability

Exposure classification

Minimum characteristic strength fc' (MPa)

A1

20

A2

25

B1

32

B2

40

C

50

 

Table 2: Assumed standard deviation

Grade designation

Characteristic strength MPa

Assumed standard deviation MPa

Standard grades

25

25

4.8

32

32

5.34

40

40

5.9

50

50

6.2

Flexural grades

F2.5

2.0

0.5

F3.5

2.5

0.5

Indirect-tensile grades

IT2.0

2.0

0.5

IT2.5

2.5

0.5

Table 3: Exposure classification table (attached)

Q7. Your engineering ?rm has been awarded a contract to replace an existing timber bridge with a new concrete bridge over a river crossing in central Queensland. You will act as the onsite Project Engineer for the construction of the bridge piers. These piers will be submerged during the wet season and above water level during the dry season.

Using the attached tables, calculate the Target Strength in MPa based on the minimum requirement for Characteristic Strength for durability.

(Round your answer to one decimal place. Do not include any spaces or commas.)

Q8. A concrete retaining wall is being built as part of the construction of an underground car park below a new high-rise development. The Characteristic Strength is 40Mpa. Using the attached tables, calculate the water/cement ratio for use in the concrete mix design. (Note: Target strength should be used as the 28-day compressive strength)

(Round your answer to two decimal places. Do not include any spaces or commas.) Table 1: Assumed standard deviation

Q9. The reinforced concrete base slab for a single storey residential house is to be constructed. The characteristic strength is 25MPa. Using the attached tables, calculate the water/cement ratio to be used to design the concrete mix.

(Note: Target strength should be used as the 28-day compressive strength) (Round you answer to two decimal places. Do not include any spaces of commas.)

Q10. Using the following known information, what is the aggregate/cement ratio to be used in the concrete mix design based on a water/cement ratio of 0.6?

Nominal aggregate size: 40 mm

Aggregate shape: irregular gravel

Slump: 160 mm

Grading curve: 3

(Round your answer to one decimal place. Do not include any spaces or commas.)

Q11. Using the following known information, what is the aggregate/cement ratio to be used in the concrete mix design based on a water/cement ratio of 0.7:1?

Nominal aggregate size: 20 mm

Aggregate shape: crushed rock

Slump: 40 mm

Grading curve: 4

(Round your answer to one decimal place. Do not include any spaces or commas.)

Q12. A concrete design has been completed for an upcoming project, with the following parameters:

  • Water/cement ratio is 0.60
  • Aggregate/cement ratio is 3.6

The total aggregate proportions in the blend are as follows:

  • 20 mm aggregate 20%
  • 10 mm aggregate 65%
  • Sand 15%

Calculate the total mass of concrete mix (in kg) using these proportions, based on a 50 kg bag of cement.

(Round your answer to one decimal place. Do not include the kg unit or any spaces or commas.)

Q13. You have an approved mix design for a concrete pour that will be taking place tomorrow morning. You are in an arid zone of Queensland and have not had any rainfall for over 2 months. Your 20 mm aggregate has been in stockpile for a number of weeks and is now very dry. Your mix design quantities for a 1 m3 batch of concrete, based on the Saturated Surface Dry condition of the aggregate are as follows:

Cement 428 kg

Water 201.2 kg

20 mm aggregate 1061.4 kg

Sand 650.6 kg

Total 2341.2 kg

The soil laboratory have taken samples from the aggregate stockpiles, and found that the actual moisture content of the 20 mm aggregate is 1.8 %, and the water absorption is 2.1 %. The sand is in SSD condition.

What is the total quantity of water in kg to be included in the concrete mix, after the adjustment for aggregate moisture content?

(Round your answer to one decimal place. Do not include the kg unit or any spaces or commas.)

Attachment:- Assignment File.rar

Other Engineering, Engineering

  • Category:- Other Engineering
  • Reference No.:- M92821063

Have any Question?


Related Questions in Other Engineering

Mine safety amp environmental engineering assignment -part

Mine Safety & Environmental Engineering Assignment - Part 1 - Questions 1. Occupational health and safety is the primary factor that needs to be considered in the mining industry. Discuss this statement. 2. Define the fo ...

Conceptual design of forced-free-mixed convection

Conceptual Design of Forced-Free-Mixed Convection Experiment This assessment is to be completed individually. 1. Learning Outcomes: - Develop a basic ability to conceptually design an experimental apparatus - Use theory ...

Q 1a discontinuity is found fully developed from the toe to

Q. 1 A discontinuity is found fully developed from the toe to the bench surface on a 15 m high slope, slope angle 65°. The discontinuity (frictional angle 32° and cohesion 20 kN/m2) is planar and its strike is parallel t ...

Question 1 define rock mechanics discuss the main

Question 1 . Define rock mechanics. Discuss the main objectives of the application of rock mechanics in mining. Question 2. Define stress. Draw a diagram and define the normal and shear stress by resolving the resultant ...

Engineering analysis homework -for every problem provide

Engineering Analysis Homework - For every problem, provide The MATLAB script/function files that solve the problems. Problem 1: Write a script that solves the problem. For (c), show results of the evaluation of every ind ...

Task 1using the lab kit design a circuit for the processor

Task 1: Using the lab kit, design a circuit for the processor to control the output of a connected 7-segment LED display device. You will be provided with a standard common anode 7-segment display of the type FND-507 (or ...

Assignment 11 what is the purpose of ore reserve and

ASSIGNMENT 1 1. What is the purpose of ore reserve and resource estimation? Why are resource and reserve estimates important to the mining industry? 2. What is meant by ore? What is meant by the term waste? How is the di ...

Register design a cpu register is simply a row of

Register design A CPU register is simply a row of flip-flops (i.e. SR, JK, T, etc) put side by side in an array to make the size of register required. For example, an 8 bit register has 8 flip-flops side by side for stor ...

Engineering analysis assignment -for every problem provide

Engineering Analysis Assignment - For every problem, provide The MATLAB script/function files that solve the problems. Problem 1: Plot the function f(t) = (x+5) 2 /(4+3x 2 ) for -3 ≤ x ≤ 5. using plot command. Use the ar ...

Part 1configure verify and troubleshoot wan links and ip

Part 1 Configure, verify and troubleshoot WAN links and IP services Answer to all questions below: 1. What is the name of the Safe Work Australia code of practise that provides guidance on how to manage the risks of elec ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As