1.0 GENERAL

The structural design shall be carried out in accordance with the relevant and applicable Australian Standards.

2.0 SCOPE

This document defines the preliminary requirements for the structural steel design for a pump station shed in Telfer, Western Australia.

The shed structure is required to provide shelter for a small water treatment pump station. In order to carry out maintenance on the pumps, a suspended monorail with a 4-tonne lifting capacity is required along the centreline of the structure.

Prepare a design for a pump station shed having a clearance opening width of 6.2 m, an overall length of 18 m and clearance height to the underside of the monorail beam of 4.2 m. The roof is to be clad with Custom Orb sheeting. The sides and ends of the shed are not clad.

Design the following elements:
• The steel structural system, including major column and beam elements, bracing members, purlins and girts
• Major connections for the steel frame
• Base plate and anchor bolts
• Roof cladding

Justify all design decisions and elements.

Full design of the monorail beam is not required, however, it will be necessary to estimate the depth of the beam to ensure sufficient underside clearance is achieved.

The structure will be assumed to be assembled on a simple pad footing. Design of the footing is not part of the scope.

Capital cost economy is a key design consideration. The resulting design and arrangement ideally will be the most economical when considering materials, fabrication, transportation and site erection. Modularisation may reduce time and cost, and improve construction safety and should be considered.

Appropriate site construction cranes can be assumed to be available for the construction of the structure.

REFERENCES

Navisworks image of pump station equipment and surrounding features.

Sample structural drawings (demonstrating the level of detail required).

The portal frame design and design process are to be presented in an oral presentation. Accompanying calculations and structural drawings are to be submitted separately. Refer to Assessment and Feedback Specification for full details.

DESIGN LOADS

General

Design shall be performed as per the AS 1170 Parts 0, 1 and 2, except as specified below.

Load conditions shall be assessed based on Structure Importance Level 2.

Permanent Actions

Minimum weights of materials shall be as per AS/NZS 1170.1:2002 Tables A1 and A2.

Imposed Actions

Imposed actions shall be in accordance with AS/NZS 1170.1:2002.

Wind Actions

Wind actions shall be calculated in accordance with AS/NZS 1170.2:2011.

Load Combinations

Load combinations shall be assessed in accordance with AS/NZS 1170.0:2002.

The minimum robustness requirements of AS/NZS 1170.0 shall be complied with.

Soil Properties

Assume the structure to be constructed on sound, firm material. The footing design is not part of the scope.

PLATE WORK AND STRUCTURAL STEELWORK

6.1 General

Design shall be in accordance with AS 4100.

6.2 Materials

Hot rolled steel sections shall be grade 300 to AS 3679.1.

Plates shall be grade 300 to AS 3678.

6.3 Transportation

The transport envelope requirements for items fabricated off-site shall be considered.

Maximum shipping width on West Australian roads is 3.5 m, without permits.

Greater than 5.5 m, escorts and police clearance is required and time added to organise.

A maximum height of 2.5 m from the top of the transport trailer.

Shipping containers can also be considered.

7.0 SERVICEABILITY

The design working life of the pump station shed shall be 50 years.

The maximum serviceability deflection (vertical) of the structure supporting the monorail beam shall be span/500.

8.0 SOFTWARE

The structural frame analysis may be performed using SpaceGass or Multiframe.

Other Engineering, Engineering

  • Category:- Other Engineering
  • Reference No.:- M91609973

Have any Question?


Related Questions in Other Engineering

Assignment 11 what is the purpose of ore reserve and

ASSIGNMENT 1 1. What is the purpose of ore reserve and resource estimation? Why are resource and reserve estimates important to the mining industry? 2. What is meant by ore? What is meant by the term waste? How is the di ...

Introduction to engineering design assignment -

Introduction to Engineering Design Assignment - Drafting Question 1 - Field notes and traverse drawing may be an outdated form of keeping and presenting information on the position of features on a site. Modern electroni ...

A detailed review of spatial modulation and simulation

A Detailed Review of Spatial Modulation and Simulation Learning Outcomes a. Learn how to model mobile communication channels d. Discern knowledge development and directions on the recent advances in 4G to the research pr ...

Part 1configure verify and troubleshoot wan links and ip

Part 1 Configure, verify and troubleshoot WAN links and IP services Answer to all questions below: 1. What is the name of the Safe Work Australia code of practise that provides guidance on how to manage the risks of elec ...

Assignment 11 what is the purpose of ore reserve and

ASSIGNMENT 1 1. What is the purpose of ore reserve and resource estimation? Why are resource and reserve estimates important to the mining industry? 2. What is meant by ore? What is meant by the term waste? How is the di ...

Assignment -problem 1 - given is the lcc difference

Assignment - Problem 1 - Given is the LCC difference equation that represents some LTI system: y(n) - ¾y(n-1) - ¼y(n-2) = x(n) + x(n-1)   a) Find the impulse response of the system (solve the LCCDE). b) Draw a block diag ...

Question - show that the zero-point energy of a simple

Question - Show that the zero-point energy of a simple harmonic oscillator does not contribute to its entropy or heat capacity, but does contribute to its energy and Helmholtz function.

Engineering analysis assignment -for every problem provide

Engineering Analysis Assignment - For every problem, provide The MATLAB script/function files that solve the problems. Problem 1: Plot the function f(t) = (x+5) 2 /(4+3x 2 ) for -3 ≤ x ≤ 5. using plot command. Use the ar ...

Question 1 define rock mechanics discuss the main

Question 1 . Define rock mechanics. Discuss the main objectives of the application of rock mechanics in mining. Question 2. Define stress. Draw a diagram and define the normal and shear stress by resolving the resultant ...

This is your second design assignment this assignment

This is your second design assignment. This assignment requires you to design a complex state machine. You are designing a digital alarm clock. There are various designs you can attempt. More complex designs are worth mo ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As