1. When buyers purchase new houses, they are frequently responsible for installing their own landscaping. The PERT/CPM network shown in the accompanying figure represents a landscaping project for a new home in Jackson, Mississippi. The times are in days.

a. What are the expected completion time and the critical path for the landscaping project?
b. What are the earliest and latest start and finish times for activity C?
c. How long can activity A be delayed without delaying the minimum completion time of the project?
d. If activities A, C, and F are each delayed three days, how long will the landscaping project be delayed?

2. Virtual Golf, Inc. (VGI) is contemplating introducing a new virtual reality golf experience that would, if successful, be located in many amusement parks and entertainment centers throughout the country. If the project gets the "go ahead", it must be completed within 20 weeks (140 days) to be installed in the Mall of America in Bloomington, Minnesota, for test marketing. The table below gives cost and time estimates (in days) for the activities of the project.

Activity

Immediate Predecessors
A. Feasibility study
-
B. Input from golf professionals
A
C. Conceptual design
B
D. Professional Feedback
C
E. Final design
D
F. Manufacture of unit
E
G. Software development
E
H. Equipment/software coordination
F,G
I. In-house unit testing
H
J. Operator training
H
K. Construct unit in mall store
I, J
L. Testing of unit in mall store
K

Activity
Normal Days
Crash Days
Normal Cost
Crash Cost
A. Feasibility study
14
12
$15,000
$17,500
B. Input from golf professionals
14
11
$55,000
$64,000
C. Conceptual design
8
8
$50,000
$50,000
D. Professional Feedback
12
9
$40,000
$50,000
E. Final design
18
16
$50,000
$65,000
F. Manufacture of unit
20
16
$40,000
$55,000
G. Software development
14
10
$55,000
$70,000
H. Equipment/software coordination
21
19
$25,000
$65,000
I. In-house unit testing
10
8
$25,000
$32,000
J. Operator training
21
21
$50,000
$50,000
K. Construct unit in mall store
9
6
$25,000
$40,000
L. Testing of unit in mall store
15
10
$10,000
$40,000

a. What is the minimum project cost that will allow the project to be completed within 21 weeks?

b. What is the minimum project cost that will allow the project to be completed within 19 weeks?

3. Consider the project facing VGI in Problem 2. If the company allocated a maximum of $450,000 to this project, what is the minimum time it would take to complete the project?

4. Universal Travel is planning to move its headquarters from Cincinnati to Columbus, Ohio. The table below details the steps that must be taken. Times are in weeks.
Immediate Predecessors
Optimistic Time
Most Likely Time
Pessimistic Time
A. Select a site
-
8
12
20
B. Refurbish building
A
9
10
12
C. Determine which staff will transfer
-
2
2
3
D. Hire staff replacements in Columbus
C
3
6
8
E. Pack boxes in Cincinnati
A,C
1
2
5
F. Move equipment
B
2
3
4
G. Move files
B,E
1
2
5
H. Set up equipment/files in Columbus
F,G
3
4
5
I. Occupancy
D,H
5
6
10

a. What is the expected completion time of the project? What is the critical path?

b. What is the probability the project will be completed within 36 weeks?

c. Suppose Universal will be charged for both sites if it is not completely moved in within 36 weeks. This will cost the company $5,000.

The company is considering two options to improve its chances to meet this deadline.
- For $1,000, additional movers can be hired to move the files. This would cut each of the three time estimates for that activity in half.
- Additional movers can be hired for $1,000 to assist in moving the equipment. This would cut the three time estimates for that activity by one week each.
The company can pursue either OR BOTH of these options. What is your recommendation?

Computer Engineering, Engineering

  • Category:- Computer Engineering
  • Reference No.:- M91379334
  • Price:- $40

Guranteed 36 Hours Delivery, In Price:- $40

Have any Question?


Related Questions in Computer Engineering

Remember all of the following steps when showing that a

Remember all of the following steps when showing that a problem D is NPcomplete: 1. Show that D is in NP by briefly explaining how to quickly verify a solution to it. 2. Choose another problem Q that is known to be NP-ha ...

Identify at least two 2 factors that have led to the

Identify at least two (2) factors that have led to the explosive growth of digital crime over the past a few decades. Next, describe the most common forms of digital crime, and give your opinion as to why those forms you ...

Stereotypes are useful toolsthey provide a shorthand way of

Stereotypes are useful tools. They provide a shorthand way of dealing with differences and allowing us to categorize how people think about things and interact with our world. Explain the positive effects of stereotypes ...

Question suppose that an attack would do 200000 in damage

Question : Suppose that an attack would do $200,000 in damage and has a 25% annual probability of success. Spending $15,000 per year on Countermeasure A would reduce the damage of a successful attack by 50%. a) Do a risk ...

What are some of the uses of bayes theorem as in what type

What are some of the uses of bayes' theorem. As in what type of problems could I come across in a Biostatistics quiz

The national sporting goods association nsga conducted a

The National Sporting Goods Association (NSGA) conducted a survey of the ages of individuals that purchased skateboarding footwear. The ages of this survey are summarized in the following relative frequency distribution. ...

You are the security manager for a mid-sized company 3000

You are the security manager for a mid-sized company (3,000 to 5,000 employees). Your company has determined that confidentiality (or privacy) and data integrity are the security services you must provide to your work fo ...

Explain the difference between penetration tests and

Explain the difference between penetration tests and security tests. Emphasize that this book will explain things from a security testing perspective.

How does a database that is associated with a mobile device

How does a database that is associated with a mobile device and with mobile apps differ from a database that is stored and created using a more traditional application and server?

A sequence of natural numbers a1 a2 an is said to be a

A sequence of natural numbers (a 1 , a 2 , ..., a n ) is said to be a degree sequence if there exists an undirected graph on n vertices {v 1 , v 2 , ..., v n } such that the degree of v i  is a i  for each i = 1, 2, ..., ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As