A factory wants the power company to run a special line to the plant. The power company is located 1000 meters down a river on the opposite bank. Ground lines cost $20 per meter. The river is 500 meters wide and underwater line will cost M (M> 1) times as much per meter as the above ground line. Since the factory owns the riverfront property on both sides of the river all the way to the power plant, you may choose where and how the line should cross the river.

1- Find in terms of M all paths that will minimize the cost and what the minimum cost is. Be sure to describe your paths clearly. See diagram.

2- If M =50 give the minimum cost and the best path.

3- If M =2 give the minimum cost and the best path.

4- If M =1.05 give the minimum cost and the best path.

2170_Riverfront property.jpg

Engineering Mathematics, Engineering

  • Category:- Engineering Mathematics
  • Reference No.:- M91629388
  • Price:- $20

Priced at Now at $20, Verified Solution

Have any Question?


Related Questions in Engineering Mathematics

Assignment - lp problemsthe data for all the problems in

Assignment - LP problems The data for all the problems in this HW are included in the LP_problems_xlsx spreadsheet. Problem 1 - Cash Planning A startup investment project needs money to cover its cash flow needs. At the ...

Question a suppose that you are given an instance of the

Question : (a) Suppose that you are given an instance of the MST problem on a graph G, with edge weights that are all positive and distinct. Let T be the minimum spanning tree for G returned by Kruskal's algorithm. Now s ...

Problem -consider a closed convex set x sub rd a function h

Problem - Consider a closed convex set X ⊂ R d , a function H : X x Ξ ι→ R d , and a deterministic nonnegative sequence {α n } such that n=0 ∑ ∞ α n = ∞ and n=0 ∑ ∞ (α n ) 2 = ∞. Consider an inner product (·, ·) on R d , ...

Question 1 - many spas many componentsconsider 4 types of

Question 1 - Many spas, many components Consider 4 types of spa tub: Aqua-Spa (or FirstSpa, or P1), Hydro-Lux (or SecondSpa, or P2), ThirdSpa (or P3) and FourthSpa (or P4), with the production of products P1, ..., P4 in ...

Problem 1given a sequence xn for 0lenle3 where x0 1 x1 1

Problem # 1: Given a sequence x(n) for 0≤n≤3, where x(0) = 1, x(1) = 1, x(2) = -1, and x(3) = 0, compute its DFT X(k). (Use DFT formula, don't use MATLAB function) Use inverse DFT and apply it on the Fourier components X ...

Question suppose that g is a directed graph in class we

Question : Suppose that G is a directed graph. In class we discussed an algorithm that will determine whether a given vertex can reach every other vertex in the graph (this is the 1-to-many reachability problem). Conside ...

Question a signal starts at point x as it travels to point

Question : A signal starts at point X. As it travels to point Y, it loses 8 dB. At point Y, the signal is boosted by 10 bB. As the signal travels to point Z, it loses 7 dB. The dB strength of the signal at point Z is -5 ...

Assignment -1 let t and or 0 1 be a boolean algebradefine

Assignment - 1. Let (T, ∧, ∨,', 0, 1) be a Boolean Algebra. Define ∗ : T × T → T and o : T × T → T as follows: x ∗ y := (x ∨ y)' x o y := (x ∧ y)' (a) Show, using the laws of Boolean Algebra, how to define x ∗ y using on ...

Question what is the signed binary sum of 1011100 and

Question : What is the signed binary sum of 1011100 and 1110101 in decimal? Show all of your work. What is the hexadecimal sum of 9A88 and 4AF6 in hexadecimal and decimal? Show all of your work.

I have these questions for a homework assignment and have

I have these questions for a homework assignment and have to show work. This works with MIPS coding language and is the class Introduction to Computer Architecture. 1. Find the 2's complement representation (in 32-bit he ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As